Theory and practice of riser and mooring dynamics
Mooring System Analysis Mooring System Design
Morning
Layout and geometry Line type -- catenary, semi-taut and taut-leg Properties – selection of chain, wire and synthetic rope or combination Anchor/pile selection Load-elongation curve for each line Offset curves for the layout Static, quasi-static and dynamic mooring system analyses Loading on lines vs. line breaking strengths FOS vs. Guidelines Mooring line fatigue assessment
48
Theory and practice of riser and mooring dynamics
In the process of design of the offshore system, For the mooring lines, first select
♦
layout
♦
geometry
♦
mechanical and structural properties (initial)
Layout of Mooring Lines
Morning
49
Theory and practice of riser and mooring dynamics
Morning
50
Theory and practice of riser and mooring dynamics
Mooring Configuration
Taut vs catenary mooring spread (symmetric)
Taut mooring system: restoring force primarily from line stretch Conventional catenary system: restoring force primarily from changes in catenary shape
Riser corridors between non-symmetric spread
Morning
51
Theory and practice of riser and mooring dynamics
Morning
52
Theory and practice of riser and mooring dynamics
Geometry of mooring lines Mooring Hardware Components Typical Chain geometry (a) Stud-Link
(b) Studless Chain
•
Wire or Rope Geometry (unsheathed or sheathed)
six strand
multi strand
s iral strand
Note: Sheathed wire ropes are of smooth cylindrical shape
Morning
53
Theory and practice of riser and mooring dynamics
Design of Mooring Lines Three possible methods: Static design Quasi-static design Dynamic design
Static Design Uses only the static environmental loads ignoring dynamic forces. Steps Input line end-point coordinates, lengths and unit weight of line. Sum forces for all lines in the mooring spread. Determine design wind, current, and wave data for site Find displacement of vessel for the load from the offset curve Line length is insufficient or the line becomes taut. Compute the safety factor (FOS) for the most heavily loaded line based on the breaking strength. FOS is too low.
Assume that the most loaded line is broken.
Morning
Outcome Line forces vs. displacement for each catenary line. Net horizontal and vertical restoring forces (offset curves) for the vessel. Compute steady forces on the vessel due to design environment Compute the tension of the most loaded line in the mooring spread. Increase the line length and repeat the above steps. Compare with design guides.
adjust suitable parameters in line pre-tension, material specification, line end co-ordinates or number of lines and repeat the above steps. Carry out the above steps and check FOS on heavily loaded line.
54
Theory and practice of riser and mooring dynamics
Quasi-Static Design Uses maximum dynamic loads as well as static, assuming all as static load.
Follow static steps. In addition
compute max wave loads and vessel motion at wave and slow-drift frequency
Compute maximum excursion and peak line tensions
Compare maximum line tensions vs. allowable safety factor (generally 2)
Use separate safety factors for the mean and dynamic loads (DNV)
If it fails the safety factor test, then try a new specification
Recalculate maximum peak line loads with one line broken NO
Acceptable Design? YES
Note: Mean loads are more reliably predictable separate FOS avoids excess conservatism. Morning
55
Theory and practice of riser and mooring dynamics
Dynamic Design In addition to steady loads, includes, the time-varying environmental loads on the mooring lines themselves
Establish a static configuration
Calculate platform motions independent of line dynamics
Include line top-end oscillation
Apply numerical scheme (lumped mass, FE or FD) to model line segments
De-compose line into straight elements (bars) with linear shape function
Lump distributed mass with added mass at end nodes
Include relative motion hydrodynamic damping
Include inertial effects between the line and fluid
NO
Acceptable Design? YES
Note:
♦ ♦ ♦ Morning
A time domain analysis is sought Damping levels vary significantly depending on water depth, line make up, offsets and top-end excitation. The influence of the last item is generally small. 56
Theory and practice of riser and mooring dynamics
Loading Mechanisms on Floater and Mooring Lines
Loads on Floater ♦ Steady and fluctuating wind ♦ Wave and wave drift ♦ Current
Morning
Loads on Mooring Lines ♦ Top end surge motion (small heave) ♦ Wave ♦ Current ♦ Seabed friction
57
Theory and practice of riser and mooring dynamics
Static Catenary Equation Definition of the single component catenary line Tv T (tension)
water line
φ (angle)
fairlead
TH
d scope, s
Single component line
chain Anchor
TDP xB
ocean floor x
h
Six (plus one) independent variables are: w = weight of line per unit length ≈ 0.87x (weight in air) for steel T = pretension at fairlead φ = fairlead angle h = horizontal component of catenary length (not including x B) d = vertical component of catenary length s = length of catenary called scope plus x B = component of line on bottom Also, (the following two items depend on T and φ ): T H = horizontal component of tension at fairlead T V = vertical component of tension at fairlead ASSUMPTIONS: (1) Seafloor is assumed flat; (2) Line segments are non-buoyant; and (3) Stretching of line is linear and follows Hooke’s law Two possible cases: Catenary: line resting on seafloor x B > 0, TBV = 0, xB = length of line on bottom Taut: line off the seafloor x B = 0, T BV > 0, TBV = vertical reaction at the anchor Morning
58
Theory and practice of riser and mooring dynamics
Single line (no stretching ) Consider the following free-body diagram Free body diagram Ti xi, yi
θ ι
s0 0
current
, Fairlead angle
weight xi+1, yi+1
θ ι+1
Ti+1
For a static analysis in the absence of any external force, the two equilibrium equations (based on the notation in Fig. 10 become: Horizontal:
T i cosθ i
− T i +1 cosθ i +1 = 0
Vertical:
T i sin θ i
− T i +1 sin θ i +1 + wi = 0
which may be solved for tension and angles of subsequent elements as follows:
T i +1
= [(T i cosθ i ) 2 + (T i sin θ i − wi ) 2 ]
1/ 2
and
tan θ i +1 =
T i sin θ i
− wi
T i cos θ i
=
T V i
− wi
T Hi
Then, knowing the coordinates of the upper end of the element ( xi ,yi), the corresponding coordinates for the lower end becomes Morning
59
Theory and practice of riser and mooring dynamics
xi +1 = xi
yi +1
l
− i [cos θ i + cos θ i +1 ] 2
l
= yi − i [sin θ i + sin θ i +1 ] 2
This calculation continues with the subsequent element until yi+1 just exceeds - d , where the d is the supplied depth of the line.
For a catenary line with portions on the bottom, the solution can be obtained in closed form using catenary equations. Basic catenary equation:
y = y0 cosh( x / y0 ) y0
= elevation at x = 0 s ( x) = (T H / w) sinh( wx / T H )
suspended line length along catenary s(x)
d ( x ) = (T H / w)[cosh( wx / T H ) − 1]
vertical line dimension along catenary d(x) for total lengths, use x = h in above equations
T H =
top tension of the line
or
T =
w( s 2
− d 2 )
2d w( s 2 + d 2 ) 2d T − T H
which reduce to
d =
horizontal component of line tension
T H = T cosφ
(2)
vertical component of line tension at top
T V = T sin φ = ws
(3)
Horizontal span of the suspended portion of line
h=
Morning
60
w
T H w
log
T A
(1)
− T VA T H
(4)
Theory and practice of riser and mooring dynamics
6 (or 7) unknowns and 3 equations; need 3 (or 4) input variables, e.g., w = weight of line per unit length T 0= initial tension at fairlead, and d = mooring line depth L = total line length or x B = line length on bottom Note that Eqs. 2 and 3 are dependent equations, but easier to use separately for the solutions. For solution, follow the steps below: Use Eq. 1 to compute T H Note: T H is constant at any point along the catenary, while T v varies. Use Eq. 2 to compute the initial fairlead angle φ A Use Eq. 3 to compute the initial suspended line length s Use Eq. 4 to compute the horizontal span h Compute xB, the line laying on the bottom, using s and L. Increment T H and repeat the above steps. Compute the excursion based on the initial configuration. Plot load vs. excursion (line stiffness curve)
Morning
61
Theory and practice of riser and mooring dynamics
Typical Example of a Single Catenary variable input unit weight of chain w pretension T 0 depth of line from fairlead d anchor line on bottom xB0
values 1.5 1300 450 700
units kN/m kN m m
The initial catenary will have the following properties: T H 0 T V0 φ 0 s0 h0 s0+ xB0
625.0 1139.9 61.3 759.9 567.5 1459.9
kN kN deg m m m
Horz. Tension Vert. Tension Fairlead Angle Length (scope) Horz. Span Total chain length
The sample output values for the catenary are obtained by setting the horizontal fairlead tension and determining the line excursion and the remaining line length on the bottom. TH kN 625.0 650 750 850 950 1050 1150 1250 1350 1450 1550 1650 1750 1850 1950 2050 2150 2250 Morning
T kN 1300 1325.0 1425.0 1525.0 1625.0 1725.0 1825.0 1925.0 2025.0 2125.0 2225.0 2325.0 2425.0 2525.0 2625.0 2725.0 2825.0 2925.0
TV kN 1139.9 1154.6 1211.7 1266.1 1318.4 1368.6 1417.1 1463.9 1509.3 1553.4 1596.3 1638.0 1678.7 1718.5 1757.3 1795.3 1832.5 1869.0
φ deg 61.3 60.6 58.2 56.1 54.2 52.5 50.9 49.5 48.2 47.0 45.8 44.8 43.8 42.9 42.0 41.2 40.4 39.7
s m 759.9 769.7 807.8 844.1 878.9 912.4 944.7 976.0 1006.2 1035.6 1064.2 1092.0 1119.2 1145.6 1171.5 1196.9 1221.7 1246.0 62
h Excursion xB m m m 567.5 0.0 700.0 580.2 2.9 690.2 628.6 13.3 652.2 673.8 22.1 615.8 716.2 29.7 581.0 756.4 36.4 547.5 794.6 42.3 515.2 831.1 47.6 484.0 866.2 52.4 453.7 899.9 56.7 424.3 932.4 60.7 395.7 963.9 64.3 367.9 994.3 67.6 340.8 1023.9 70.7 314.3 1052.7 73.6 288.4 1080.7 76.3 263.1 1108.0 78.8 238.3 1134.6 81.1 213.9
Theory and practice of riser and mooring dynamics
2350 2450 2550 2650 2750 2850 2950 3050
3025.0 3125.0 3225.0 3325.0 3425.0 3525.0 3625.0 3725.0
1904.8 1939.9 1974.4 2008.3 2041.6 2074.4 2106.7 2138.5
39.0 38.4 37.8 37.2 36.6 36.1 35.5 35.0
1269.8 1293.3 1316.2 1338.8 1361.1 1382.9 1404.5 1425.7
1160.7 1186.2 1211.2 1235.6 1259.6 1283.1 1306.3 1329.0
83.3 85.4 87.4 89.2 91.0 92.7 94.3 95.8
190.1 166.7 143.7 121.1 98.9 77.0 55.5 34.3
The load-excursion curve for the catenary line is shown in Fig. 11. Note that the curve is nonlinear. It is assumed in the curve that the line is catenary and a portion of line remains on the bottom throughout its range. 3500.0
2800.0
k , d a o L
2100.0
1400.0
700.0
0.0 0.0
20.0
40.0
60.0
80.0
Excursion, m
Figure 11. Load-excursion curve for a single catenary line
Morning
63
100.0
Theory and practice of riser and mooring dynamics
Two line catenary
Three component line
Definitions: See preceding figure for multiple lines α = angle at the top of second line segment w1 = unit submerged weight of top line segment w2 = unit submerged weight of bottom line segment
total line length s
s = s1 + s2 line 1 –Top line
tensions T H and T V
T H = T cos φ ; TV
= T sin φ
(5)
line length s1
T H
w1 x1 + w2 x2 w2 x2 s1 = sinh − sinh w1 T T H H
(11)
vertical dimension d1
d 1
=
T H w1
w1 x1 + w2 x2 − cosh w2 x2 T H T H
cosh
angle Morning
64
(10)
Theory and practice of riser and mooring dynamics
tan θ
w1 x1 + w2 x2 = sinh − tan α T H
line 2 Bottom line (same as single caternary)
vertical tension at fairlead T V
TV
= w1s1 + w2 s2
(6)
line length s2
s2
=
T H w2
sinh(
w2 x2
)
(7)
w2 x2 T H
(8)
T H
angle
tan α = sinh vertical dimension d2
d 2
=
T H w2
cosh(
w2 x2 T H
) − 1
(9)
NOTE: Clump weight or buoy may be added at the junction of the two lines giving an added vertical load at the joint.
Inputs:
w1 = unit weight of line 1 w2 = unit weight of line 2 T = Pretension at fairlead point (top of segment no. 1) φ = fairlead angle to x-axis s1 = segment 1 length L = total line length or x B = line length on bottom
Morning
65
Theory and practice of riser and mooring dynamics
Calculations for Two Line Catenary Steps: Compute T H , same for both lines (Eq. 5) Compute T V, vertical tension at fairlead (Eq. 5) Compute s2 = segment 2 length (Eq. 6) Compute x2 = segment 2 span (Eq. 7) Compute α = segment 2 top angle (Eq. 8) Compute d 2 = segment 2 depth (Eq. 9) Compute d 1 = segment 1 depth (Eq. 10) Compute x1 = segment 1 span (Eq. 11)
INPUT Unit weight, w1 Unit weight, w2 Pretension at fairlead (line 1) Fairlead angle to x-axis Line length, s1 Total catenary length
Ex. do not UNIT change 0.104 0.10 kips/ft 0.104 0.04 kips/ft 300 300.0 kips 61.3 60 deg 2530.1 2000.0 ft 5030.6
4000.0
ft
Horiz. tension, TH Vert. tension, Tv at fairlead Line length, s2 Total scope, s Bottom length, xB Horiz. span line 2, x2 w2*x2/TH tan (a) Top angle line 2, a Horiz. span line 1, x1 w1*x1/TH
144.1 263.1 0.1 2530.2 2500.4 0.1 0.000 0.00 0.0 1888.4 1.363
150.0 259.8 1295.2 3295.2 704.8 1270.7 0.339 0.35 19.1 1635.6 1.134
kips kips ft ft ft ft
Total span, h Line 2 depth, d2 Line 1 depth, d1 Total depth, d
1888.5 0.0 1499.5 1499.5
2906.3 217.4 1784.9 2002.3
check
61.3
Initial Catenary Properties
Morning
66
144 263.2 2530.4 2500
deg ft 1888.3 ft ft ft
1500
Theory and practice of riser and mooring dynamics
Single semi-taut line (no stretching ) Nine independent variables are: w = weight of line per unit length T = tension at fairlead T H = horizontal tension at fairlead T V = vertical tension at fairlead h = horizontal component of line length d = vertical component of line length s = curved length of line θ A = fairlead angle θ B = anchor angle Properties of semi-taut line: B = anchor point;
A = fairlead point;
s =
Scope
Horizontal fairlead tension
T H
T AV
Vertical fairlead tension
T BV
Vertical anchor tension
θ A
T AV − T BV
d =
Depth
Angles satisfy
=
w
T A − T B w s 2
− d 2
2 s
=
2dT A
=
2dT A
(2T A − wd )2 − w 2 s 2
+ w( s 2 − d 2 ) 2 s
− w( s 2 + d 2 ) 2 s
Horizontal component of tension
T AH Morning
= T A cos θ A ;
T BH 67
= T B cos θ B
> θ B ;
Theory and practice of riser and mooring dynamics
Vertical component of tension
T AV
= T AH tan θ A ;
T BV
= T BH tan θ B
9 unknowns and 5 independent equations; 4 input variables: w = weight of line per unit length θ A = fairlead angle s = line length d = vertical component of line length NOTES:
♦
The two cases of catenary and semi-taut line may switch back and forth under dynamic loads as the chain is picked up completely from the floor or settles down on floor.
♦
Semi-taut line with negligible stretch will move both in the horizontal and vertical direction with the vessel movement.
♦
When the line is completely taut, stretching will be needed to move it. In this case the angle throughout the line may be taken as the same.
Since stretching takes place along the entire shape of the mooring line under loading, and the stretched length or the shape of the line is not known apriori, a numerical procedure similar to the above may be adopted. In this case the stretching of a segment will occur based on the tensions at the two ends of the segment. Hooke’s law may be applied to obtain the stretch.
Morning
68
Theory and practice of riser and mooring dynamics
TYPICAL SINGLE SEMI-TAUT LINE (NO STRETCH) NOTE: Horizontal excursion of line will require a simultaneous vertical excursion
Sample input values unit weight of chain vertical depth of chain length (scope) initial tension at fairlead
w d s 0 TA
Initial Semi-taut Lines initial tension at anchor initial horizontal tension initial fairlead angle initial anchor angle
0.0489 170 1000.0 175.0
TB TH
θA θB
kips/ft or kN/m ft/m ft/m kips/kN
166.69 166.62 17.8 1.6
kips/kN kips/kN deg deg
2.0
2.5
400.0
350.0 p i k , n 300.0 o i s n e T 250.0 p o T
200.0
150.0 0.0
0.5
1.0
1.5
Excursion, ft
Morning
69
3.0
Theory and practice of riser and mooring dynamics
Offset Tension Curves of Mooring Lines Example Nansen SPAR in 3,678ft water depth The curve gives the top tension of the mooring line versus the horizontal offset of the fairlead point. Nansen SCR Case A, Offset-Tension Curves Lines 1, 4 and 7 3600 3200 ) s p i k ( n o i s n e T
2800
LINE NO. 1
2400
LINE NO. 4 LINE NO. 7
2000 1600 1200 800 400 0
-100 -75 -50 -25
0
25
50
75 100 125 150 175 200 225 250 275 300
Distance From Pretension Position (ft)
The curve gives the restoring force of the mooring line versus the horizontal offset of the fairlead point.
Restoring Characteristic of Mooring Lines Restoring Characteristic SCR Case A, Offset Direction Relative to Platform East
0 -4000 ) s p i k (
-8000
270° 315° 0° 45° 90° 180°
e -12000 c r o F -16000
-20000 -24000 0
25
50
75
100
125
150
175
200 2 25
250
275
Offset (ft)
Morning
70
300 3 25
350
Theory and practice of riser and mooring dynamics
Example Quasi-static Mooring System Design Example 1
Consider an 8-point catenary spread mooring system for a semisubmersible [adopted from Offshore Moorings, p.104]. Use a typical 1-year storm for the North Sea environment. 4
5 Catenary lines
3
6
Wave
Semi
2
7
1
8
Input data: Semi: 22000 T displacement Water depth = 155 m Survival draft Fairlead point 5m below SWL Two component lines – chain and wire 8 catenary lines of same geometry chain on top: 3” ORQ w (submerged weight) = 117 kg/m Breaking strength = 472 T Proof load = 313 T s1 length from fairlead to wire top = 850m wire at the bottom end: 3-1/2” 6x41 Breaking strength = 498 T 2 Elastic modulus on nominal CSA = 7000 kg/mm Elasticity of chain-wire combination = 32.7 T/m s2 length from chain bottom to anchor = 800m Morning
71
Theory and practice of riser and mooring dynamics
Environment: Wind: 1 hr mean = 34.0 m/s 1 min mean = 39.0 m/s Wave: HS = 12.1 m Hmax = 22.4 m TS = 13.3 s Current: Surface = 1.10 m/s 15 m depth = 0.84 m/s based on these environmental data, the mean environmental forces on the semi are computed at its nominal survival draft. The mean forces in a head sea case: load due to mean wind: hourly load due to mean wind: 1 min gust load due to mean wave drift load due to mean current
= 88 T = 114 T = 27 T = 46 T
Total (mean wind) = 161 T Total (1 min gust) = 187 T Mean steady displacement (1 min gust) = 24.2 m Compute the high frequency motions in surge for the head seas for the given wave spectrum as follows: Transfer function Response spectrum Most probable maximum surge amplitude = 8.4 m Mean static displacement (1 min gust) = 24.2 m Total displacement = 32.6 m Mooring line force (chain) = 210 T Safety factor (chain) = 2.25 Similar computation should be carried for other wave angles, e.g., beam and quartering seas, since the setup is not symmetric. Also, the analysis should be repeated for one broken line for the worst case from the above to check the safety factor. Morning
72
Theory and practice of riser and mooring dynamics
Example 2
Mooring arrangement for the floater in shallow water
Buoy Mooring System
Auxiliary surface buoy
Spar
Environment
Float Flounder plate Catenary
Morning
73
Theory and practice of riser and mooring dynamics
Choose a typical mooring line as a starting point: Stud Link Chain diameter = 1.25 inch Chain angle at the buoy = 45 degrees Vertical length = 5 meters (from buoy to the flounder plate) Catenary length = 132 meters (from the flounder plate to the foundation anchor) Chain virtual diameter = 3 x chain wire size CDN (normal)= 1.0 CDT (tangential) = 0.02 Environment Wind speed Wave Height Wave Period Surface current Bottom current Water Depth
Survival 80 knots 13.8 meter 12 seconds 3 knots 1 knots 40 meters
Maximum loading on the upstream leg Wind drag force Maximum hydrodynamic drag force Pull of the two downstream legs Total tension in the tether
1,400 lbs 48,000 lbs 12,000 lbs 61,000 lbs
Static Catenary solution (zero load): At the buoy end vertical tension = 1950 kg horizontal tension = 1950 kg and At the anchor end vertical tension = 0.0 kg horizontal tension = 1950 kg.
Morning
74
700 kg 21,800 kg 5,500 kg 28,000 kg
Theory and practice of riser and mooring dynamics
Computed tensions from the load: Location Buoy Flounder plate Anchor
Tension, kg 23472 27689 27267
Angle, degrees 35.49 69.05 75.34
Horizontal distance between anchor and buoy =128.3 meters.
Total tensions Location Vertical, kg Horizontal, kg Buoy 19,111 + 1,950 = 21,061 3,626 + 1,950 = 15 576 Flounder plate 9,900 + 1,850 = 11,750 25,858 +1,950= 27 808 Anchor 6,900 + 0.0 = 6,900 6,379 + 1,950 = 28 329
Choice of chain. The chain strength = 3 x tether tension = 183,700 lbs. Choose 1.25 inch, grade 3, stud link chain The immersed weight = 19.4 kg/m. Rated breaking strength of 184,000 lbs. (83 258 kg) Safety factor Highest tension occurs at the flounder plate = 30,000 kg. Breaking strength of the chain = 83,000 kg. Safety factor = 83,000/30,000= 2.75
Morning
75
Total, kg 26,194 30,271 29,157
Theory and practice of riser and mooring dynamics
Dynamic Mooring System Design Two step procedure Step 1: Vessel Motion Analysis For floating structure, mooring/ riser system is an external nonlinear stiffness term.
Step 2: Mooring & Riser Analysis For the flexible elements, motions of the floating structure are added to the attachment point as an externally defined oscillation.
Morning
76
Theory and practice of riser and mooring dynamics
Numerical Model for a Mooring Line partially on the seabed
♦ ♦ ♦ ♦ ♦ ♦ ♦ ♦
Morning
Mooring line divided into N segments (lumped mass system) Mass of each segment is lumped at the intersection point Line between the masses is massless elastic element. All forces at each mass are equated to the mass inertia Boundaries between masses are matched to the mooring line displacement Seabed supporting mooring line is a series of linear springs with dashpot The touchdown point is a variable during the oscillating excitation Flexural rigidity is negligible
77
Theory and practice of riser and mooring dynamics
Matrix equation for lumped mass
Inertia Force Matrix + Damping Force Matrix (includes hydrodynamic and soil damping) + Stiffness Force Matrix (includes tension, hydrodynamic and soil stiffness) = External Force Matrix External forces (considering only the fluid drag term):
f nj
=
1 ρ C Dnj D j u nj u nj 2
Example problem (Inoue and Surendran) Consider a chain in a catenary form with a portion on the bottom foundation soil. The catenary is subjected to a harmonic oscillation. The following input values for the experiment was chosen: Chain weight = 0.127 kg/m Chain equivalent diameter = 0.0059 m Chain length = 15 m Initial length of chain on seabed = 5.19 m Initial tension = 1.84 kgf Added mass = 1.98(normal) Added mass = 0.2(tangential) Top harmonic displacement amplitude = 0.04 m Properties of chain in different media Medium
Vert. stiffness Mass density Drag coeff. Drag coeff. 6 kgf/m (x 10 ) Kg/m^3 normal tangential water 0 1025 2.18 0.17 clay 2.25 1428 3.04 0.24 mud w/ sand 8.01 1538 3.27 0.26 mud 10.79 2000 4.25 0.33 Note: Modified drag coeff. = C Dwater *(medium density/ water density) Morning
78
Theory and practice of riser and mooring dynamics
Reduction in dynamic amplitudes w/ partial chain on seabed
Morning
79
Theory and practice of riser and mooring dynamics
A finite element approach: Free-body diagram of the line segment, i Ti θ ι
wave
FE free body diagram
current
weight
θ 0, Fairlead angle
θ ι+1
Ti+1
BE free body diagram
The equation of motion: inertia force + linear damping force + nonlinear damping force + soil damping + restoring force + soil restoring force = line tensions + mooring line weight + current force + wave force + soil force finite line element equation in the horizontal direction, x:
&&i mi x
+ c1i x&i + c2i x&i x&i + c soil x&i + k x i i + k soil xi = T i cosθ i − T i +1 cos θ i +1 + f ci+ f wi+ f soili
vertical direction, y:
&&i mi y
+ c1i y& i + c2i y& i y& i + c soil y& i + k y i i + k soil yi = T i sin θ i − T i +1 sin θ i +1 + wi + f ci+ f wi+ f soili
These equations are written in a matrix form and solved for the values for xi and yi. Morning
80
Theory and practice of riser and mooring dynamics
Mooring Line Fatigue Analysis Mooring line fatigue is based on long term cycle of dynamic tension due to time varying current and wave forces. Fatigue life estimates are made by comparing the loading in a mooring component with the resistance of that component to fatigue damage.
Choose appropriate T-N (tension vs. allowable number of cycles) design curves e.g., API RP 2SK:
= K
N R M Fatigue Design Parameters Component Common chain link Spiral strand rope
M 3.36 5.05
K 370 166
Fatigue Design Curves (API RP 2SK) 10000 s p i k , e g n a R n o i s n e T
1000
100
10 1.E+03
1.E+05
1.E+07
1.E+09
1.E+11
Number of Cycles Chain DIA=3.75
Chain DIA=4.00
Wire DIA=3.50
Miner’s Rule for cumulative damage ratio, D:
D
=∑
ni
N i
< 1.0
ni = number of cycles applied at each tension range N i = number of cycles allowed at the corresponding tension range Morning
81
Theory and practice of riser and mooring dynamics
Assume short-term tension peaks are represented by the Rayleigh distribution
p( s)
σ
2
exp ( −
s 2 2σ
2
)
compute damage for each load case:
D j
=
s
= N j ( 2
σ j
) M Γ(1 + M / 2) / K BS
Repeat calculations are for each fatigue load case Accumulated damage to obtain the total damage. The fatigue life is obtained from the inverse of the total damage.
Factors of Safety Dynamic Analysis Break Strength ABS BV DNV
FOS
Fatigue Life
1.82 2.0 1.82
Inspectable lines Un-inspectable lines Polyester rope
FOS 3 10 60
Variables: BS = breaking strength of line segment K = intercept of T-N curve M = slope of T-N curve ni = number of cycles within the tension range interval ‘i’, N = number of cycles N i = number of cycles to failure at the tension range ‘i’ as given by the appropriate T-N curve. N j = number of cycles for load case ‘j’ for a duration of 1 year R = ratio of tension range (double amplitude) to nominal breaking strength s = tension range Г = Gamma function σ = standard deviation of the tension range = 2 times the standard deviation of tension time history σ j = standard deviation of effective tension range for load case ‘j’
Morning
82
Dynamics of floating structure and model testing
References Statistics
1. Borgman, L. E., Ocean wave simulation for engineering design, Journal of Waterways and Harbors Division, ASCE, November 1969,557-583. 2. Bretschneider, C.L., Wave variability and Wave Spectra for Wind-Generated Gravity Waves”, Technical memorandum No. 118, Beach Erosion Board, US Army Corps of Engineers, Washington, DC, 1959. 3. Chakrabarti, S.K., Hydrodynamics of Offshore Structures, Computational Mechanics Publication, Southampton, U.K., 1987. 4. Hasselman, K.,”A Parametric Wave Prediction Model”, Journal of Physical Oceanography, Vol. 6, 1976, pp. 200-228. th
th
5. ITTC, Recommendations of the 11 International Towing Tank Conference, Proceedings 11 ITTC, Tokyo, 1966.
6. Longuet-Higgins, M.S., “On the Statistical Distribution of of the Heights of Sea Waves”, Journal of Marine Research, Vol. 11, 1952, pp. 245-266. 7. Ochi M.K., and Hubble, E.N., “Six Parameter Wave Spectra”, Proceedings of the Fifteenth Coastal Engineering Conference, Vancouver, BC, ASCE, 1972, pp. 301-328. 8. Ochi, M. K., Wave statistics for the design of ships and ocean structures, Transactions of the Society of Naval Architects and Marine Engineers 1978, 86, 47-76. 9. Pierson, W.J., and Moskowitz, L., “A Proposed Spectral Form for Fully Developed Wind Seas Based on the Similarity theory of Kitaigorodskii”, Journal of Geophysical Research, Vol. 69, No. 24, December, 1964, pp.5181-5203. 10. Proceedings of Second International Ship Structures Congress, Delft, Netherlands, 1964. 11. Walden, H., Comparison of one-dimensional wave spectra recorded in the German Bight with various "theoretical" spectra, Ocean Wave Spectra, National Academy of Sciences, Prentice-Hall, New Jersey, 1963, pp. 67-98. Mooring
1. ABS “Guidance Notes on The Application of Synthetic Ropes for Offshore Mooring”, American Bureau of Shipping, New York, Houston, 1999. 2. API, “Recommended Practice for Design and Analysis of Station Keeping Systems for Floating Structures, API RP 2SK, 2nd Edition, American Petroleum Institute, Washington, DC, 1996. 3. API, Recommended Practice for Design, Analysis and Testing of Synthetic Fiber Ropes in Offshore Mooring Applications, API RP 2SM, Fourth Draft, August, 1999. 4. Asaland, M and B.E. Sogstad, “Certification of Fibre Ropes for Offshore Mooring”, 1999 Offshore Technology Conference Proceedings, OTC 10911, Offshore Technology Conference, Richardson, TX, 1999. Day1PM
83
Dynamics of floating structure and model testing
5. Banfield, S.J., J.F. Flory, J.W.S. Hearle and M.S. Overington, “Comparison of Fatigue Data for Polyester and Wire Ropes Relevant to Deepwater Moorings”, Proceedings of 1999 OMAE Conference”, ASME, New York, 1999. 6. BV, “Guidance Note, Certification of Synthetic Fibre Ropes for Mooring Systems”, NI 432 DTO R00E, Bureau Veritas, Paris, 1997. 7. Cupertino, CA, 1999. TTI/ND “Deepwater Fibre Moorings – An Engineer’s Design Guide”, Oilfield Publications Ltd., Herefordshire, UK, 1999. 8. De Pellegrin, Ivan, “Manmade Fiber Ropes in Deepwater Mooring Applications”, 1999 Offshore Technology Conference Proceedings, OTC 10907, Offshore Technology Conference, Richardson, TX, 1999. 9. Det Norske Veritas, Offshore Standard Position Mooring, DNV-OS-E301, June 2001. 10. DNV, “Standard for Certification of Offshore Mooring Fibre Ropes”, Det Norske Veritas, Hovik, Norway, 1998. 11. Flory, J.F., H.A. McKenna and M.R. Parsey, “Fiber Ropes For Ocean Engineering In the 21st Century”, Civil Engineering In the Oceans V Conference Proceedings, American Society of Civil Engineers, New York, 1992. 12. Francios, M, “Experience and Developments in Fibre Rope Mooring Certification”, Proceedings of 1999 ISOPE Conference, International Society of Offshore and Polar Engineering, Cupertino, CA, 1999. 13. Goldsmith, B., Burns, D., Das, S. (KBR), 2002 spread mooring systems and components for floating units, Poster, Offshore Magazine, Oct., 2002. 14. Huse, E., 1986, ‘‘Influence of Mooring Line Damping Upon Rig Motions,’’ Proc., 18th OTC Conference. 15. Inoue, Y., and Surendran, S., “Dynamics of the interaction of mooring line with the seabed”, th Proceedings of the 4 International Offshore and Polar Engineering Conference, Osaka, Japan, 1994, pp. 317-323. 16. Koralek, A.S. and J.K. Barton, “Performance of a Lightweight Aramid Mooring Line”, 1987 Offshore Technology Conference Proceedings, OTC 5381, Offshore Technology Conference, Richardson, TX, 1987. 17. Lee, M-Y, J.F. Flory and R. Yam, “ABS Guide for Synthetic Ropes in Offshore Mooring Applications”, 1999 Offshore Technology Conference Proceedings, OTC 10910, Offshore Technology Conference, Richardson, TX, 1999. 18. Lloyd’s “Fibre Ropes in Offshore Mooring Systems”, LR Report OS/TR/97008 (draft), Lloyd’s Register Offshore Services, London,, 1999. 19. OCIMF “Guide to Purchasing Hawsers”, “Procedures for Quality Control and Inspection during the Production of Hawsers”, and “Guide to Prototype Rope Testing”, Oil Companies International Marine Forum, Witherby & Co., London, 1987. 20. OCIMF, “Hawser Standards Development Program, Trial Prototype Rope Tests, Draft Final Report, Oil Companies International Marine Forum, London, 1983. 21. OCIMF, Hawser Test Report, Data on Large Synthetic Ropes in the Used Condition, Oil Companies International Marine Forum, Witherby & Co., London, 1982. Day1PM
84