Information System Management A report on
Library Management System Software Cost Estimation Using COCOMO II Model
Submitted to Dr. Abu Turab Alam Course Instructor
Submitted by M. Kamran Zubairy Roll No.: 2005-3-21-4930
Library Management System Software Cost Estimation using COCOMO II
MBA (Executive), IoBM Date: 16 December, 2007
College of Business Management Letter of Authorization 16 Dec 2007
Dear Reader
As a students of IoBM, I have been authorized by Dr. Abu Turab Alam to prepare a term report on “Library Management System Software Cost Estimation using COCOMO II Model”. This report is an integral part of our course ‘Information System Management’ to be submitted by 16 Dec, 07. The report required an in-depth research to be conducted before compiling a detailed account of the underlying knowledge. All attempts have been made to provide you with an informational report detailing credible data and results to educate you on this subject.
Sincerely
M. Kamran Zubairy Roll No: 2005-3-21-4930 Phone: 0333-214-3970
Information Management System (Fall Semester) Institute of Business Management
Page 2 of 12
Library Management System Software Cost Estimation using COCOMO II
Letter of Transmittal 16 Dec 2007
Dr. Abu Turab Alam Course Instructor Institute of Business Management
Dear Dr. Alam Please find enclosed a report on “Library Management System Software Cost Estimation using COCOMO II Model” that you authorized me to prepare. This report provides an understanding of estimating software cost using COCOMO II model. Application composition model of COCOMO II has been used for this purpose. IEEE 830 SRS for the same software was provided by you to extract object points from. If there be any clarification demanded, I would appreciate a call on the contact number given below.
Sincerely
M. Kamran Zubairy Roll No: 2005-3-21-4930 Phone: 0333-214-3970
Information Management System (Fall Semester) Institute of Business Management
Page 3 of 12
Library Management System Software Cost Estimation using COCOMO II
Contents Letter of Authorization........................................................................................................................ 2 Letter of Transmittal............................................................................................................................3 Contents...............................................................................................................................................4 Introduction......................................................................................................................................... 5 Introduction to COCOMO II Model.....................................................................................................5 COCOMO II Sub-models................................................................................................................... 6 Object Points in Application Composition Model................................................................................6 Steps to calculate Efforts using Application Composition Model........................................................6 Screens..............................................................................................................................................7 Reports.............................................................................................................................................. 7 Modules............................................................................................................................................. 8 Total Weighted Object Points............................................................................................................ 8 Productivity Level...............................................................................................................................9 Reuse................................................................................................................................................ 9 Effort.................................................................................................................................................. 9 Total Software Cost Calculation...................................................................................................... 10 Cost Drivers..................................................................................................................................... 10 Software Cost.................................................................................................................................. 10 Total Cost Grid.................................................................................................................................10 Project Duration and Staffing...........................................................................................................12 Exponential Value (B)...................................................................................................................... 12 Sources............................................................................................................................................12
Information Management System (Fall Semester) Institute of Business Management
Page 4 of 12
Library Management System Software Cost Estimation using COCOMO II
Introduction This report is part of the course of Information System Management, which shows the usage and importance of SRS to the management and its team and moreover explains how to estimate the cost of such products. As future managers it is very important for us to learn how to estimate the cost of software products.
The main objective of this report is to estimate the cost of the software with the help of cost estimation modules.
A library management system software requirement specification is taken in order to estimate the cost of system
To understand the art and science of software cost estimation techniques, which as a future manager would be helpful for us in making educated decisions
Introduction to COCOMO II Model
COCOMO II allow for spiral development model instead of waterfall model only
Use Function Points, Object Points and LOC for Sizing
COCOMO II includes same activities as COCOMO 81 o
development activities are included: documentation, planning & control, software configuration management (CM)
o
excluded: database management, general CM, Management
COCOMO II has add-on effort for back-end Transition Phase (conversion, installation, training)
Information Management System (Fall Semester) Institute of Business Management
Page 5 of 12
Library Management System Software Cost Estimation using COCOMO II
COCOMO II Sub-models There are following three sub-models in COCOMO II:
Application Composition Mode : prototyping, use of existing components, based on “Object Points”
Early Design Model : architectural design stage, closest to original COCOMO, uses Function Points as Size estimation
Post-Architecture Model :For actual development stage & Maintenance; Uses FPs or SLOC as size measure; Most detailed COCOMO II model
Object Points in Application Composition Model Object Point estimation is a relatively new software sizing approach, but it is well-matched to the practices in the Applications Composition sector. It is also a good match to associated prototyping efforts, based on the use of a rapid-composition Integrated Computer Aided Software Environment (ICASE) providing graphic user interface builders, software development tools, and large, composable infrastructure and applications components. In these areas, it has compared well to Function Point estimation on a nontrivial (but still limited) set of applications. Following are some of the highlights of objection point model:
Object points are alternative measure to function points when similar languages are used for development.
Object points are easier to estimate from a specification rather than function points, as they are simply concerned with screens, reports, and programming language modules.
They can therefore be estimated at a fairly early point in the development process.
The number of object points in a program is weighted estimate of: o
The number of separate screens that are displayed.
o
The number of reports that are produced by the system
o
The number of program modules that must be developed to supplement the database code.
Steps to calculate Efforts using Application Composition Model 1.
Assess Application Counts: estimate the number of screens, reports and 3GL components
2.
Classify each element instance to simple, medium and difficult complexity levels
3.
Weigh the number in each cell. The weights reflect the relative effort required to implement an instance of that complexity level
Information Management System (Fall Semester) Institute of Business Management
Page 6 of 12
Library Management System Software Cost Estimation using COCOMO II 4.
Determine Application Points = add all the weights to get 1 number, the Application Point Count
5.
Estimate the percentage of reuse & compute the New Application Points (NAP) to be developed
6.
Determine a productivity rate
7.
Compute the estimated person-months
Screens The complexity of the screens can be judged by the following:
Simple Screen counts as 1 Object Point. Moderately Complex Screen counts as 2 Object Points. Highly Complex Screens counts as 3 Object Points.
The number of separate screens that are displayed in the system are as follows:
Object Section
Library user account manage system Book borrowing system Book recall system Search book record Subtotal Total
Simple Count Wt Total . 2 1 2 2 1 2
Medium Count Wt Total . 1 1 2
2 2 2
2 2 4 8
4
Complex Count Wt Total . 1 1
3 3
3 3 6 18
Reports The complexity of the report generation can be judged by the following:
Simple Report counts as 2 Object Point. Moderately Complex Reports counts as 5 Object Points. Highly Complex Reports counts as 8 Object Points.
The number of separate reports that are generated by the system are as follows:
Object Section
Simple Count Wt Total .
Sign out books report Overdue books and penalty report Patron report Book purchase report Report printing and export Subtotal Total
Information Management System (Fall Semester) Institute of Business Management
Medium Count Wt Total . 1 1
5 5
Complex Count Wt Total . 1 8 8
5 5 1 1 10
8 8
8 8 24 34
Page 7 of 12
Library Management System Software Cost Estimation using COCOMO II
Modules Modules are imperative programming language code that must be developed to supplement the database access and decision logic blocks. The number of separate modules that are required by the system are as follows: Object Section
Data Entry Library user account manage system Book borrowing system Book recall system Search book record Update book database Subtotal Total
Simple Count Wt Total . 2 2 4 1 2 2 4 2 8 1 2 2 1 2 2 18
Medium Count Wt Total . 1 5 5 1 5 5 3 5 15 1 5 5 1 5 5 2 5 10 45
Difficult Count Wt Total . 1 10 10 1 10 10 1 10 10 1 10 10 1 10 10 50 113
Total Weighted Object Points Simple Medium Difficult Total
Screens 4 8 6 18
Reports 10 24 34
Modules 18 45 50 113
Total 22 63 80 165
Total Number of Screens + Total Number of Reports Generated + Total Modules Used by the System => 18 + 34 + 113 => 165 –> Total Weighted Object Points (NAP)
Information Management System (Fall Semester) Institute of Business Management
Page 8 of 12
Library Management System Software Cost Estimation using COCOMO II
Productivity Level The table has been generated to show the levels of object point productivity. OBJECT POINT PRODUCTIVITY Developer's Experience and Capability Very Low Low Nominal CASE Maturity and Capability Very Low Low Nominal PROD (NOP/Month) 4 7 13
High High 25
Very High Very High 50
Reuse - User account management module – 5% of the code - Date entry via calendar – 2% of the code - Total Reuse of code = 7%
Effort PM = [NAP * (1 - % reuse/100)] / PROD Where: NAP = 165 Reuse% = 7% Therefore: => [165 * (1 – 0.07)] / 25 => 6.138 ~ 6 Person-Months
Information Management System (Fall Semester) Institute of Business Management
Page 9 of 12
Library Management System Software Cost Estimation using COCOMO II
Total Software Cost Calculation There are three components taken into account for calculating the Total Software Cost of the project, which are as follows:
The cost of the hardware for executing the system. The cost of the platform (computer plus software) to develop the system. The cost of the effort required to develop the system.
Cost Drivers Cost Driver RELY CPLX DOCU TIME ACAP PCAP PCON LTEX TOOL SITE
Type
Description Very Low
Product Product Product Computer Personnel Personnel Personnel Personnel Project Project
Required system reliability Complexity of system modules Extent of documentation required Execution time constraint Capability of project analysts Programmer capability Personnel continuity Language and tool experience Use of software tools Extent of multi-site working
Low
0.75 0.75 0.89 1.5 1.37 1.24 1.22 1.24 1.25
0.88 0.88 0.95 1.22 1.16 1.1 1.1 1.12 1.1
Rating Normal High 1 1 1 1 1 1 1 1 1 1
1.15 1.15 1.06 1.11 0.83 0.87 0.92 0.91 0.86 0.92
Very High
Extra High
1.39 1.3 1.13 1.31 0.67 0.74 0.84 0.84 0.72 0.84
1.66 1.67
0.78
Software Cost SC = Effort Estimate x RELY x CPLX x DOCU x TIME x ACAP x PCAP x PCON x LTEX x TOOL x SITE x Rs. 100,000
=> 6.138 PM x 1.15 x 0.88 x 1.06 x 1.11 x 0.83 x 0.87 x 0.84 x 0.84 x 0.86 x 0.84 x Rs. 100,000 => Rs. 269,010.9
* Estimated Average Cost of One Person-Month is Rs 100,000, which covers salaries and operational expenses per person.
Total Cost Grid Total Cost Factor RELY CPLX DOCU
Description Required system reliability Complexity of system modules Extent of documentation required
TIME
Execution time constraint
1.11
ACAP
Capability of project analysts
0.83
PCAP
Programmer capability
0.87
PCON
Personnel continuity
0.84
Information Management System (Fall Semester) Institute of Business Management
Value 1.15 0.88 1.06
Page 10 of 12
Library Management System Software Cost Estimation using COCOMO II LTEX
Language and tool experience
0.84
TOOL
Use of software tools
0.86
SITE
Extent of multi-site working
0.84
Total Effort
6.14 PM
Software Cost
Rs. 269,010
Hardware Cost
Rs. 300,000
Total Cost
Rs. 569,010
* Estimated Hardware Cost is Rs. 300,000 (assuming purchase of 10 PCs at the cost of Rs. 30,000 per PC.)
Information Management System (Fall Semester) Institute of Business Management
Page 11 of 12
Library Management System Software Cost Estimation using COCOMO II
Project Duration and Staffing The project managers also estimate how long the software will take to develop and when staff will be needed to work on the project. Through the COCOMO Model, the following formula is used to estimate the Calendar Time (TDEV) that is required to complete the project: TDEV = 3 x [PM ^ {0.33 + 0.2 * (B – 1.01)}] * PM is the effort computation. * B is the exponent. * This computation predicts the nominal schedule for the project.
Exponential Value (B) In COCOMO II, a continuous range of values is possible for exponent B. This exponent is based on five scale factors (rated on a six-point scale from Very low (5) to Extra high (0)). The rating is then added and divided by 100 and then added to 1.01 to get the exponent. Following are the scale factors and their ratings as per the project of Library Management System:
Exponent Calculation Exponent Factor Precedentedness Development flexibility Architecture/risk resolution
Description Required system reliability
Value 3
Complexity of system modules
1
Extent of documentation required
5
Team cohesion
Execution time constraint
2
Process maturity
Use of software tools
2
Total Rating Divide by 100 and Add to 1.01
13 1.14
Therefore, the Exponential Value would be: Therefore: TDEV = 3 x [6 ^ {0.33 + 0.2 * (1.14 – 1.01)}] => 5.68 ~ 6 Months Thus, the project will take an estimated time of 6 months to be completed.
Sources
http://yunus.hun.edu.tr/~sencer/objectp.html http://sern.ucalgary.ca/courses/seng/621/W98/johnsonk/cost.htm
Information Management System (Fall Semester) Institute of Business Management