Chapter 09 - Reducing Project Duration
Chapter 09 Reducing Project Duration Multiple Choice Questions
1. The president of a software company remarks in a speech that new technoogicay ad!anced software wi "e a!aia"e in one year. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
+. &ntense go"a competition and rapid technoogica ad!ances create pressure on de!eoping projects rapidy. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
,. % contractor finished a "ridge across a ake 1 months eary and recei!ed more than / miion for the eary competion. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
Chapter 09 - Reducing Project Duration
. %d!erse weather design faws and e2uipment "reakdown can create negati!e sack. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
3. Tota project costs incude a of the foowing e#cept$ %. 4uper!ision '. %dministration C. Project manager5s saary D. &nterest *. % of these are incuded in tota project costs
/. 6hich of the foowing is not considered a project indirect cost7 %. 4uper!ision '. Consutants C. *2uipment D. &nterest *. % of these are considered project indirect costs
8. Project costs are generay cassified as costs. co sts. %. Direct '. &ndirect C. :!erhead D. 'oth % and ' are correct *. % ' and C are a correct
Chapter 09 - Reducing Project Duration
. %d!erse weather design faws and e2uipment "reakdown can create negati!e sack. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
3. Tota project costs incude a of the foowing e#cept$ %. 4uper!ision '. %dministration C. Project manager5s saary D. &nterest *. % of these are incuded in tota project costs
/. 6hich of the foowing is not considered a project indirect cost7 %. 4uper!ision '. Consutants C. *2uipment D. &nterest *. % of these are considered project indirect costs
8. Project costs are generay cassified as costs. co sts. %. Direct '. &ndirect C. :!erhead D. 'oth % and ' are correct *. % ' and C are a correct
Chapter 09 - Reducing Project Duration
. ;ow-cost reaistic efficient methods for competing an acti!ity under norma c onditions are supported "y time. %.
9. The shortest possi"e time an acti!ity can "e competed reaisticay is caed time. %. *#pedited '. %cceerated C. Crash D. :ptimistic *. :ptima
10. The most common response for meeting unattaina"e deadines is to %. Reduce or scae "ack the scope of the project. '. Decrease the critica paths C. Crash a eements of the project D. Change the time to market statement *. ' and C are correct
11. costs are incurred when competing an acti!ity in its reaisticay shortest time. %.
Chapter 09 - Reducing Project Duration
1+. %n acti!ity5s crash costs incude costs. %. Direct '. &ndirect C. :!erhead D. 'oth % and ' are correct *. % ' and C are correct
1,. Cost sope can "e determined "y di!iding the %. Run "y the rise '. Rise "y the run C. Crash cost "y the norma cost D.
1. The ess steep the cost sope of an acti!ity the %. ;ess it costs to shorten one time period '. >ore it costs to shorten one time period C. 4maer the crash time D. ;arger the crash time *. Cannot "e determined "y the information gi!en
13. 6hich of the foowing correcty cacuates an acti!ity5s cost sope7 %. ?norma cost-crash cost@A?norma time-crash time@ '. ?crash cost-norma cost@A?norma time-crash time@ C. ?norma time-crash time@A?crash cost-norma cost@ D. ?norma time-crash time@A?norma cost-crash cost@ *. ?crash cost-norma cost@A?crash time-norma time@
1/. %n acti!ity5s cost sope represents an acti!ity5s %. Tota cost per unit of time '. Cost per unit of time C. &ndirect cost per unit of time D. 'oth ' and C are correct *. % ' and C are a correct
Chapter 09 - Reducing Project Duration
18. &n seecting the "est acti!ity to reduce you woud first seect the acti!ity with the %. *ariest start time '. 4teepest sope C. ;east steep sope D. ;ongest duration *. ;argest crash time
1. The optimum duration for a project is at the point where$ %. Direct costs are the owest '. &ndirect costs are the owest C. Direct costs e2ua indirect costs D. Tota project costs are the owest *. The project changes from time-constrained to resource-constrained
19. Creating a Project Cost-Duration graph is usefu$ %. During the pre-project panning phase '. %fter the project has "egun C. %fter the competion of the project D. 'oth % and ' are correct *. % ' and C are a correct
+0. Crashing a project shoud occur$ %. %s eary as possi"e '. %s ate as possi"e C. >idway through the project D. 'oth % and C are correct *. Cannot "e determined with the information gi!en
+1. &f a network has se!era critica or near-critica paths it is deemed to "e$ %. 6e panned '. The owest cost aternati!e C. Resource-constrained D. 4ensiti!e *. &nsensiti!e
Chapter 09 - Reducing Project Duration
++. The project direct-cost ine near the norma point is usuay$ %. 4oped steepy '. Reati!ey fat C. Rising D. Baing *. enty soped
+,. The reationship "etween cost and time for !arious durations is assumed to "e$ %. ;inear '. Cur!iinear C. aria"e D. Con!ersey reated *. *#ponentiay reated
+. % common method for shortening the project time is to$ %. %dding resources '. 4chedue o!ertime C. 4u"contract an acti!ity D. 'oth % and ' are correct *. % ' and C are a correct
+3. % positi!e situation where mo!ing toward the optimum time can resut in !ery rea arge sa!ingsEthis occurs when the network is$ %. &nsensiti!e '. 4ensiti!e C. %head of schedue D. 4hifting to the critica chain *. &mpementing a fast-tracking system
Chapter 09 - Reducing Project Duration
+/. 6hich of the foowing isAare incuded in a Project Cost-Duration raph7 %. Tota indirect cost '. Tota direct cost C. Tota project cost D. 'oth % and ' are correct *. % ' and C are a correct
+8. :ne way of reducing project costs is identifying tasks that can do themse!es. %. endors '. 4uppiers C. Customers D. Company empoyees *. Project teams
+. The most common method for shortening project time is to %. 4u"contract acti!ities '. Compromise the 2uaity C. %dd additiona staff and e2uipment D. 6ork o!ertime *. Reduce the project scope
+9. 6hich of the foowing is not one of the more commony used options for cutting project costs7 %. Reduce project scope '. )a!e owner take more responsi"iity C. >o!ing the competion date further out D. 'rainstorming cost sa!ings options *. :utsourcing project acti!ities
Chapter 09 - Reducing Project Duration
,0. 6hich of the foowing is the most common method for shortening project time7 %. %ssigning additiona staff and e2uipment '. 4u"contract work C. 4chedue o!ertime D. Reduce project scope *. Reduce the 2uaity
,1. %ccording to 'rooks5 ;aw adding more peope to a ate project is most ikey to ha!e which of the foowing impact7 %. Feep the project from sipping any further '. et the project "ack on schedue C. >ake the project sips further D. 'oth % and ' are correct *.
,+. 6hich of the foowing is the easiest method for shortening project time7 %. %ssigning additiona staff and e2uipment '. 4u"contract work C. 4chedue o!ertime D. Reduce project scope *. Reduce the 2uaity
,,. 6hich of the foowing is not one of the techni2ues for acceerating project competion7 %. %ssigning additiona staff and e2uipment '. *sta"ish a core team C. Do it twiceEfast and correcty D. Reduce project scope *. % of these are accepta"e techni2ues
Chapter 09 - Reducing Project Duration
,. 6hen the project team is saaried which of the foowing is the preferred choice for acceerating project competion7 %. %ssigning additiona staff and e2uipment '. 4u"contract work C. 4chedue o!ertime D. 6ork onger hours *. 'oth C and D are preferred choices
,3. The 4napshot from Practice GCe-Phone 6arsG is an e#ceent e#ampe of reducing project duration due to$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts
Fill in the Blank Questions
,/. 6hen a poitician makes a pu"ic statement that a new "uiding wi "e a!aia"e in two years a?n@ duration has reduced the project duration.
,8. &ntense go"a competition and rapid technoogica ad!ances com"ine to create a?n@ imposed project duration date.
,. The 4napshot from Practice which detaied the
Chapter 09 - Reducing Project Duration
,9. 4ometimes !ery high costs are recogni=ed "efore a project "egins and reducing these costs through shorter project durations "ecomes a high priority.
0. The project cost is the sum of the indirect and direct costs.
1. Costs such as super!ision administration consutants and interest are e#ampes of project costs.
+. Costs such as a"or materias e2uipment or contractors are e#ampes of project costs.
,. Direct costs are assigna"e directy to a project .
. 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud the cost of the acti!ity.
3. To shorten the duration of a project the project manager shoud imit the choices of acti!ities to just those which .
Chapter 09 - Reducing Project Duration
/. The time for an acti!ity represents ow-costs reaistic efficient methods for competing the acti!ity under typica conditions.
8. 4hortening an acti!ity is caed .
. The direct costs for competing an acti!ity as eary as possi"e is caed its .
9. %n acti!ity5s is cacuated "y di!iding the rise "y the run.
30. 4u"tracting an acti!ity5s norma cost from the crash cost wi cacuate an acti!ity5s .
31. 4u"tracting an acti!ity5s crash time from the norma time wi cacuate an acti!ity5s .
3+. 6hen considering whether to mo!e the project to its optimum cost-time position the manager shoud aso consider .
3,. % network is considered to "e if it has a predominate critica path with no other path cose in terms of sack.
Chapter 09 - Reducing Project Duration
3. The easiest way to add more resources to a project is not to add more peope "ut to schedue .
33. %ccording to adding more manpower to a ate software project makes it ater.
3/. The easiest way to add more a"or to a project is not to add more peope "ut to add .
38. is the rearranging of the project network ogic so that critica acti!ities are done in parae rather than se2uentiay.
3. is pro"a"y the most common response for meeting unattaina"e deadines.
39. &n the G&5 'et Hou...G 4napshot from Practice the draftsman won for making a !ery difficut deadine.
True / False Questions
/0. % rue of thum" for moderate- to high-technoogy firms is that a si#-month deay in "ringing a product to market can resut in a gross profit oss of a"out ,3 percent. True Base
Chapter 09 - Reducing Project Duration
/1. &mposed project durations amost aways eads to a higher-cost project than one panned with detaied scheduing of a the project5s acti!ities. True Base
/+. >anagers ha!e se!era effecti!e methods for crashing specific project acti!ities when resources are not constrained. True Base
/,. &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest. True Base
/. The tota cost for each possi"e duration of a project is the sum of a"or materias and e2uipment. True Base
/3. Direct costs are so named "ecause they can "e assigned directy to a work package and acti!ity. True Base
//. 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud add to the costs of the acti!ity. True Base
/8. The sum of the costs of a the work packages represents the tota direct costs for the project. True Base
Chapter 09 - Reducing Project Duration
/. &ncenti!e contracts can make reduction of project time rewardingEusuay for "oth the project contractor and owner. True Base
/9. 4hortening an acti!ity5s duration is termed crashing . True Base
80. *#pected time for an acti!ity represents ow-cost reaistic efficient methods for competing the acti!ity under anticipated conditions. True Base
81. Crash cost is the incrementa cost incurred when an acti!ity is reduced in duration. True Base
8+. The cost sope of an acti!ity is cacuated "y di!iding the run "y the rise. True Base
8,. Crash time is the greatest time reduction possi"e under reaistic conditions. True Base
8. The higher the sope of an acti!ity the greater the cost to reduce its duration. True Base
83. Creating a Project Cost-Duration raph in the pre-project panning phase without an imposed duration is the "est time to use this too. True Base
Chapter 09 - Reducing Project Duration
8/. Crashing a more e#pensi!e acti!ity may "e wise if fewer inherent risks are in!o!ed. True Base
88. % project network is cassified as sensiti!e if it has a arge num"er of interacting paths. True Base
8. Coecting crash times for a moderate-si=e project is reati!ey easy. True Base
89. 6hie the reationship "etween norma and crash times is reay cur!iinear the assumption that it is inear is sedom a concern for practicing managers. True Base
0. The accuracy of crash times and costs is fre2uenty rough at "est when compared with norma time and cost. True Base
1. :ne of the ad!antages of using a Project Cost-Duration raph is that it keeps the importance of indirect costs in the forefront of decision making. True Base
Short ns!er Questions
Chapter 09 - Reducing Project Duration
+. &dentify and "riefy descri"e fi!e reasons for attempting to reduce the duration of a project.
,. &dentify and gi!e an e#ampe for "oth of the major categories that make up project costs.
. Draw a typica Project Cost-Duration raph and a"e the key eements.
3. 6hy is the project duration with the owest direct costs sedom the optimum duration for a project7
Chapter 09 - Reducing Project Duration
/. i!en an e2ua e!e of risk and the need to reduce o!era project duration why woud you not seect the acti!ity with the owest sope in the entire project network to crash first7
8. 6hat is crashing and incude a discussion of crash time and crash cost 7
. )ow woud you cacuate an acti!ity5s sope and what does it represent7
9. i!en that an acti!ity5s norma time and cost are ten days and 00 and its crash time is fi!e days and 00 what is the acti!ity5s sope7
Chapter 09 - Reducing Project Duration
90. 6hat do we mean when we say that a project network is sensitive and why is that important to a project manager7
91. &dentify options for acceerating a project schedue when resources are not constrained.
9+. &dentify options for acceerating a project schedue when resources are constrained or the "udget is se!erey constrained.
9,. 6hat are the "enefits to using a Project Cost-Duration raph to assist in comparing any proposed aternati!e or change with the current "aseine7
Chapter 09 - Reducing Project Duration
9. 6hat is Critica-chain ?C-C@ project management and why can it "e of "enefit to project managers7
Chapter 09 - Reducing Project Duration
Chapter 09 Reducing Project Duration %nswer Fey
Multiple Choice Questions
1. The president of a software company remarks in a speech that new technoogicay ad!anced software wi "e a!aia"e in one year. This is an e#ampe of reducing project duration caused "y$ " &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts G&mposed deadinesG is another reason for acceerating project competion. Bor e#ampe the president of a software company remarks in a speech that new ad!anced software wi "e a!aia"e in one year. 4uch statements too often "ecome imposed project duration datesE without any consideration of the pro"ems or cost of meeting such a date. The project duration time is set whie the project is in its GconceptG phase "efore or without any detaied scheduing of a the acti!ities in the project. This phenomenon occurs !ery fre2uenty in practiceI
AACSB: Analytic Bloom's: Knowledge Learning Objective: Rationale for Redcing !roject "ration Level: #asy
Chapter 09 - Reducing Project Duration
+. &ntense go"a competition and rapid technoogica ad!ances create pressure on de!eoping projects rapidy. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines B" Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts &ntense go"a competition and rapid technoogica ad!ances ha!e made speed a competiti!e ad!antage. To succeed companies ha!e to spot new opportunities aunch project teams and "ring new products or ser!ices to the marketpace in a fash.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
,. % contractor finished a "ridge across a ake 1 months eary and recei!ed more than / miion for the eary competion. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C. (nforeseen project deays D. )igh o!erhead #" &ncenti!e contracts &ncenti!e contracts can make reduction of project time rewardingEusuay for "oth the project contractor and owner. Bor e#ampe a contractor finished a "ridge across a ake 1 months eary and recei!ed more than / miion for the eary competion. The a!aia"iity of the "ridge to the surrounding community 1 months eary to reduce traffic grid-ock made the incenti!e cost to the community seem sma to users.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
Chapter 09 - Reducing Project Duration
. %d!erse weather design faws and e2uipment "reakdown can create negati!e sack. This is an e#ampe of reducing project duration caused "y$ %. &mposed project deadines '. Time to market C" (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts %nother common reason for reducing project time occurs when unforeseen deaysEfor e#ampe ad!erse weather design faws and e2uipment "reakdownE cause su"stantia deays midway in the project.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Rationale for Redcing !roject "ration Level: #asy
3. Tota project costs incude a of the foowing e#cept$ %. 4uper!ision '. %dministration C. Project manager5s saary D. &nterest #" % of these are incuded in tota project costs Direct costs commony represent a"or materias e2uipment and sometimes su"contractors. &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
/. 6hich of the foowing is not considered a project indirect cost7 %. 4uper!ision '. Consutants C" *2uipment D. &nterest *. % of these are considered project indirect costs &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !roject Cost"ration (ra$h Level: )edim
8. Project costs are generay cassified as costs. %. Direct '. &ndirect C. :!erhead D" 'oth % and ' are correct *. % ' and C are a correct Direct Costs J &ndirect Costs K Tota Costs
AACSB: Analytic Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
. ;ow-cost reaistic efficient methods for competing an acti!ity under norma c onditions are supported "y time. "
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
9. The shortest possi"e time an acti!ity can "e competed reaisticay is caed time. %. *#pedited '. %cceerated C" Crash D. :ptimistic *. :ptima The shortest possi"e time an acti!ity can reaisticay "e competed in is caed its crash time.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
10. The most common response for meeting unattaina"e deadines is to " Reduce or scae "ack the scope of the project. '. Decrease the critica paths C. Crash a eements of the project D. Change the time to market statement *. ' and C are correct &t is prudent to e#amine the direct costs of shortening the critica path !ersus the o!erhead cost sa!ings.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
11. costs are incurred when competing an acti!ity in its reaisticay shortest time. %.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
1+. %n acti!ity5s crash costs incude costs. " Direct '. &ndirect C. :!erhead D. 'oth % and ' are correct *. % ' and C are correct The direct cost for competing an acti!ity in its crash time is caed crash cost. 'oth norma and crash times and costs are coected from personne most famiiar with competing the acti!ity.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
1,. Cost sope can "e determined "y di!iding the %. Run "y the rise B" Rise "y the run C. Crash cost "y the norma cost D.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
1. The ess steep the cost sope of an acti!ity the " ;ess it costs to shorten one time period '. >ore it costs to shorten one time period C. 4maer the crash time D. ;arger the crash time *. Cannot "e determined "y the information gi!en The ess steep the cost sope of an acti!ity the ess it costs to shorten one time period.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
13. 6hich of the foowing correcty cacuates an acti!ity5s cost sope7 %. ?norma cost-crash cost@A?norma time-crash time@ B" ?crash cost-norma cost@A?norma time-crash time@ C. ?norma time-crash time@A?crash cost-norma cost@ D. ?norma time-crash time@A?norma cost-crash cost@ *. ?crash cost-norma cost@A?crash time-norma time@ ?crash cost-norma cost@A?norma time-crash time@.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
1/. %n acti!ity5s cost sope represents an acti!ity5s %. Tota cost per unit of time B" Cost per unit of time C. &ndirect cost per unit of time D. 'oth ' and C are correct *. % ' and C are a correct Fnowing the sope of acti!ities aows managers to compare which critica acti!ities to shorten. The ess steep the cost sope of an acti!ity the ess it costs to shorten one time periodL a steeper sope means it wi cost more to shorten one time unit.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
18. &n seecting the "est acti!ity to reduce you woud first seect the acti!ity with the %. *ariest start time '. 4teepest sope C" ;east steep sope D. ;ongest duration *. ;argest crash time The ess steep the cost sope of an acti!ity the ess it costs to shorten one time period.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
1. The optimum duration for a project is at the point where$ %. Direct costs are the owest '. &ndirect costs are the owest C. Direct costs e2ua indirect costs D" Tota project costs are the owest *. The project changes from time-constrained to resource-constrained 4ee Bigure 9./ on Page ,1.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
19. Creating a Project Cost-Duration graph is usefu$ %. During the pre-project panning phase '. %fter the project has "egun C. %fter the competion of the project D" 'oth % and ' are correct *. % ' and C are a correct 4uch a graph can "e used "efore the project "egins or whie the project is in progress.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
Chapter 09 - Reducing Project Duration
+0. Crashing a project shoud occur$ %. %s eary as possi"e '. %s ate as possi"e C. >idway through the project D. 'oth % and C are correct #" Cannot "e determined with the information gi!en Coecting crash times for e!en a moderate-si=e project can "e difficut. The meaning of crash time is difficut to communicate. 6hat is meant when you define crash time as Gthe shortest time you can reaisticay compete an acti!ityG7 Crash time is o pen to different interpretations and judgments.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: "ifficlt
+1. &f a network has se!era critica or near-critica paths it is deemed to "e$ %. 6e panned '. The owest cost aternati!e C. Resource-constrained D" 4ensiti!e *. &nsensiti!e % network is sensiti!e if it has se!era critica or near-critica paths.
AACSB: Analytic Bloom's: Knowledge Learning Objective: !ractical Considerations Level: #asy
Chapter 09 - Reducing Project Duration
++. The project direct-cost ine near the norma point is usuay$ %. 4oped steepy B" Reati!ey fat C. Rising D. Baing *. enty soped The project direct-cost ine near the norma point is usuay reati!ey fat.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
+,. The reationship "etween cost and time for !arious durations is assumed to "e$ " ;inear '. Cur!iinear C. aria"e D. Con!ersey reated *. *#ponentiay reated The cost-time reationship is inear.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
+. % common method for shortening the project time is to$ %. %dding resources '. 4chedue o!ertime C. 4u"contract an acti!ity D. 'oth % and ' are correct #" % ' and C are a correct The most common method for shortening project time is to assign additiona staff and e2uipment to acti!ities.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: )edim
+3. % positi!e situation where mo!ing toward the optimum time can resut in !ery rea arge sa!ingsEthis occurs when the network is$ " &nsensiti!e '. 4ensiti!e C. %head of schedue D. 4hifting to the critica chain *. &mpementing a fast-tracking system % positi!e situation where mo!ing toward the optimum time can resut in !ery rea arge sa!ingsEthis occurs when the network is insensiti!e.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !ractical Considerations Level: #asy
Chapter 09 - Reducing Project Duration
+/. 6hich of the foowing isAare incuded in a Project Cost-Duration raph7 %. Tota indirect cost '. Tota direct cost C. Tota project cost D. 'oth % and ' are correct #" % ' and C are a correct 4ee ist on Page ,1.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
+8. :ne way of reducing project costs is identifying tasks that can do themse!es. %. endors '. 4uppiers C" Customers D. Company empoyees *. Project teams :ne way of reducing project costs is identifying tasks that customers can do themse!es. )omeowners fre2uenty use this method to reduce costs on home impro!ement projects. Bor e#ampe to reduce the cost of a "athroom remode a homeowner may agree to paint the room instead of paying the contractor to do it. :n &4 projects a customer may agree to take on some of the responsi"iity for testing e2uipment or pro!iding in-house training.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: *s the *sse+ Learning Objective: ,ot %ime Learning Objective: -hat if Cost Level: #asy
Chapter 09 - Reducing Project Duration
+. The most common method for shortening project time is to %. 4u"contract acti!ities '. Compromise the 2uaity C" %dd additiona staff and e2uipment D. 6ork o!ertime *. Reduce the project scope The most common method for shortening project time is to assign additiona staff and e2uipment to acti!ities.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: )edim
+9. 6hich of the foowing is not one of the more commony used options for cutting project costs7 %. Reduce project scope '. )a!e owner take more responsi"iity C" >o!ing the competion date further out D. 'rainstorming cost sa!ings options *. :utsourcing project acti!ities 6ays to cut costs are Reduce project scope ha!e the owner take more responsi"iity outsourcing project acti!ities or e!en the entire project " rainstorming cost sa!ings options.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: *s the *sse+ Learning Objective: ,ot %ime Learning Objective: -hat if Cost Level: )edim
Chapter 09 - Reducing Project Duration
,0. 6hich of the foowing is the most common method for shortening project time7 " %ssigning additiona staff and e2uipment '. 4u"contract work C. 4chedue o!ertime D. Reduce project scope *. Reduce the 2uaity The most common method for shortening project time is to assign additiona staff and e2uipment to acti!ities.
AACSB: Analytic Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
,1. %ccording to 'rooks5 ;aw adding more peope to a ate project is most ikey to ha!e which of the foowing impact7 %. Feep the project from sipping any further '. et the project "ack on schedue C" >ake the project sips further D. 'oth % and ' are correct *.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
Chapter 09 - Reducing Project Duration
,+. 6hich of the foowing is the easiest method for shortening project time7 %. %ssigning additiona staff and e2uipment '. 4u"contract work C" 4chedue o!ertime D. Reduce project scope *. Reduce the 2uaity The easiest way to add more a"or to a project is not to add more peope "ut to schedue o!ertime.
AACSB: Analytic Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
,,. 6hich of the foowing is not one of the techni2ues for acceerating project competion7 %. %ssigning additiona staff and e2uipment '. *sta"ish a core team C. Do it twiceEfast and correcty D. Reduce project scope #" % of these are accepta"e techni2ues %dding resources outsourcing project work scheduing o!ertime esta"ishing a core project team and the concept of do it twice - fast and correcty are options when resources are not constrained.
AACSB: Analytic Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
Chapter 09 - Reducing Project Duration
,. 6hen the project team is saaried which of the foowing is the preferred choice for acceerating project competion7 %. %ssigning additiona staff and e2uipment '. 4u"contract work C. 4chedue o!ertime D. 6ork onger hours #" 'oth C and D are preferred choices :!ertime and working onger hours is the preferred choice for acceerating project competion especiay when the project team is saaried.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
,3. The 4napshot from Practice GCe-Phone 6arsG is an e#ceent e#ampe of reducing project duration due to$ %. &mposed project deadines B" Time to market C. (nforeseen project deays D. )igh o!erhead *. &ncenti!e contracts There are many good reasons for attempting to reduce the duration of a project. :ne of the more important reasons today is time to market. &ntense go"a competition and rapid technoogica ad!ances ha!e made speed a competiti!e ad!antage. To succeed companies ha!e to spot new opportunities aunch project teams and "ring new products or ser!ices to the marketpace in a fash. Perhaps in no industry does speed matter as much as in the eectronics industry.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
Fill in the Blank Questions
Chapter 09 - Reducing Project Duration
,/. 6hen a poitician makes a pu"ic statement that a new "uiding wi "e a!aia"e in two years a?n@ duration has reduced the project duration. i$posed G&mposed deadinesG is another reason for acceerating project competion. Bor e#ampe a poitician makes a pu"ic statement that a new aw "uiding wi "e a!aia"e in two years.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
,8. &ntense go"a competition and rapid technoogica ad!ances com"ine to create a?n@ imposed project duration date. $arket &ntense go"a competition and rapid technoogica ad!ances ha!e made speed a competiti!e ad!antage. To succeed companies ha!e to spot new opportunities aunch project teams and "ring new products or ser!ices to the marketpace in a fash.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
,. The 4napshot from Practice which detaied the
AACSB: Analytic Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
Chapter 09 - Reducing Project Duration
,9. 4ometimes !ery high costs are recogni=ed "efore a project "egins and reducing these costs through shorter project durations "ecomes a high priority. o%erhead 4ometimes !ery high o!erhead costs are recogni=ed "efore the project "egins. &n these cases it is prudent to e#amine the direct costs of shortening the critica path !ersus the o!erhead cost sa!ings.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: #asy
0. The project cost is the sum of the indirect and direct costs. total see Bigure 9.3 on Page ,1.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
1. Costs such as super!ision administration consutants and interest are e#ampes of project costs. indirect &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
+. Costs such as a"or materias e2uipment or contractors are e#ampes of project costs. direct Direct costs commony represent a"or materias e2uipment and sometimes su"contractors.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: #asy
,. Direct costs are assigna"e directy to a project . !ork package Direct costs are assigned directy to a work package and acti!ity hence the term.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: #asy
. 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud the cost of the acti!ity. increase 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud add to the costs of the acti!ity.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
3. To shorten the duration of a project the project manager shoud imit the choices of acti!ities to just those which . are on the critical path 4ometimes !ery high o!erhead costs are recogni=ed "efore the project "egins. &n these cases it is prudent to e#amine the direct costs of shortening the critica path !ersus the o!erhead cost sa!ings. (suay there are opportunities to shorten a few critica acti!ities at ess than the daiy o!erhead rate. (nder specific conditions ?which are not rare@ huge sa!ings are possi"e with itte risk.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: )edim
/. The time for an acti!ity represents ow-costs reaistic efficient methods for competing the acti!ity under typica conditions. nor$al
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
8. 4hortening an acti!ity is caed . crashing 4hortening an acti!ity is caed crashing.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
Chapter 09 - Reducing Project Duration
. The direct costs for competing an acti!ity as eary as possi"e is caed its . crash cost The direct cost for competing an acti!ity in its crash time is caed crash cost. 'oth norma and crash times and costs are coected from personne most famiiar with competing the acti!ity.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
9. %n acti!ity5s is cacuated "y di!iding the rise "y the run. slope Cost 4ope K RiseARun
AACSB: Analytic Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
30. 4u"tracting an acti!ity5s norma cost from the crash cost wi cacuate an acti!ity5s . rise Rise K Crash cost -
AACSB: Analytic Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
31. 4u"tracting an acti!ity5s crash time from the norma time wi cacuate an acti!ity5s . run Run K
AACSB: Analytic Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
3+. 6hen considering whether to mo!e the project to its optimum cost-time position the manager shoud aso consider . risk 4houd the project owner or project manager go for the optimum cost-time7 The answer is G&t depends.G Risk must "e considered.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
3,. % network is considered to "e if it has a predominate critica path with no other path cose in terms of sack. insensiti%e There is a positi!e situation where mo!ing toward the optimum time can resut in !ery rea arge sa!ingsEthis occurs when the network is insensiti!e. % project network is insensiti!e if it has a dominant critica path that is no near-critica paths. &n this project circumstance mo!ement from the norma time point toward the optimum time wi not create new or nearcritica acti!ities.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
Chapter 09 - Reducing Project Duration
3. The easiest way to add more resources to a project is not to add more peope "ut to schedue . o%erti$e The easiest way to add more a"or to a project is not to add more peope "ut to schedue o!ertime.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: )edim
33. %ccording to adding more manpower to a ate software project makes it ater. Brooks& la! 'rooks5 aw$ %dding manpower to a ate software project makes it ater.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: )edim
3/. The easiest way to add more a"or to a project is not to add more peope "ut to add . o%erti$e The easiest way to add more a"or to a project is not to add more peope "ut to schedue o!ertime.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
Chapter 09 - Reducing Project Duration
38. is the rearranging of the project network ogic so that critica acti!ities are done in parae rather than se2uentiay. Fast'tracking Bast-Tracking >akes it possi"e to rearrange the ogic of the project network so that critica acti!ities are done in parae ?concurrenty@ rather than se2uentiay.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
3. is pro"a"y the most common response for meeting unattaina"e deadines. Reducing project scope Pro"a"y the most common response for meeting unattaina"e deadines is to reduce or scae "ack the scope of the project.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
39. &n the G&5 'et Hou...G 4napshot from Practice the draftsman won for making a !ery difficut deadine. tickets to a (asket(all ga$e 'rue Houng tes Danny that he knows this is going to "e a rush jo" "ut he is confident that he can do it. 6hen Danny "aks he responds G& te you what &5 make a "et with you. &f you are a"e to finish the design "y $00 &5 make sure you get two of the company5s tickets to tomorrow night5s Cetics-Fnicks "asket"a game.G Danny accepts the chaenge works fe!erishy to compete the assignment and is a"e to take his daughter to her first professiona "asket"a game.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: #asy
True / False Questions
Chapter 09 - Reducing Project Duration
/0. % rue of thum" for moderate- to high-technoogy firms is that a si#-month deay in "ringing a product to market can resut in a gross profit oss of a"out ,3 percent. TR)# Bor e#ampe a rue of thum" for moderate- to high-technoogy firms is that a si#-month deay in "ringing a product to market can resut in a oss of market share of a"out ,3 percent.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: )edim
/1. &mposed project durations amost aways eads to a higher-cost project than one panned with detaied scheduing of a the project5s acti!ities. TR)# G&mposed deadinesG is another reason for acceerating project competion. The project duration time is set whie the project is in its GconceptG phase "efore or without any detaied scheduing of a the acti!ities in the project. This phenomenon occurs !ery fre2uenty in practiceI (nfortunatey this practice amost aways eads to a higher cost project than one that is panned using ow-cost and detaied panning. &n addition 2uaity is sometimes compromised to meet deadines. >ore important these increased costs of imposed duration dates are sedom recogni=ed or noted "y project participants.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Rationale for Redcing !roject "ration Level: )edim
/+. >anagers ha!e se!era effecti!e methods for crashing specific project acti!ities when resources are not constrained. TR)# >anagers ha!e se!era effecti!e methods for crashing specific project acti!ities when resources are not constrained.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: O$tions for Accelerating !roject Com$letion Level: #asy
Chapter 09 - Reducing Project Duration
/,. &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest. TR)# &ndirect costs generay represent o!erhead costs such as super!ision administration consutants and interest.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !roject Cost"ration (ra$h Level: #asy
/. The tota cost for each possi"e duration of a project is the sum of a"or materias and e2uipment. F*S# Direct costs commony represent a"or materias e2uipment and sometimes su"contractors.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !roject Cost"ration (ra$h Level: #asy
/3. Direct costs are so named "ecause they can "e assigned directy to a work package and acti!ity. TR)# Direct costs are assigned directy to a work package and acti!ity hence the term. The idea assumption is that direct costs for an acti!ity time represent norma costs which typicay mean ow-cost efficient methods for a norma time.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
//. 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud add to the costs of the acti!ity. TR)# 'ecause direct costs are assumed to "e de!eoped from norma methods and time any reduction in acti!ity time shoud add to the costs of the acti!ity.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
/8. The sum of the costs of a the work packages represents the tota direct costs for the project. TR)# The sum of the costs of a the work packages or acti!ities represents the tota direct costs for the project.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
/. &ncenti!e contracts can make reduction of project time rewardingEusuay for "oth the project contractor and owner. TR)# &ncenti!e contracts can make reduction of project time rewardingEusuay for "oth the project contractor and owner.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Rationale for Redcing !roject "ration Level: )edim
Chapter 09 - Reducing Project Duration
/9. 4hortening an acti!ity5s duration is termed crashing . TR)# 4hortening an acti!ity is caed crashing.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
80. *#pected time for an acti!ity represents ow-cost reaistic efficient methods for competing the acti!ity under anticipated conditions. F*S#
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
81. Crash cost is the incrementa cost incurred when an acti!ity is reduced in duration. F*S# The direct cost for competing an acti!ity in its crash time is caed crash cost.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
8+. The cost sope of an acti!ity is cacuated "y di!iding the run "y the rise. F*S# Cost 4ope K RiseARun
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
8,. Crash time is the greatest time reduction possi"e under reaistic conditions. TR)# The shortest possi"e time an acti!ity can reaisticay "e competed in is caed its crash time.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: #asy
8. The higher the sope of an acti!ity the greater the cost to reduce its duration. TR)# % steeper sope means it wi cost more to shorten one time unit.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
83. Creating a Project Cost-Duration raph in the pre-project panning phase without an imposed duration is the "est time to use this too. TR)# Creating the graph in the preproject panning phase without an imposed duration is the first choice "ecause norma time is more meaningfu.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
8/. Crashing a more e#pensi!e acti!ity may "e wise if fewer inherent risks are in!o!ed. TR)# Crashing a more e#pensi!e acti!ity may "e wise if fewer inherent risks are in!o!ed.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: #asy
88. % project network is cassified as sensiti!e if it has a arge num"er of interacting paths. F*S# % network is sensiti!e if it has se!era critica or near-critica paths.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
Chapter 09 - Reducing Project Duration
8. Coecting crash times for a moderate-si=e project is reati!ey easy. F*S# Coecting crash times for e!en a moderate-si=e project can "e difficut.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !ractical Considerations Level: )edim
89. 6hie the reationship "etween norma and crash times is reay cur!iinear the assumption that it is inear is sedom a concern for practicing managers. TR)# 'ecause the accuracy of compressed acti!ity times and costs is 2uestiona"e the concern of some theoristsEthat the reationship "etween cost and time is not inear "ut cur!iinearEis sedom a concern for practicing managers.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
0. The accuracy of crash times and costs is fre2uenty rough at "est when compared with norma time and cost. TR)# Regardess of the comfort e!e the accuracy of crash times and costs is fre2uenty rough at "est when compared with norma time and cost.
AACSB: Reflective %hin&ing Bloom's: Knowledge Learning Objective: !ractical Considerations Level: #asy
Chapter 09 - Reducing Project Duration
1. :ne of the ad!antages of using a Project Cost-Duration raph is that it keeps the importance of indirect costs in the forefront of decision making. TR)# The creation of such a graph keeps the importance of indirect costs in the forefront of decision making.
AACSB: Reflective %hin&ing Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: #asy
Short ns!er Questions
+. &dentify and "riefy descri"e fi!e reasons for attempting to reduce the duration of a project. 1. imposed durations made "y top management +. market demands created "y competition and rapid technoogy ad!ances ,. incenti!e contracts that pay for eary project competion . reco!ery of unforeseen project deays 3. to reduce project costs "y reducing charges created "y high o!erhead costs /. to reassign key resources to other projects.
AACSB: Analytic Bloom's: Knowledge Learning Objective: Resorce Allocation )ethods Level: "ifficlt
,. &dentify and gi!e an e#ampe for "oth of the major categories that make up project costs. 1. &ndirect costsL super!ision administration consutants and interest and +. direct costsL a"or materias and e2uipment.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
. Draw a typica Project Cost-Duration raph and a"e the key eements. 4ee Bigure 9-1 in your te#t.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !roject Cost"ration (ra$h Level: )edim
3. 6hy is the project duration with the owest direct costs sedom the optimum duration for a project7 &ndirect costs those accumuating each day wi at some point outweigh the reduction in direct costs eading to an increase in tota costs. The Project Cost-Duration graph is a mode that demonstrates this.
AACSB: Analytic Bloom's: Knowledge Learning Objective: !ractical Considerations Level: "ifficlt
/. i!en an e2ua e!e of risk and the need to reduce o!era project duration why woud you not seect the acti!ity with the owest sope in the entire project network to crash first7 &f it is not on the critica path crashing it wi not reduce project duration.
AACSB: Analytic Bloom's: Knowledge Learning Objective: !ractical Considerations Level: "ifficlt
Chapter 09 - Reducing Project Duration
8. 6hat is crashing and incude a discussion of crash time and crash cost 7 Crashing is shortening an acti!ity5s duration. Crash time is the shortest reaistic time that an acti!ity can "e competed. Crash costs are the tota costs associated with the crash time.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
. )ow woud you cacuate an acti!ity5s sope and what does it represent7 %n acti!ity5s sope is the cost per unit of time to reduce its duration. &t is cacuated "y di!iding the rise "y the run.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
9. i!en that an acti!ity5s norma time and cost are ten days and 00 and its crash time is fi!e days and 00 what is the acti!ity5s sope7 ?crash cost-norma cost@A?norma time-crash time@ K ?00-00@A?10-3@ K 0 per day
AACSB: Analytic Bloom's: Com$rehension Learning Objective: Constrcting a !roject Cost"ration (ra$h Level: )edim
Chapter 09 - Reducing Project Duration
90. 6hat do we mean when we say that a project network is sensitive and why is that important to a project manager7 % network is sensiti!e if it has se!era critica or near-critica paths. This is important "ecause the P> cannot ony focus on the critica path due to the possi"iities of reati!ey sma acti!ity deays that wi cause other paths to "ecome critica.
AACSB: Analytic Bloom's: Com$rehension Learning Objective: !ractical Considerations Level: )edim
91. &dentify options for acceerating a project schedue when resources are not constrained. 1. outsourcing project work +. scheduing o!ertime ,. adding resources . esta"ish a core project team and 3. do it twice.
AACSB: Analytic Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: "ifficlt
9+. &dentify options for acceerating a project schedue when resources are constrained or the "udget is se!erey constrained. 1. fast-tracking +. critica chain ,. "rainstorming time sa!ers . reducing project scope 3. phase project dei!ery and /. compromise 2uaity.
AACSB: Analytic Bloom's: Knowledge Learning Objective: O$tions for Accelerating !roject Com$letion Level: "ifficlt