SADARA MIXED FEED CRACKER PROJECT METHOD STATEMENT FOR FIRE AND GAS DETECTOR INSTALLATION (FOR INSTRUMENTATION WORKS)
Document No. A554-E-103-IC-GEN-DOC-008 Revision:
0
Prepared by:
J.U. Saguagan
Reviewed by:
J.H Lee
Checked by QA/QC:
K. K. Akhter
Approved by:
S.H Joo
1
2
3
Owner Approved by: Revision Date:
19 FEB 13
Issue Purpose:
IFA
This document contains technical information that may be subject to the export control regulations of the United States and/or other jurisdictions. It may not be exported or re-exported except as authorized under applicable U.S. or other export control regulations.
Contains Confidential Information of SADARA Page 1 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
SUMMARY OF DOCUMENT REVISIONS Rev. No.
Date Revised
Section Revised
Revision Description
0
19 FEB 13
All
Initial Issue
Contains Confidential Information of SADARA Page 2 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
Table of Contents
Section
1.0
Topic
1.0
Purpose ……………………………………………………………………………. 4
2.0
Scope ………………………………………………………………………………. 4
3.0
Responsibilities ……………………………………………………………………. 4
4.0
References ……………………….…………………………………………………. 4
5.0
List of Acronyms ……………….…………………………………………………. 5
6.0
Method of Preparation ……………………….….………………………….……. 5
7.0
Safety Requirements …………………………………………………….………. 6
8.0
QA / QC Requirements ……………………….….…………………….…………. 7
9.0
Procedure ……………………….…………….………………………….…………. 8
PURPOSE Contains Confidential Information of SADARA Page 3 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
The purpose of this procedure is to ensure that all works regarding Fire and Gas Detector installation shall be done in accordance with the SADARA standards and all other applicable international codes and standards. 2.0
SCOPE The scope covers the steps to be followed for general installation of Fire and Gas Detector is intended for permanent installation in the plant. DAELIM and AIC shall ensure that the Construction Method Statement of procedures is adhered to the SADARA Standards with reference to SADARA specifications.
3.0
RESPONSIBILITIES The DAELIM Instrumentation Construction Manager is responsible to plan and schedule activities for the execution of work in co-ordination with client personnel. It is the responsibility of the Instrument QC inspector to carry out inspection. Check the physical condition of the materials before installation. Any damages found must be reported immediately to their immediate supervisor. The material personnel shall be responsible for the proper handling, storage and preservation of the incoming materials. Visually check for physical damage.
4.0
REFERENCES: A554-O-PRG-IC-GEN-BOD-003 : SADARA Instrument Basis of Design A554-F-PRG-SE-GEN-BOD-002
: Fire and Gas Detection System Basis of Design
A554-K-PRG-PE-GEN-PDD-001
: Project Design Data
A554-O-PRG-PR-GEN-BOD-001
: EH&S Basis of Design
RT-LPP-9.1
: Fire Detectors
RT-LPP-9.2
: Combustible Gas and Oxygen Detectors
G6A-0002-00
: DOW Global Instrument Administrative Guideline Contains Confidential Information of SADARA Page 4 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
G6A-0041-00
: DOW Global Instrument Job Specification Master Dictionary
NFPA 70 – National Electric Code NFPA 72 – National Fire Alarm and Signalling Code 5.0
LIST OF ACRONYMS F&G DAS
Fire and Gas Detection and Alarm Signalling System
EH&S
Environment Health and Safety
FACP
Fire Alarm and Control Panel
LPP
Loss Prevention Principle
PA/GA UPS
6.0
Public Address/General Alarm Uninterruptible Power Supply
METHOD OF PREPARATION: 6.1) Work permit shall be obtained before the installation work and appropriate work permit shall be used according to SADARA Work Permit Procedure. Furthermore Job Safety Awareness shall be conducted before starting the job. 6.2)
All tools and equipment shall be prepared and maintained in good working condition prior to installation activities.
6.3)
For the safety of workmen, workplace shall be evaluated first for any hazards like gas, falling debris, etc., and gas testing shall be performed whenever necessary or required.
6.4) Safeguards, warning signs and proper PPE shall be employed at all times. 6.5) Approved and latest IFC drawings shall be available and used for construction. 6.6)
All fire and gas system shall be as shown on approved drawing and shall be in accordance with SADARA requirements, specification and NFPA 72 requirements.
Contains Confidential Information of SADARA Page 5 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
6.7)
All open conduits or assembly shall be properly plugged with appropriate fittings.
6.8)
Special care shall be provided not to cause any damage to relevant surfaces during welding, drilling or bolting and Any damaged surfaces shall be repaired properly.
6.9)
Detectors shall be away from grease or silicone oils to prevent contamination.
6.10) Housekeeping shall be performed after daily working and all waste materials shall be segregated and disposed properly. 6.11) All installation and modification work shall be guided, monitored and checked by supervisor in charge to ensure that all works are in accordance with FEED requirements and specification. 6.12) Any deviation from the criteria indicated in specification, shall be submitted to FEED for review and approval prior to installation. 6.13) Prior to transportation of fire and gas detectors, the check of their tag number, size, type, model no. quantity, physical damage and accessories for fire and gas devices shall be made in warehouse to ensure that the material is in compliance with the requirement. Corrosion and cleanliness also shall be checked. At the same time a filed survey shall be performed to ensure working area is ready for the commencement of installation. 6.14) All fire and gas devices, including accessories, shall be secured firmly to the carrier to keep the safety during the transportation. 6.15)
Special care shall transportation.
be
taken
to
avoid
physical
damage
during
6.16) Foundation, penetration and embedded parts shall have been properly installed and inspected as shown on the latest approved IFC drawings and procedure prior to the device installation.
7.0
SAFETY REQUIREMENTS:
Contains Confidential Information of SADARA Page 6 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
7.1) 7.2) 7.3)
8.0
The safety officer shall verify all the necessary and applicable documents, related to the safest operation are in possession before commencing the job. Check adequacy and availability of all tools, before commencement of work executions. Safety procedures will be followed at all times. Wearing a suitable PPE requirement before starts of work.
QA/QC REQUIREMENTS: 8.1)
The Quality Control Program shall be as per DAELIM Project Procedures in conjunction with SADARA Mixed Feed Cracker Project Specification and Engineering Standard. The detailed inspection stages and methods shall be as per the approved Inspection and Test Plans.
8.2)
Test equipment shall conform to the vendor manufacturer’s recommendations, as stated in their manual operation and maintenance instructions. Test equipment will include special tools or are required for any particular type of testing equipments. Calibration certificate must be submitted to DAELIM prior to commencement of testing activities.
8.3)
Prior to commencing the installation work, the unit/s and its components shall be visually inspected for any damages during the transportation.
8.4)
Inspection and test plan shall be submitted for PMT & DAELIM’s review and approval.
8.5)
RFI’s shall be submitted 24 hours ahead of scheduled inspection date & time as per PMT & Daelim procedure. All necessary attachments must be attached on all submitted RFI’s.
8.6)
All material to be used or installed shall have approval from PMT and DAELIM prior to installations.
8.7)
Work execution, material and testing shall be monitored, witnessed and recorded in accordance to the inspection list, QC forms given by the applicable ITP.
8.8)
Instrument Inspector shall carefully check against IFC drawing for the following items. a.) Check for correct location. b.) Check for correct installation. c.) Check for correct size and material. d.) Check for any damages. Contains Confidential Information of SADARA Page 7 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
8.9) 9.0
e.) Check for area classification. f.) Check proper grounding. g.) Check equipment/ device identification mark. h.) Check maintenance accessibility. Relevant test and inspection forms shall be filled by QC inspector.
PROCEDURE 9.1
GENERAL REQUIREMENTS 9.1.1)
The F&G DAS system shall be designed and installed in accordance with local and international codes and standards, LPPs, EH&S Basis of Design, International Building and Fire Codes and National Fire Protection Association (NFPA) Codes.
9.1.2)
For the installation of the kinds of the panels, racks and junction boxes, like fire and gas control system, IFC Drawing (Method statement for panel and junction box installation) should be referred.
9.1.3)
For cable pulling and termination, IFC drawing (Method statement for cable pulling and termination) should be referred.
9.1.4)
For the cable tray and conduit installation, IFC drawing (Method Statement for Instrument Cable tray and Conduit installation) should be referred.
9.1.5)
The stanchion or support of fire and gas device shall be decided for its suitable height, orientation, location, considering the site situation, based on the fire and gas layout drawing and SADARA specification depending on the type of gas detectors.
9.1.6)
Orientation, elevation and direction of stanchion or support shall be checked and installed in an orderly manner, on the plot plan and installation detail drawings.
9.1.7)
Device installation generally shall be in strict compliance with the latest and approved IFC drawing. However the main requirements during F&G device installation are as follows; Detectors shall be installed on surfaces free from vibration. Detectors shall be fitted with guards to protect them from mechanical damage and the effect of rain, water wash, strong wind, dust sun and sand.
Contains Confidential Information of SADARA Page 8 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
Detectors shall be fitted with guards to protect them from mechanical damage and the effect of rain, water wash, strong wind, dust sun and sand. For lighter-than air gases, sensors should be sited above the level of the potential sources of release, whereas for the detection of heavier-than air gases or vapors, sensors should be sited below the potential sources of release. The detectors shall be oriented downwards. Especially the prevailing wind direction shall be considered. Accessibility shall be considered. Detectors shall be readily accessible for calibration. If necessary, access platforms shall be provided as needed. Contamination shall be considered. Detectors shall be protected from greases or silicone oils to prevent contamination and shall be located away from direct sprays of oils and other liquids. 9.2
FIRE DETECTION 9.2.1 PROCESS UNITS
Fusible plugs shall be installed on and/or around Equipment such as pumps, rotating machinery and vessels that will be protected with water spray systems.
Flame detectors shall be installed areas with a potential for 3 dimensional hydrocarbon fires.
Fire detection notification will be via the PA/GA and Plant Alarm System.
9.2.2 BUILDINGS
Smoke detectors shall be located in accordance with NFPA 72 in buildings such as offices, electrical areas (substations/Motor Control Centers etc), control rooms, warehouses, or other buildings that contain class-A fire hazards.
Buildings HVAC shall have two (2) duct mounted smoke detectors installed to intercept the air flow toward the return air openings. Both detectors must be in alarm condition to confirm the presence of smoke and shut down fans or blowers Contains Confidential Information of SADARA Page 9 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
and to close fire dampers. The detectors shall be placed upstream of filters and downstream from fans.
9.3
Early Warning Fire Detectors (EWFD) air sampling smoke detection systems may shall be installed to detect fire in the incipient stages. Early warming air sampling smoke detection systems are used in environments where downtime must be eliminated or minimized such as telecommunication rooms, computer rooms, warehouses or critical electrical rooms, such as switchgear and motor control rooms.
Manual alarm call points shall be located inside each building. Manual alarm call points are required at every exit (preferably at the location of a portable extinguisher). Locating and mounting of manual alarm call points shall be in accordance with NFPA 72.
Heat detectors shall be located in work areas that anticipate excessive amounts of dust, fumes, or high humidity that could cause false alarms by using smoke detectors.
The interior of each building shall have audible and visual alarms. Mounting and location of audible and visual alarms shall be in accordance with NFPA 72.
All building(s) shall have audible and visual alarms mounted on the exterior of the building. The visual (red) alarm shall be mounted in such a way that it is not blocked by other buildings or Equipment. The audible and visual alarms shall be suitable for the intended area classification.
GAS DETECTION 9.3.1 PROCESS AREAS
Point monitoring gas detectors will be installed to provide detection of flammable and/or toxic gas leaks or releases. Locations are subject to a review with Company and/or Company’s Representatives. Locations shall be based on gas properties, PFDs and heat and material balances for the various process Units.
Flammable gas detectors shall also be installed in process areas where the potential for any abnormal gas release exists.
Contains Confidential Information of SADARA Page 10 of 11
SADARA Mixed Feed Cracker
Document No: A554-E-103-IC-GEN-DOC-008 Revision: 0 Document Title: Method Statement For Fire and Gas Detector Installation Issue Purpose: IFA
Flammable gas detectors shall also be considered for process Equipment handling flammable fluids at or above autoignition temperature.
Infra-red type flammable gas detectors will mainly be used except in cases where a catalytic bead type detector is more suitable, such as in Hydrogen detection or in high temperature service.
Toxic gas detectors shall be the electrochemical cell type specific to the tpe of gas to be monitored.
Gas detection notification will be via the PA/GA and Plant Alarm System.
9.3.2 BUILDINGS
Two (2) flammable gas detectors shall be installed at every building HVAC fresh air intake. Outside fresh air supply intake dampers shall be closed and HVAC unit shall be shut down upon confirmed detection of flammable gas.
Toxic gas detectors may be required at a building HVAC fresh air intake dependent upon the buildings proximity to any process area containing toxic gases. Toxic gas detectors for buildings shall be located as required and after review with the Company.
Each building shall have audible and visual alarms and shall indicate gas alarm condition within the building. Mounting and location shall be in accordance with NFPA 72.
All building(s) shall have audible and visual alarms mounted on the exterior of the building. The visual (blue) alarm shall be mounted in such a way that it is not blocked by other buildings or Equipment. The audible and visual alarms shall be suitable for the intended area classification.