Chapter 08 - Scheduling Resources and Costs
Chapter 08 Scheduling Resources and Costs Multiple Choice Questions
1. Delaying noncritical activities to lower peak demand on resources is known as resource A. Shiting !. "ectiveness C. #anipulating D. Resource smoothing ". Allocation
$. % resources are not ade&uate to meet peak demands' the resulting reschedule is termed A. Resource-constrained scheduling !. (ime-constrained scheduling C. #andatory leveling D. )ro*ect resource ad*ustment ". Allocation
+. ,hich o the ollowing is a potential conse&uence o ailing to schedule limited resources A. Costly activity delays !. Costly pro*ect delays C. Diiculty in taking &uick corrective action D. !oth A and ! are correct ". A' !' and C are all correct
. ,hen developing a new sotware package' the sotware must /e designed' the code must /e written' and the code must /e tested. (his is an eample o a constraint. A. )hysical !. (echnical C. Resource D. Schedule ". (ime
8-1
Chapter 08 - Scheduling Resources and Costs
2. ,hich o the ollowing is not one o the types o pro*ect constraints A. )hysical !. (echnical C. Resource D. (ime ". All o these are types o pro*ect constraints
3. Sam the pro*ect engineer has /een scheduled to run the product system test at the same time he is to /uild a marketing prototype. (his is an eample o a constraint. A. )hysical !. (echnical C. Resource D. Scheduling ". (ime
4. Susan is to conduct environmental testing /ut the cham/er cannot hold all the e&uipment that she wants to test. (his is an eample o a constraint. con straint. A. )hysical !. (echnical C. Resource D. Scheduling ". (ime
8. All o the ollowing are kinds o resource constraints ecept A. #aterials !. )eople C. "&uipment D. %normation ". All o the a/ove are resource constraints
8-$
Chapter 08 - Scheduling Resources and Costs
2. ,hich o the ollowing is not one o the types o pro*ect constraints A. )hysical !. (echnical C. Resource D. (ime ". All o these are types o pro*ect constraints
3. Sam the pro*ect engineer has /een scheduled to run the product system test at the same time he is to /uild a marketing prototype. (his is an eample o a constraint. A. )hysical !. (echnical C. Resource D. Scheduling ". (ime
4. Susan is to conduct environmental testing /ut the cham/er cannot hold all the e&uipment that she wants to test. (his is an eample o a constraint. con straint. A. )hysical !. (echnical C. Resource D. Scheduling ". (ime
8. All o the ollowing are kinds o resource constraints ecept A. #aterials !. )eople C. "&uipment D. %normation ". All o the a/ove are resource constraints
8-$
Chapter 08 - Scheduling Resources and Costs
5. Sam is trying to order the concrete con crete needed to continue his pro*ect. 6owever' the supplier won7t /e a/le to deliver it until net week. (his is an eample o a constraint. A. ,orking capital !. )eople C. "&uipment D. %normation ". #aterials
10. A special truck that eorge needs on his pro*ect has /een scheduled on another pro*ect. (his is a constraint. A. ,orking capital !. )eople C. "&uipment D. %normation ". #aterials
11. #ost o the scheduling methods availa/le today re&uire the pro*ect manager to classiy the pro*ect as either constrained or constrained. A. (ime' &uality !. 9uality' resource C. Cost' time D. 9uality' cost ". (ime' resource
1$. Regina7s /oss has told her that her pro*ect is very important. % the critical path is delayed' she will /e given whatever she needs to get it /ack on schedule. 6er pro*ect is constrained. A. (ime !. 9uality C. Cost D. )erormance ". Resource
8-+
Chapter 08 - Scheduling Resources and Costs
1+. %n reviewing the status o her pro*ect with top management' Shirley was told that there only were two programmers that she could use or her pro*ect. 6er pro*ect is constrained. A. (ime !. 9uality C. Cost D. )erormance ". Resource
1. All resource leveling techni&ues involve A. Delaying noncritical activities !. Delaying critical activities C. :sing negative slack D. !oth A and C are correct ". A' !' and C are all correct
12. Scheduling time-constrained pro*ects ocuses on resource A. Demands !. %ncreases C. Assumptions D. :tili;ation ". All are correct
13. (he most widely used approach to apply heuristics' which have /een ound to consistently minimi;e pro*ect delay over a large variety v ariety o pro*ects is the A. )arallel method !. Resource method C. #aterials D. !oth A and C are correct ". A' !' and C are all correct
8-
Chapter 08 - Scheduling Resources and Costs
14. Resource leveling can provide A.
18. =an is trying to reallocate resources in a time-constrained pro*ect to create smoother resource utili;ation with a low level o risk. She shou ld move to activities with the A. Smallest duration !.
15. %n a resource-constrained pro*ect' which o o the ollowing is most likely to /e changed A. (he completion date !. (he /udget C. )ro*ect &uality D. !oth A and ! are e&ually likely ". A' !' and C are all e&ually likely
$0. %n a resource-constrained pro*ect' the irst priority in assigning resources is usually given to activities with the A. Smallest duration !.
8-2
Chapter 08 - Scheduling Resources and Costs
$1. %n a resource-constrained pro*ect the second priority in assigning resources is usually given to activities with the A. Smallest duration !.
$$. (he word 6euristics means A. Resource constraints !. >lei/ility C. (he critical path changed D. )arallel activities /ecome se&uential ". Rule o thum/
$+. Splitting an activity creates the ollowing situation? A. #ore people working on the same activity !. (here are possi/le startup and shutdown costs C. A resource may /e moved rom one activity to another and then /ack D. !oth ! and C are correct ". A' !' and C are all correct
$. (he :.S. >orest Service @snapshot rom practice@ illustrated the importance o A. (ime constraints !. Resource constraints C. Cost constraints D. !oth ! and C are correct ". A' !' and C are all correct
8-3
Chapter 08 - Scheduling Resources and Costs
$2. #ore common pro/lems associated with managing multipro*ect resources include all o the ollowing ecept A. %neicient resource utili;ation !. Delays in one pro*ect cause delays in other pro*ects C. Reducing @downtime@ created /y lack o tasks to perorm D. Resource /ottlenecks ". All o these are common pro/lems
$3. ,hen a company will reduce the num/er o pro*ects they have to manage internally to only core pro*ects and send noncritical pro*ects to contractors and consulting irms this is called A. utsourcing !. Redistri/ution o pro*ects C. )ro*ect allocation D. (ask sharing ". !oth ! and D are correct
$4. ,hich o the ollowing is not one o the more common pro/lems associated with scheduling multipro*ect resources A. verall schedule slippage !. %neicient resource utili;ation C. Resource /ottlenecks D. !oth A and C are correct ". A' !' and C are all correct
$8. %n a resource-constrained pro*ect the third priority in assigning resources is usually g iven to activities with the A. Smallest duration !.
8-4
Chapter 08 - Scheduling Resources and Costs
$5. %n the !otanical arden eample' which o the ollowing was used to solve the resource pro/lem A. Resource allocation !. Smoothing resource demand C. (he parallel method D. !oth A and C are correct ". A' !' and C are all correct
+0. )ro*ect /udgets are developed /y time-phasing which o the ollowing A. Resource schedules !. ,ork packages C. (he network diagram D. !oth A and C are correct ". A' !' and C are all correct
+1. A pro*ect /udget report is showing our pro*ect as spending B+2'000 against a /udgeted amount o B0'000. ,hich o the ollowing is true A. ,e are spending less than we should or the pro*ect !. ,e are doing a good *o/ managing the pro*ect C. ,e should check to see i all the /ills have /een paid D. !oth A and ! are correct ". ,e can7t /e sure how the pro*ect is going
Fill in the Blank Questions
+$. Delaying noncritical activities to lower peak demand and' thus' increase resource utili;ation is called leveling.
++. An constraint addresses the se&uence in which pro*ect activities must occur.
8-8
Chapter 08 - Scheduling Resources and Costs
+. 6aving one person responsi/le or perorming several activities' all due at the same time' is an eample o an constraint.
+2. (rying to renovate a ship compartment that is too small or more than one person is an eample o an constraint.
+3. A shortage o programmers to write sotware is an eample o an type o resource constraint.
+4. (he shortage o computer chips to produce a circuit /oard is an eample o an type o resource constraint.
+8. % three copiers are needed to produce a inal report on time and only two are availa/le' the pro*ect is acing an type o resource constraint.
+5. 6ector wants to /ring on another programmer to work on the pro*ect /ut the company does not have anyone who has the needed skills. 6ector7s pro*ect is acing an constraint.
0. %n order that the new product is on the shel or the Christmas /uying season' the development o the new product would /e classiied as an constrained pro*ect.
8-5
Chapter 08 - Scheduling Resources and Costs
1. !eth has two engineers assigned to her pro*ect and cannot get any more even i it means slipping the due date on her pro*ect. She is managing an constrained pro*ect.
$. All leveling techni&ues delay noncritical activities /y using to reduce peak demand.
+. Scheduling activities in a constrained pro*ect typically has as the top heuristic rule.
. (he is the most widely used approach to apply heuristic rules to scheduling activities in a constrained pro*ect.
2. ,hen using the scheduling techni&ue' the work in an activity is interrupted to work on another activity and is then resumed at a later point in time.
3. %n scheduling resource-constrained pro*ects' are typically used rather than optimum mathematical solutions.
4. %n scheduling terms' constrained means that pro*ect duration is ied and resources are lei/le.
8-10
Chapter 08 - Scheduling Resources and Costs
8. %n scheduling terms' constrained means that a speciic resource is ied and the duration o the pro*ect is lei/le.
5. Start-up and shutdown costs are ma*or considerations when using the scheduling techni&ue.
20. (o deal with pro/lems related to having several concurrent pro*ects' companies are creating to oversee the scheduling o resources across multiple pro*ects.
21. #any companies are using rom contractors and consultants as a means o dealing with the peaks and valleys o resource allocation among pro*ects.
2$. (he is the most widely used approach to apply heuristics in resourceconstrained pro*ects.
2+. (he a/ility to more eiciently manage the e//s and lows o pro*ect work is one o the ma*or driving orces /ehind today.
2. ,ithout a time-phased good pro*ect schedule and cost control are impossi/le.
8-11
Chapter 08 - Scheduling Resources and Costs
22. A pro*ect cost /aseline is also called .
True / False Questions
23. (he se&uence o 1 pour oundation' $ /uild rame' and + cover roo is a type o physical constraint. (rue >alse
24. (oo many parallel activities or one individual are an eample o a resource constraint. (rue >alse
28. A pro*ect that is not resource-constrained is time-constrained. (rue >alse
25. Resource leveling is only used on pro*ects which are resource-constrained. (rue >alse
30. Resource !ottlenecks are one o the three more common pro/lems encountered in managing multipro*ect resource schedules. (rue >alse
31. (he ina/ility to get more than two earth movers on a construction site at the same time is an eample o a physical constraint. (rue >alse
8-1$
Chapter 08 - Scheduling Resources and Costs
3$. (he most o/vious and important kind o resource constraint is a lack o materials. (rue >alse
3+. 6aving too ew programmers and too many engineers is an eample o a people resource constraint. (rue >alse
3. % a pro*ect needs one earth-mover si months rom now and the organi;ation has our such machines' there is no e&uipment resource constraint. (rue >alse
32. A lack o readily availa/le engineers is a technical constraint. (rue >alse
33. All pro*ects are usually either time-constrained or resource-constrained. (rue >alse
34. (o determine i a pro*ect is time-constrained or resource-constrained you would consult the pro*ect priority matri. (rue >alse
38. Scheduling time-constrained pro*ects ocuses on the optimal utili;ation o resources. (rue >alse
35. All leveling techni&ues delay noncritical activities /y using positive slack to smooth out the resource re&uirements. (rue >alse
8-1+
Chapter 08 - Scheduling Resources and Costs
40. Scheduling time-constrained pro*ects ocuses on resource utili;ation. (rue >alse
41. Scheduling resource-constrained pro*ects ocuses on completing the pro*ect as soon as possi/le under the given constraints. (rue >alse
4$. 6euristics are used in resource-constrained pro*ects to develop the optimal schedule. (rue >alse
4+. (he top priority in using heuristics to allocate scare resources is those activities with the smallest duration. (rue >alse
4. (he critical path in a resource-constrained schedule can /e a group o dis*ointed' unconnected activities. (rue >alse
42. Splitting is a scheduling techni&ue used to get a /etter schedule or /etter resource utili;ation. (rue >alse
43. ,ithout a time-phased /udget good pro*ect schedule and cost control are impossi/le. (rue >alse
44. #any companies are using outsourcing as a means or dealing with their resource allocation pro/lems associated with managing multipro*ect resources. (rue >alse
8-1
Chapter 08 - Scheduling Resources and Costs
Short Answer Questions
48. %dentiy and /riely descri/e the three types o pro*ect constraints.
45. ,hat is the dierence in pro*ect goals when using resource leveling on time-constrained pro*ects and using it on resource-constrained pro*ects
80. %dentiy the potential impacts o pro*ect constraints.
81. %dentiy and give an eample o the three types o resource constraints.
8-12
Chapter 08 - Scheduling Resources and Costs
8$. %dentiy and /riely descri/e the two classiications o scheduling pro/lems.
8+. ,hat are the disadvantages o resource leveling
8. ,hy would a pro*ect manager use heuristics rather than a mathematical solution to level resources
82. ,hat are the three most common heuristics in order o priority used to allocate resources to pro*ect activities
8-13
Chapter 08 - Scheduling Resources and Costs
83. Descri/e the parallel method or applying heuristics to the allocation o pro*ect resources.
84. ,hy should pro*ect managers /e cautious a/out using the splitting scheduling techni&ue
88. %dentiy and /riely discuss the three more common pro/lems encountered in managing multipro*ect resource schedules.
85. %dentiy and /riely descri/e the potential impacts o resource-constrained scheduling.
8-14
Chapter 08 - Scheduling Resources and Costs
50. % your pro*ect has spent B20'000 versus a /udget o B2'000 and it is a week ahead o schedule' is it a certainty that your pro*ect is doing well
8-18
Chapter 08 - Scheduling Resources and Costs
Chapter 08 Scheduling Resources and Costs Answer Eey
Multiple Choice Questions
1. Delaying noncritical activities to lower peak demand on resources is known as resource A. Shiting !. "ectiveness C. #anipulating D Resource smoothing ". Allocation % resources are ade&uate /ut the demand varies widely over the lie o the pro*ect' it may /e desira/le to even out resource demand /y delaying noncritical activities using slack to lower peak demand and' thus' increase resource utili;ation. (his process is called resource smoothing.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
$. % resources are not ade&uate to meet peak demands' the resulting reschedule is termed A Resource-constrained scheduling !. (ime-constrained scheduling C. #andatory leveling D. )ro*ect resource ad*ustment ". Allocation % resources are not ade&uate to meet peak demands' the late start o some activities must /e delayed' and the duration o the pro*ect may /e increased. (his process is called resourceconstrained scheduling.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
8-15
Chapter 08 - Scheduling Resources and Costs
+. ,hich o the ollowing is a potential conse&uence o ailing to schedule limited resources A. Costly activity delays !. Costly pro*ect delays C. Diiculty in taking &uick corrective action D. !oth A and ! are correct ! A' !' and C are all correct (he conse&uences o ailing to schedule limited resources are a costly activity and pro*ect delays usually maniest themselves midway in the pro*ect when & uick corrective action is diicult.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
. ,hen developing a new sotware package' the sotware must /e designed' the code must /e written' and the code must /e tested. (his is an eample o a constraint. A. )hysical B (echnical C. Resource D. Schedule ". (ime A network or a new sotware pro*ect could place the activities in the network' as a se&uence o 1 design' $ code' and + test. %n other words' you cannot logically perorm activity $ until 1 is completed' and so on. (he pro*ect network depicts technical constraints.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: &edim
8-$0
Chapter 08 - Scheduling Resources and Costs
2. ,hich o the ollowing is not one o the types o pro*ect constraints A. )hysical !. (echnical C. Resource D (ime ". All o these are types o pro*ect constraints % resources are not ade&uate to meet peak demands' the late start o some activities must /e delayed' and the duration o the pro*ect may /e increased. (he a/sence or shortage o resources can drastically alter technical constraints. %n rare situations' physical actors cause activities that would normally occur in parallel to /e constrained /y contractual or environmental conditions.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: &edim
3. Sam the pro*ect engineer has /een scheduled to run the product system test at the same time he is to /uild a marketing prototype. (his is an eample o a constraint. A. )hysical !. (echnical C Resource D. Scheduling ". (ime % one person must perorm all activities' the resource constraint re&uires the activities /e perormed in se&uence or series.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
8-$1
Chapter 08 - Scheduling Resources and Costs
4. Susan is to conduct environmental testing /ut the cham/er cannot hold all the e&uipment that she wants to test. (his is an eample o a constraint. A )hysical !. (echnical C. Resource D. Scheduling ". (ime Since space allows only one person to work at one time' all tasks have to /e perormed se&uentially this is a physical constraint.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Com%ter emonstration of Resorce(Constrained Schedling Level: "asy
8. All o the ollowing are kinds o resource constraints ecept A. #aterials !. )eople C. "&uipment D %normation ". All o the a/ove are resource constraints See list on pages $22-$24.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: #y%es of Resorce Constraints Level: "asy
8-$$
Chapter 08 - Scheduling Resources and Costs
5. Sam is trying to order the concrete needed to continue his pro*ect. 6owever' the supplier won7t /e a/le to deliver it until net week. (his is an eample o a constraint. A. ,orking capital !. )eople C. "&uipment D. %normation ! #aterials #aterial availa/ility and shortages have /een /lamed or the delay o many pro*ects. ,hen it is known that a lack o availa/ility o materials is important and pro/a/le' materials should /e included in the pro*ect network plan and schedule.
AACSB: Analytic Bloom's: Reflective #hin$ing Learning Objective: #y%es of Resorce Constraints Level: &edim
10. A special truck that eorge needs on his pro*ect has /een scheduled on another pro*ect. (his is a constraint. A. ,orking capital !. )eople C "&uipment D. %normation ". #aterials "&uipment is usually presented /y type' si;e' and &uantity. %n some cases e&uipment can /e interchanged to improve schedules' /ut this is not typical. "&uipment is oten overlooked as a constraint. (he most common oversight is to assume the resource pool is more than ade&uate or the pro*ect.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: #y%es of Resorce Constraints Level: &edim
8-$+
Chapter 08 - Scheduling Resources and Costs
11. #ost o the scheduling methods availa/le today re&uire the pro*ect manager to classiy the pro*ect as either constrained or constrained. A. (ime' &uality !. 9uality' resource C. Cost' time D. 9uality' cost ! (ime' resource #ost o the scheduling methods availa/le today re&uire the pro*ect manager to classiy the pro*ect as either time constrained or resource constrained.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: &edim
1$. Regina7s /oss has told her that her pro*ect is very important. % the critical path is delayed' she will /e given whatever she needs to get it /ack on schedule. 6er pro*ect is constrained. A (ime !. 9uality C. Cost D. )erormance ". Resource A time-constrained pro*ect is one that must /e completed /y an imposed date. % re&uired' resources can /e added to ensure the pro*ect is completed /y a speciic date. Although time is the critical actor' resource usage should /e no more than is necessary and suicient.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Classification of a Schedling !roblem Level: &edim
8-$
Chapter 08 - Scheduling Resources and Costs
1+. %n reviewing the status o her pro*ect with top management' Shirley was told that there only were two programmers that she could use or her pro*ect. 6er pro*ect is constrained. A. (ime !. 9uality C. Cost D. )erormance ! Resource A resource-constrained pro*ect is one that assumes the level o resources availa/le cannot /e eceeded. % the resources are inade&uate' it will /e accepta/le to delay the pro*ect' /ut as little as possi/le.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: &edim
1. All resource leveling techni&ues involve A Delaying noncritical activities !. Delaying critical activities C. :sing negative slack D. !oth A and C are correct ". A' !' and C are all correct All leveling techni&ues delay noncritical activities /y using positive slack to reduce peak demand and ill in the valleys or the resources.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
8-$2
Chapter 08 - Scheduling Resources and Costs
12. Scheduling time-constrained pro*ects ocuses on resource A. Demands !. %ncreases C. Assumptions D :tili;ation ". All are correct Scheduling time-constrained pro*ects ocuses on resource utili;ation.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
13. (he most widely used approach to apply heuristics' which have /een ound to consistently minimi;e pro*ect delay over a large variety o pro*ects is the A )arallel method !. Resource method C. #aterials D. !oth A and C are correct ". A' !' and C are all correct (he parallel method is the most widely used approach to apply heuristics' which have /een ound to consistently minimi;e pro*ect delay over a large variety o pro*ects.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: "asy
8-$3
Chapter 08 - Scheduling Resources and Costs
14. Resource leveling can provide A.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
18. =an is trying to reallocate resources in a time-constrained pro*ect to create smoother resource utili;ation with a low level o risk. She shou ld move to activities with the A. Smallest duration !.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: ifficlt
8-$4
Chapter 08 - Scheduling Resources and Costs
15. %n a resource-constrained pro*ect' which o the ollowing is most likely to /e changed A (he completion date !. (he /udget C. )ro*ect &uality D. !oth A and ! are e&ually likely ". A' !' and C are all e&ually likely #anagers who ail to schedule resources usually encounter a scheduling risk when it is too late to work around pro/lems' resulting in a pro*ect delay.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
$0. %n a resource-constrained pro*ect' the irst priority in assigning resources is usually given to activities with the A. Smallest duration B
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: "asy
8-$8
Chapter 08 - Scheduling Resources and Costs
$1. %n a resource-constrained pro*ect the second priority in assigning resources is usually given to activities with the A Smallest duration !.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
$$. (he word 6euristics means A. Resource constraints !. >lei/ility C. (he critical path changed D. )arallel activities /ecome se&uential ! Rule o thum/
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
8-$5
Chapter 08 - Scheduling Resources and Costs
$+. Splitting an activity creates the ollowing situation? A. #ore people working on the same activity !. (here are possi/le startup and shutdown costs C. A resource may /e moved rom one activity to another and then /ack D !oth ! and C are correct ". A' !' and C are all correct A planner splits the continuous work included in an activity /y interrupting the work and sending the resource to another activity or a period o time and then having the resource resume work on the original activity. Splitting can /e a useul tool i the work involved does not include large start-up or shutdown costsFor eample' moving e&uipment rom one activity location to another. (he most common error is to interrupt @people work'@ where there are high conceptual start-up and shutdown costs.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: S%litting Activities Level: &edim
$. (he :.S. >orest Service @snapshot rom practice@ illustrated the importance o A. (ime constraints !. Resource constraints C. Cost constraints D !oth ! and C are correct ". A' !' and C are all correct %t is important to remem/er that' i resources are truly limited and activity time estimates are accurate' the resource-constrained schedule will materiali;e as the pro*ect is implementedF not the time-constrained scheduleG (hereore' ailure to schedule limited resources can lead to serious pro/lems or a pro*ect manager. (he /eneit o creating this schedule /eore the pro*ect /egins leaves time or considering reasona/le alternatives.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Benefits of Schedling Resorces Level: &edim
8-+0
Chapter 08 - Scheduling Resources and Costs
$2. #ore common pro/lems associated with managing multipro*ect resources include all o the ollowing ecept A. %neicient resource utili;ation !. Delays in one pro*ect cause delays in other pro*ects C Reducing @downtime@ created /y lack o tasks to perorm D. Resource /ottlenecks ". All o these are common pro/lems See
AACSB: Analytic Bloom's: Knowledge Learning Objective: <i%roject Resorce Schedles Level: &edim
$3. ,hen a company will reduce the num/er o pro*ects they have to manage internally to only core pro*ects and send noncritical pro*ects to contractors and consulting irms this is called A utsourcing !. Redistri/ution o pro*ects C. )ro*ect allocation D. (ask sharing ". !oth ! and D are correct #any companies are using outsourcing as a means or dealing with their resource allocation pro/lems. %n some cases' a company will reduce the num/er o pro*ects they have to manage internally to only core pro*ects and outsource noncritical pro*ects to contractors and consulting irms. %n other cases' speciic segments o pro*ects are outsourced to overcome resource deiciencies and scheduling pro/lems.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: <i%roject Resorce Schedles Level: "asy
8-+1
Chapter 08 - Scheduling Resources and Costs
$4. ,hich o the ollowing is not one o the more common pro/lems associated with scheduling multipro*ect resources A. verall schedule slippage !. %neicient resource utili;ation C. Resource /ottlenecks D. !oth A and C are correct ! A' !' and C are all correct See
AACSB: Analytic Bloom's: Knowledge Learning Objective: <i%roject Resorce Schedles Level: "asy
$8. %n a resource-constrained pro*ect the third priority in assigning resources is usually g iven to activities with the A. Smallest duration !.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: "asy
8-+$
Chapter 08 - Scheduling Resources and Costs
$5. %n the !otanical arden eample' which o the ollowing was used to solve the resource pro/lem A. Resource allocation B Smoothing resource demand C. (he parallel method D. !oth A and C are correct ". A' !' and C are all correct (he !otanical arden pro*ect schedule reached the three goals o smoothing? (he peak o demand or the resource was reduced' resources over the lie o the pro*ect have /een reduced' the luctuations in resource demand were minimi;ed.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
+0. )ro*ect /udgets are developed /y time-phasing which o the ollowing A. Resource schedules B ,ork packages C. (he network diagram D. !oth A and C are correct ". A' !' and C are all correct :sing your pro*ect schedule' you can time-phase work packages and assign them to their respective scheduled activities to develop a /udget schedule over the lie o your pro*ect.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: )sing the Resorce Schedle to evelo% a !roject Cost Baseline Level: &edim
8-++
Chapter 08 - Scheduling Resources and Costs
+1. A pro*ect /udget report is showing our pro*ect as spending B+2'000 against a /udgeted amount o B0'000. ,hich o the ollowing is true A. ,e are spending less than we should or the pro*ect !. ,e are doing a good *o/ managing the pro*ect C. ,e should check to see i all the /ills have /een paid D. !oth A and ! are correct ! ,e can7t /e sure how the pro*ect is going (here is no way to /e certain how much o the physical work has /een accomplished.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: )sing the Resorce Schedle to evelo% a !roject Cost Baseline Level: &edim
Fill in the Blank Questions
+$. Delaying noncritical activities to lower peak demand and' thus' increase resource utili;ation is called leveling. resource )ractitioners have attacked the utili;ation pro/lem using resource leveling techni&ues that /alance or smooth demand or a resource. !asically' all leveling techni&ues delay noncritical activities /y using positive slack to reduce peak demand and ill in the valleys or the resources.
AACSB: Analytic Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
8-+
Chapter 08 - Scheduling Resources and Costs
++. An constraint addresses the se&uence in which pro*ect activities must occur. technical or logic (he start and se&uence o activities has /een /ased solely on technical or logical considerations. >or eample' a pro*ect network or raming a house might show three activities in a se&uence? 1 pour oundation' $ /uild rame' and + cover roo.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
+. 6aving one person responsi/le or perorming several activities' all due at the same time' is an eample o an constraint. resource % one person must perorm all activities' the resource constraint re&uires the activities /e perormed in se&uence or series.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
+2. (rying to renovate a ship compartment that is too small or more than one person is an eample o an constraint. ph"sical %n rare situations' physical actors cause activities that would normally occur in parallel to /e constrained /y contractual or environmental conditions. >or eample' in theory the renovation o a sail/oat compartment might involve our to ive tasks that can /e done independently. 6owever' since space allows only one person to work at one time' all tasks have to /e perormed se&uentially.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
8-+2
Chapter 08 - Scheduling Resources and Costs
+3. A shortage o programmers to write sotware is an eample o an type o resource constraint. people (his is the most o/vious and important pro*ect resource. 6uman resources are usually classiied /y the skills they /ring to the pro*ectFor eample' programmer' mechanical engineer' welder' inspector' marketing director' supervisor. %n rare cases some skills are interchangea/le' /ut usually with a loss o productivity. (he many diering skills o human resources add to the compleity o scheduling pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
+4. (he shortage o computer chips to produce a circuit /oard is an eample o an type o resource constraint. #aterials #aterial availa/ility and shortages have /een /lamed or the delay o many pro*ects. ,hen it is known that a lack o availa/ility o materials is important and pro/a/le' materials should /e included in the pro*ect network plan and schedule.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
+8. % three copiers are needed to produce a inal report on time and only two are availa/le' the pro*ect is acing an type o resource constraint. e$uip#ent (he most common oversight is to assume the resource pool is more than ade&uate or the pro*ect.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: #y%es of Resorce Constraints Level: "asy
8-+3
Chapter 08 - Scheduling Resources and Costs
+5. 6ector wants to /ring on another programmer to work on the pro*ect /ut the company does not have anyone who has the needed skills. 6ector7s pro*ect is acing an constraint. people t"pe o% resource (his is the most o/vious and important pro*ect resource. 6uman resources are usually classiied /y the skills they /ring to the pro*ectFor eample' programmer' mechanical engineer' welder' inspector' marketing director' supervisor. %n rare cases some skills are interchangea/le' /ut usually with a loss o productivity. (he many diering skills o human resources add to the compleity o scheduling pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
0. %n order that the new product is on the shel or the Christmas /uying season' the development o the new product would /e classiied as an constrained pro*ect. ti#e A time-constrained pro*ect is one that must /e completed /y an imposed date. % re&uired' resources can /e added to ensure the pro*ect is completed /y a speciic date. Although time is the critical actor' resource usage should /e no more than is necessary and suicient.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Classification of a Schedling !roblem Level: &edim
1. !eth has two engineers assigned to her pro*ect and cannot get any more even i it means slipping the due date on her pro*ect. She is managing an constrained pro*ect. resource A resource-constrained pro*ect is one that assumes the level o resources availa/le cannot /e eceeded. % the resources are inade&uate' it will /e accepta/le to delay the pro*ect' /ut as little as possi/le.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Classification of a Schedling !roblem Level: &edim
8-+4
Chapter 08 - Scheduling Resources and Costs
$. All leveling techni&ues delay noncritical activities /y using to reduce peak demand. positi&e slack All leveling techni&ues delay noncritical activities /y using positive slack to reduce peak demand and ill in the valleys or the resources.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
+. Scheduling activities in a constrained pro*ect typically has as the top heuristic rule. #ini#u# slack See list on )age $30.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
. (he is the most widely used approach to apply heuristic rules to scheduling activities in a constrained pro*ect. parallel #ethod (he parallel method is the most widely used approach to apply heuristics' which have /een ound to consistently minimi;e pro*ect delay over a large variety o pro*ects.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
8-+8
Chapter 08 - Scheduling Resources and Costs
2. ,hen using the scheduling techni&ue' the work in an activity is interrupted to work on another activity and is then resumed at a later point in time. splitting or #ultitasking A planner splits the continuous work included in an activity /y interrupting the work and sending the resource to another activity or a period o time and then having the resource resume work on the original activity.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: S%litting Activities Level: &edim
3. %n scheduling resource-constrained pro*ects' are typically used rather than optimum mathematical solutions. heuristics A ew researchers have demonstrated optimum mathematical solutions to the resource allocation pro/lem /ut only or small networks and very ew resource types. (he massive data re&uirements or larger pro/lems make pure mathematical solutions e.g.' linear programming impractical. An alternative approach to the pro/lem has /een the use o heuristics rules o thum/ to solve large com/inatorial pro/lems.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
4. %n scheduling terms' constrained means that pro*ect duration is ied and resources are lei/le. ti#e %n scheduling terms' time constrained means time pro*ect duration is ied and resources are lei/le.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: "asy
8-+5
Chapter 08 - Scheduling Resources and Costs
8. %n scheduling terms' constrained means that a speciic resource is ied and the duration o the pro*ect is lei/le. resource %n scheduling terms' constrained means resources are ied and time is lei/le.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: Classification of a Schedling !roblem Level: "asy
5. Start-up and shutdown costs are ma*or considerations when using the scheduling techni&ue. splitting/#ultitasking (he most common error is to interrupt @people work'@ where there are high conceptual startup and shutdown costs.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: S%litting Activities Level: "asy
20. (o deal with pro/lems related to having several concurrent pro*ects' companies are creating to oversee the scheduling o resources across multiple pro*ects. pro'ect o%%ices or pro'ect depart#ents #ore and more companies create pro*ect oices or departments to oversee the scheduling o resources across multiple pro*ects.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: <i%roject Resorce Schedles Level: "asy
8-0
Chapter 08 - Scheduling Resources and Costs
21. #any companies are using rom contractors and consultants as a means o dealing with the peaks and valleys o resource allocation among pro*ects. outsourcing #any companies are using outsourcing as a means or dealing with their resource allocation pro/lems. %n some cases' a company will reduce the num/er o pro*ects they have to manage internally to only core pro*ects and outsource noncritical pro*ects to contractors and consulting irms. %n other cases' speciic segments o pro*ects are outsourced to overcome resource deiciencies and scheduling pro/lems.
AACSB: Reflective #hin$ing Bloom's: Com%rehension Learning Objective: <i%roject Resorce Schedles Level: "asy
2$. (he is the most widely used approach to apply heuristics in resourceconstrained pro*ects. parallel #ethod (he parallel method is the most widely used approach to apply heuristics' which have /een ound to consistently minimi;e pro*ect delay over a large variety o pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
2+. (he a/ility to more eiciently manage the e//s and lows o pro*ect work is one o the ma*or driving orces /ehind today. outsourcing (he a/ility to more eiciently manage the e//s and lows o pro*ect work is one o the ma*or driving orces /ehind outsourcing today.
AACSB: Analytic Bloom's: Knowledge Learning Objective: <i%roject Resorce Schedles Level: &edim
8-1
Chapter 08 - Scheduling Resources and Costs
2. ,ithout a time-phased good pro*ect schedule and cost control are impossi/le. (udget (hese systems do not measure how much work was accomplished or the money spentG 6ence' without time-phasing cost to match your pro*ect schedule' it is impossi/le to have relia/le inormation or control purposes.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: )sing the Resorce Schedle to evelo% a !roject Cost Baseline Level: &edim
22. A pro*ect cost /aseline is also called . planned &alue )*+, (he outcome o these /udget allocations is the pro*ect cost /aseline also called planned value F)H' which is used to determine cost and schedule variances as the pro*ect is implemented.
AACSB: Analytic Bloom's: Knowledge Learning Objective: )sing the Resorce Schedle to evelo% a !roject Cost Baseline Level: &edim
True / False Questions
23. (he se&uence o 1 pour oundation' $ /uild rame' and + cover roo is a type o physical constraint. FA-S! (he start and se&uence o activities has /een /ased solely on technical or logical considerations. >or eample' a pro*ect network or raming a house might show three activities in a se&uence? 1 pour oundation' $ /uild rame' and + cover roo.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Overview of the Resorce Schedling !roblem Level: "asy
8-$
Chapter 08 - Scheduling Resources and Costs
24. (oo many parallel activities or one individual are an eample o a resource constraint. TR.! % one person must perorm all activities' the resource constraint re&uires the activities /e perormed in se&uence or series.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem Level: &edim
28. A pro*ect that is not resource-constrained is time-constrained. TR.! %n scheduling terms' time constrained means time pro*ect duration is ied and resources are lei/le' where constrained means resources are ied and time is lei/le.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Classification of a Schedling !roblem Level: &edim
25. Resource leveling is only used on pro*ects which are resource-constrained. FA-S! )ractitioners have attacked the utili;ation pro/lem using resource leveling techni&ues that /alance or smooth demand or a resource. !asically' all leveling techni&ues delay noncritical activities /y using positive slack to reduce peak demand and ill in the valleys or the resources.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
8-+
Chapter 08 - Scheduling Resources and Costs
30. Resource !ottlenecks are one o the three more common pro/lems encountered in managing multipro*ect resource schedules. TR.! See list on )age $4.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: <i%roject Resorce Schedles Level: &edim
31. (he ina/ility to get more than two earth movers on a construction site at the same time is an eample o a physical constraint. TR.! %n rare situations' physical actors cause activities that would normally occur in parallel to /e constrained /y contractual or environmental conditions.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: #y%es of Resorce Constraints Level: &edim
3$. (he most o/vious and important kind o resource constraint is a lack o materials. FA-S! )eople are the most o/vious and important pro*ect resource.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: "asy
8-
Chapter 08 - Scheduling Resources and Costs
3+. 6aving too ew programmers and too many engineers is an eample o a people resource constraint. TR.! >inding people with certain diering skills adds to the compleity o scheduling pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: &edim
3. % a pro*ect needs one earth-mover si months rom now and the organi;ation has our such machines' there is no e&uipment resource constraint. FA-S! (he most common oversight is to assume the resource pool is more than ade&uate or the pro*ect. >or eample' i a pro*ect needs one earth-moving tractor si months rom now and the organi;ation owns our' it is common to assume the resource will not delay the pending pro*ect. 6owever' when the earthmoving tractor is due on-site in si months' all our machines in the pool might /e occupied on other pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: &edim
32. A lack o readily availa/le engineers is a technical constraint. FA-S! ,hen the num/er o people andIor e&uipment is not ade&uate to meet peak demand re&uirements and it is impossi/le to o/tain more' the pro*ect manager aces a resourceconstrained pro/lem.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
8-2
Chapter 08 - Scheduling Resources and Costs
33. All pro*ects are usually either time-constrained or resource-constrained. TR.! #ost o the scheduling methods availa/le today re&uire the pro*ect manager to classiy the pro*ect as either time constrained or resource constrained.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: "asy
34. (o determine i a pro*ect is time-constrained or resource-constrained you would consult the pro*ect priority matri. TR.! )ro*ect managers need to consult their priority matri to determine which case its their pro*ect.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: &edim
38. Scheduling time-constrained pro*ects ocuses on the optimal utili;ation o resources. TR.! A time-constrained pro*ect is one that must /e completed /y an imposed date. % re&uired' resources can /e added to ensure the pro*ect is completed /y a speciic date. Although time is the critical actor' resource usage should /e no more than is necessary and suicient.
AACSB: Analytic Bloom's: Reflective #hin$ing Learning Objective: Classification of a Schedling !roblem Level: &edim
8-3
Chapter 08 - Scheduling Resources and Costs
35. All leveling techni&ues delay noncritical activities /y using positive slack to smooth out the resource re&uirements. TR.! All leveling techni&ues delay noncritical activities /y using positive slack to reduce peak demand and ill in the valleys or the resources.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
40. Scheduling time-constrained pro*ects ocuses on resource utili;ation. FA-S! Scheduling time-constrained pro*ects ocuses on resource utili;ation.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
41. Scheduling resource-constrained pro*ects ocuses on completing the pro*ect as soon as possi/le under the given constraints. TR.! ,hen the num/er o people andIor e&uipment is not ade&uate to meet peak demand re&uirements and it is impossi/le to o/tain more' the pro*ect manager aces a resourceconstrained pro/lem. Something has to give. (he trick is to prioriti;e and allocate resources to minimi;e pro*ect delay without eceeding the resource limit or altering the technical network relationships.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: ifficlt
8-4
Chapter 08 - Scheduling Resources and Costs
4$. 6euristics are used in resource-constrained pro*ects to develop the optimal schedule. FA-S! 6euristics do not always yield an optimal schedule' /ut they are very capa/le o yielding a @good@ schedule or very comple networks with many types o resources.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
4+. (he top priority in using heuristics to allocate scare resources is those activities with the smallest duration. FA-S! 6euristics allocate resources to activities to minimi;e pro*ect delayJ that is' heuristics prioriti;e which activities are allocated resources and which activities are delayed when resources are not ade&uate.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: "asy
4. (he critical path in a resource-constrained schedule can /e a group o dis*ointed' unconnected activities. TR.! (he traditional critical path concept o se&uential activities rom the start to the end o the pro*ect is no longer meaningul. (he resource constraints can /reak the se&uence and leave the network with a set o dis*ointed critical activities.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Com%ter emonstration of Resorce(Constrained Schedling Level: &edim
8-8
Chapter 08 - Scheduling Resources and Costs
42. Splitting is a scheduling techni&ue used to get a /etter schedule or /etter resource utili;ation. TR.! Splitting tasks is a scheduling techni&ue used to get a /etter pro*ect schedule andIor to increase resource utili;ation.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: S%litting Activities Level: "asy
43. ,ithout a time-phased /udget good pro*ect schedule and cost control are impossi/le. TR.!
AACSB: Analytic Bloom's: Knowledge Learning Objective: )sing the Resorce Schedle to evelo% a !roject Cost Baseline Level: "asy
44. #any companies are using outsourcing as a means or dealing with their resource allocation pro/lems associated with managing multipro*ect resources. TR.! Companies may hire temporary workers to epedite certain activities that are alling /ehind schedule or contract pro*ect work during peak periods when there are insuicient internal resources to meet the demands o all pro*ects.
AACSB: Reflective #hin$ing Bloom's: Knowledge Learning Objective: <i%roject Resorce Schedles Level: "asy
Short Answer Questions
8-5
Chapter 08 - Scheduling Resources and Costs
48. %dentiy and /riely descri/e the three types o pro*ect constraints. 1. (echnical logicJ the se&uence that activities must /e perormed' $. resourceJ the a/sence o re&uired people' materials' e&uipment' or working capital' and +. physicalJ limitations /ased on space or environmental limits.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Overview of the Resorce Schedling !roblem and #y%es of Resorce Constraints Level: &edim
45. ,hat is the dierence in pro*ect goals when using resource leveling on time-constrained pro*ects and using it on resource-constrained pro*ects %n time-constrained pro*ects the goal is to smooth out the peaks and valleys and thus improve the utili;ation. %n resource-constrained pro*ects the goal is to achieve the shortest pro*ect duration given a limited supply o resources.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Com%ter emonstration of Resorce(Constrained Schedling Level: ifficlt
80. %dentiy the potential impacts o pro*ect constraints. 1. reduction in slack on the pro*ect network' $. decrease in lei/ility' +. possi/le decrease in parallel activities' and . increase in the likelihood o delaying the pro*ect.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: &edim
8-20
Chapter 08 - Scheduling Resources and Costs
81. %dentiy and give an eample o the three types o resource constraints. 1. )eopleJ /y skill classiication engineer' programmer' salesperson' $. materialsJ paint' data' parts' and +. e&uipmentJ computers' earth-movers' oice space.
AACSB: Analytic Bloom's: Knowledge Learning Objective: #y%es of Resorce Constraints Level: &edim
8$. %dentiy and /riely descri/e the two classiications o scheduling pro/lems. 1. time-constrainedJ the end date is ied and needed resources are availa/le' $. resourceconstrainedJ the resources are ied and the end date is lei/le.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Classification of a Schedling !roblem Level: &edim
8+. ,hat are the disadvantages o resource leveling 1. loss o lei/ility' $. increased risk o pro*ect delay' +. more critical or near critical activities.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: ifficlt
8-21
Chapter 08 - Scheduling Resources and Costs
8. ,hy would a pro*ect manager use heuristics rather than a mathematical solution to level resources #athematical models work on small networks and a small num/er o resources.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: Resorce Allocation ðods Level: ifficlt
82. ,hat are the three most common heuristics in order o priority used to allocate resources to pro*ect activities 1. minimum slackJ start with activities with the least amount o slack' $. smallest durationJ i two activities have the same slack select the one with the smallest duration' and +. lowest activity identiication num/er' i slack and duration are the same select the earliest activity.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: &edim
83. Descri/e the parallel method or applying heuristics to the allocation o pro*ect resources. (he irst priority is to allocate resources to the activity with the least amount o slack' usually an activity on the critical path. % more than one activity has the same amount o slack then selects the activity with the smallest duration. % more than one activity has the same slack and the same duration then select the activity that occurs the earliest.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation ðods Level: ifficlt
8-2$
Chapter 08 - Scheduling Resources and Costs
84. ,hy should pro*ect managers /e cautious a/out using the splitting scheduling techni&ue (he splitting techni&ue is where an activity is interrupted and the resources are applied to another activity. (he potential pro/lems are in the addition o shutdown and startup costs which are added as one moves rom activity to activity prior to completing the original activity.
AACSB: Analytic Bloom's: Knowledge Learning Objective: S%litting Activities Level: &edim
88. %dentiy and /riely discuss the three more common pro/lems encountered in managing multipro*ect resource schedules. 1. overall schedule slippage' $. ineicient resource utili;ation' and +. resource /ottlenecks.
AACSB: Analytic Bloom's: Com%rehension Learning Objective: <i%roject Resorce Schedles Level: ifficlt
85. %dentiy and /riely descri/e the potential impacts o resource-constrained scheduling. 1. reduced slack reduces lei/ility' $. increased num/er o critical and near-critical activities' +. increase compleity due to resource constrains added to technical constraints' . the critical path may /ecome a set o dis*ointed critical activities' and 2. ormerly critical activities may now /ecome non-critical.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Com%ter emonstration of Resorce(Constrained Schedling Level: ifficlt
8-2+