EMC® AX4-5F8 Architecture Architecture for NX4 Series
Replacing a Standby Power Supply This document describes how to replace a standby power supply (SPS) in the storage system in an NX4 system. Note: The
storage system in an NX4 system is an AX4-5F8.
Summary of tasks for replacing an SPS........................... SPS......................................... ............................. ............................. ............................ ............................. ............................2 .............2 Handling field replaceable units (FRUs)............................ (FRUs).......................................... ............................ ............................. ............................. ............................ .........................3 ...........3 Disabling CallHome or ConnectHome and Email notifications......................................................................5 Shutting down power and removing the cables............................. cables........................................... ............................ ............................. ............................. .........................7 ...........7 Unlocking and removing the SPS front bezel............................ bezel.......................................... ............................. ............................. ............................ ............................. ................8 .8 Removing the front plate........................... plate.......................................... ............................. ............................ ............................. ............................. ............................ ............................. .......................9 ........9 Removing a standby power supply............................ supply........................................... ............................. ............................ ............................. ............................. ............................ ................10 ..10 Installing a standby power supply........................... supply......................................... ............................. ............................. ............................ ............................. ............................. ..................11 ....11 Reconnecting Cables and Powering up the SPS........................... SPS.......................................... ............................. ............................ ............................. ..........................12 ...........12 Installing the front plate............................ plate........................................... ............................. ............................ ............................. ............................. ............................ ............................. .....................13 ......13 Installing and locking the SPS front bezel........................... bezel......................................... ............................. ............................. ............................ ............................. .....................14 ......14 Verifying the operation of a new or replacement part...................................... part.................................................... ............................. ............................. ..................15 ....15 Restoring trespassed virtual disks or LUNs using the CLI ............................................................................17 Checking system status........................... status......................................... ............................. ............................. ............................ ............................. ............................. ............................ .......................18 .........18 Enabling CallHome Cal lHome or o r ConnectHome and Email notifications............................ notifications.......................................... ............................ ............................19 ..............19 Returning the failed part........................... part.......................................... ............................. ............................ ............................. ............................. ............................ ............................. .....................23 ......23
Summary of tasks for replacing an SPS
Summary of tasks for replacing an SPS To replace an SPS you must complete the tasks below in the order in which they appear. This document provides instructions for completing each task. 1. Disable CallHome or ConnectHome. ConnectHome. 2. Shut down the failed SPS and remove remove all cables. 3. Unlock and remove remove the bezel. bezel. 4. Remove Remove the front front plate. plate. 5. Remove Remove the failed failed SPS. SPS. 6. Install Install the replac replacemen ementt SPS. 7. Reinstall Reinstall the the front front plate. plate. 8. Reconnect cables cables and power power up the replacement replacement SPS. 9. Reinstall Reinstall the the front front plate. plate. 10. Reinstall and lock the bezel. 11. 11. Verify the operation of the replacement SPS. 12. Restore any trespassed virtual disks or LUNs. 13. Check system status. 14. 14. Enable CallHome or ConnectHome. ConnectHome.
2
Replacing a Standby Power Supply
Handling field replaceable units (FRUs)
Handling field replaceable units (FRUs) This section describes the precautions that you must take and the general procedures that you must follow when removing, installing, and storing any field replaceable unit (FRU).
Power issues and FRUs Your storage system is designed to be powered on continuously. Most components are hot swappable; that is, you can replace or install these components while the storage system is running. Front bezels should always be attached and each compartment should contain a FRU or filler panel to ensure EMI compliance and proper air flow over the FRUs. You should not remove a faulty FRU until you have a replacement available. When you replace or install FRUs, you can inadvertently damage the sensitive electronic circuits in the equipment by simply touching them. Electrostatic charge (ESD) that has accumulated on your body discharges through the circuits. If the air in the work area is very dry, running a humidifier in the work area will help decrease the risk of ESD damage. Follow the procedures below to prevent damage to the equipment. Read and understand the following instructions: ◆
Provide enough room to work on the equipment. Clear the work site of any unnecessary materials or materials that naturally build up electrostatic charge,such as foam packaging, foam cups, cellophane wrappers, and similar items.
◆
Do not remove replacement or upgrade FRUs from their antistatic packaging until you are ready to install them.
◆
Before you service a storage system, gather together the ESD kit and all other materials you will need. Once servicing begins, avoid moving away from the work site; otherwise, you may build up an electrostatic charge.
◆
An ESD wristband is supplied with your storage system. To use it, attach the clip of the ESD wristband (strap) to any bare (unpainted) metal on the storage system; then put the wristband around your wrist with the metal button against your skin.
◆
Use the ESD kit when handling any FRU. If an emergency arises and the ESD kit is not available, follow the procedures in the Emergency procedures (without an ESD kit) on page 3.
Emergency procedures (without an ESD kit) In an emergency when an ESD kit is not available, use the procedures below to reduce the possibility of an electrostatic discharge by ensuring that your body and the subassembly are at the same electrostatic potential. These procedures are not a substitute for the use of an ESD kit. Follow them only in the event of an emergency.
Handling field replaceable units (FRUs)
3
Handling field replaceable units (FRUs)
4
◆
Before touching any FRU, touch a bare (unpainted) metal surface of the cabinet or storage system.
◆
Before removing any FRU from its antistatic bag, place one hand firmly on a bare metal surface of the storage system, and at the same time, pick up the FRU while it is still sealed in the antistatic bac. Once you have done this do not move around the room or touch other furnishings, personnel, or surfaces until you have installed the FRU.
◆
When you remove a FRU from the antistatic bag, avoid touching any electronic components and circuits on it.
◆
If you must move around the room or touch other surfaces before installing a FRU, first place the FRU back in the antistatic bag. When you are ready again to install the FRU, repeat these procedures.
Replacing a Standby Power Supply
Disabling CallHome or ConnectHome and Email notifications
Disabling CallHome or ConnectHome and Email notifications Open a HyperTerminal session with theCelerra system and then use procedure in thesection that follows for your EMCNAS version to disable CallHome or ConnectHome and Email notification.
Opening a HyperTerminal session with the system 1. At the rear of the cabinet, connect the null modem cable (P/N 038-003-458) fromthe serial port on the service laptop to the primary Control Station ( Figure 1 on page 5).
Figure 1. Control station serial connection
2. Open the HyperTerminal session using the following settings: Bits per second:
19200
Data bits:
8
Parity:
None
Stop bits:
1
Flow control:
None
Emulation:
Auto Detect
Telnet terminal ID:
ANSI
Note: If
you cannot connect to the HyperTerminal session, reboot the Control Station, log in, and repeat this step.
3. Login as nasadmin: login:nasadmin
4. Become the root user: $ su root Password:
Disabling CallHome or ConnectHome and Email notifications
5
Disabling CallHome or ConnectHome and Email notifications
For EMCNAS 5.6 or later Use a HyperTerminal session to disable ConnectHome: 1. From the root directory, disable CallHome: /nas/sbin/nas_connecthome stop
2. Disable the Email notification service: /nas/bin/nas_emailuser -modify -enabled
Sample output: OK
3. Verify that the Email notification service has stopped (is not enabled): /nas/bin/nas_emailuser-info
Sample output: Service Enabled = No Recipient Address(es) =
[email protected] Carbon Copy Address(es) = Email Server = emcmail.lss.emc.com Subject Prefix = Celerra Notification -NDU through NST Sender Address =
ConnectHome and Email notifications are now disabled. You are now ready to replace the part. After completing the part replacement procedure, be sure to enable ConnectHome and Email notifications.
6
Replacing a Standby Power Supply
Shutting down power and removing the cables
Shutting down power and removing the cables 1. Shut down power on the SPS that you are replacing by pressing the left side of the SPS power switch (Figure 2 on page 7).
Figure 2. Off position for the SPS power switch (SPS A shown)
2. Disconnect the SPS cables: Note: Label
the cables for reinstallation later.
a. Unplug the SPS power cord from the site power source and then from the SPS. b. From the SPS, unplug the sense cable and the power cord connecting the SPS to the SP directly above it.
Shutting down power and removing the cables
7
Unlocking and removing the SPS front bezel
Unlocking and removing the SPS front bezel 1. Unlock the front bezel by turning the key at the front of the enclosure counterclockwise. 2. Press the buttons on the front of the bezel and pull the bezel toward you to release it. 3. Save the bezel for reinstallation later.
Figure 3. Unlocking and removing the front bezel
8
Replacing a Standby Power Supply
Removing the front plate
Removing the front plate The front plate covers the front of the SPS tray. You must remove it to replace either SPS. 1. Remove the four or six screws on the front plate and remove the front plate (Figure 4 on page 9).
Figure 4. Removing the front plate
2. Save the front plate and screws for reinstallation later.
Removing the front plate
9
Removing a standby power supply
Removing a standby power supply 1. From the rear, remove the four screws that secure the SPS. 2. From the front of the cabinet, slide the SPS off the tray (Figure 5 on page 10).
Figure 5. Removing an SPS
10
Replacing a Standby Power Supply
Installing a standby power supply
Installing a standby power supply 1. Remove the SPS from its packaging. 2. From the front, slide the SPS onto the tray and into position (Figure 6 on page 11). 3. From the rear, secure the SPS with four screws that you saved either from removing the back plate (if you are adding a second SPS) or from removing from a failed SPS (if you are replacing an SPS).
Figure 6. Installing a standby power supply
Ins talling a s tandby power supply
11
Reconnecting Cables and Powering up the SPS
Reconnecting Cables and Powering up the SPS 1. Reconnect the sense cable from the SPS serial port (marked with a battery symbol) on management module to the SPS (detailed in reconnecting the sense cable and power cords). 2. Reconnect the power cables to the replacement SPS as shown in and described in the steps that follow the figure. a. Connect the power cord to the power distribution unit (PDU) in the cabinet or the site power circuit and to the SPS. 3. Power up the SPS by pressing the right side of the SPS power switch (Figure 7 on page 12).
Figure 7. On position for the SPS switch (SPS A shown)
12
Replacing a Standby Power Supply
Installing the front plate
Installing the front plate 1. Reposition the front plate and secure it with the screws that you saved when you removed the plate (Figure 8 on page 13). 2. If you are adding a second SPS, secure that SPS to the front plate with two additional screws that came with the SPS upgrade kit (Figure 8 on page 13). Figure 8. Installing the front plate
Ins talling the front plate
13
Installing and locking the SPS front bezel
Installing and locking the SPS front bezel 1. While holding the front SPS bezel by its edges, attach it to the latch brackets on the front of the enclosure (Figure 9 on page 14). 2. Push the bezel in until you feel it latch into place, and pull back on the bezel slightly to ensure it is secured. 3. Lock the bezel by inserting and then turning the key clockwise (Figure 9 on page 14).
Figure 9. Installing and locking the SPS bezel
14
Replacing a Standby Power Supply
Verifying the operation of a new or replacement part
Verifying the operation of a new or replacement part Use Navisphere Express® or Navisphere® Manager to verify the operation of a new or replacement part. If the storage system is running Navisphere Express, use Navisphere Express to verify the operation of a new or replacement part. If the storage system is running Navisphere Manager, use Navisphere Manager to verify the operation of a new or replacement part. Note: All
AX4-5 series storage systems ship with Navisphere Express installed. To use Navisphere Manager, you need to upgrade your storage system to Navisphere Manager.
Verify the operation of a new or replacement part using Navisphere Express 1. In a browser on a network-connected host, start Navisphere® Express for the storage system by entering the IP address of an SP in the storage system. 2. In the Navisphere Express navigation pane, under View , click Components. 3. Scan the list of components to verify that all components are recognized and working properly. If fault lights on storage system are still lit, go to the Celerra Tools page on the http://Powerlink.EMC.com website for more information.
Verifying the operation of a new or replacement part using Navisphere Manager 1. Start Navisphere® Manager for the storage systemby entering the IP address in a browser window. 2. In the Navisphere Manager Storage tree, locate the icon for the storage system in which you installed or replaced the part, expand the storage-system icon, and select the Physical icon. 3. Expand the enclosure in which you installed or replaced the part, and navigate to the part. 4. Verify that the part is in the enclosure and that it is not faulted.
Verifying the operation of a new or replacement part
15
Verifying the operation of a new or replacement part
If fault lights on storage system are still lit, go to the Celerra Tools page on the http://Powerlink.EMC.com website for more information.
16
Replacing a Standby Power Supply
Restoring trespassed virtual disks or LUNs using the CLI
Restoring trespassed virtual disks or LUNs using the CLI When a backend FRU/CRU component fails, the virtual disks or LUNs assigned to that storage processor trespass to the other storage processor. This keeps the data available to the clients. After replacing the failed backend FRU/CRU component you need to restore the virtual disks or LUNs to their original storage processor. 1. Using the CLI, log in to the primary Control Station as nasadmin and change to the root user: su root
2. Determine the storage-system serial number (storage-system ID): nas_storage -list
3. Restore the virtual disks or LUNs to the correct SP: nas_storage –failback storage-system-id
For example: # nas_storage -failback APM00070300923 id = 1 serial_number = APM00070300923 name = APM00070300923 acl = 0 done
This restores the virtual disks or LUNs to the correct SP. After the restore, both SPs have their status listed as OK.
Restoring trespassed virtual disks or LUNs using the CLI
17
Checking system status
Checking system status Before you begin
You should still be in your HyperTerminal session. Procedure
To view the system state: 1. Enter the following command to verify the system state: # /nas/bin/nas_checkup
Example: # /nas/bin/nas_checkup ]# /nas/bin/nas_checkup Check Version:
Check Command: /nas/bin/nas_checkup Check Log : /nas/log/checkup-run.100128-181007.log -------------------------------------Checks------------------------------------Control Station: Checking if file system usage is under limit.............. Pass Control Station: Checking if NAS Storage API is installed correctly........ Pass Control Station: Checking if NBS clients are started....................... Pass Control Station: Checking if NBS configuration exists...................... Pass Control Station: Checking if NBS devices are accessible.................... Pass Control Station: Checking if NBS service is started........................ Pass Storage System : Checking for unsupported storage profile.................. Pass Storage System : Checking if Fibre Channel zone checker is set up.......... N/A Storage System : Checking if Fibre Channel zoning is OK.................... N/A Storage System : Checking if proxy arp is setup............................ Pass Storage System : Checking SPA SPB communication............................ Pass --------------------------------------------------------------------------------
If the output of the nas_checkup command indicates any problems, correct the problems and re-do the command before continuing.
18
Replacing a Standby Power Supply
Enabling CallHome or ConnectHome and Email notifications
Enabling CallHome or ConnectHome and Email notifications Use the procedure in the section that follows for your EMCNAS version to enable CallHome or ConnectHome and Email notification.
For EMCNAS 5.6 or later Use a HyperTerminal session to enable ConnectHome and Email notification: 1. From the root directory, clear any existing Callhome files and enable ConnectHome: /nas/sbin/nas_connecthome -service start -clear
2. From the ConnectHome configuration, determine the connections that are enabled: /nas/sbin/nas_connecthome -i
Sample output:
Enabling CallHome or ConnectHome and Email notifications
19
Enabling CallHome or ConnectHome and Email notifications
ConnectHome Configuration: Encryption Enabled = yes Dial In: Enabled = yes Modem phone number = Site ID = Serial number = HK192201084 Email: Priority = 1 Sender Address = [email protected] Recipient Address(es) = [email protected] Subject = CallHome Alert Primary: Email Server = sun1.hosts.pvt.dns Secondary: Email Server = FTP: Priority = Disabled Primary: FTP Server = FTP Port = 21 FTP User Name = onalert FTP Password = ********** FTP Remote Folder = incoming FTP Transfer Mode = active Secondary: FTP Server = FTP Port = 21 FTP User Name = onalert FTP Password = ********** FTP Remote Folder = incoming FTP Transfer Mode = active Modem: Priority = Disabled Primary: Phone Number = 918005270941 BT Tymnet = no Secondary: Phone Number = 918006262452 BT Tymnet = no
3. Verify that ConnectHome works with the /nas/sbin/nas_connecthome -test connec tion_name command for each enabled connection. For example: /nas/sbin/nas_connecthome -t -email_1
Sample output: ----------------------------------------------------ConnectEMC 2.0.27-bl18 Wed Aug 22 10:24:32 EDT 2007 RSC API Version: 2.0.27-bl18 Copyright (C) EMC Corporation 2003-2008, all rights reserved. ----------------------------------------------------Reading configuration file: ConnectEMC.ini. Run Service begin... Test succeeded for primary email.
20
Replacing a Standby Power Supply
Enabling CallHome or ConnectHome and Email notifications
Sample returns for disabled connections: /nas/sbin/nas_connecthome -t -email_2 Error 14504231218: Secondary Email is not currently enabled. /nas/sbin/nas_connecthome -t -modem_1 Error 14504231218: Primary Modem is not currently enabled. /nas/sbin/nas_connecthome -t -modem_2 Error 14504231218: Secondary Modem is not currently enabled.
4. Verify email notifications is configured: /nas/bin/nas_emailuser -info
Sample output: /nas/bin/nas_emailuser –info Service Enabled = No Recipient Address(es) = [email protected] Carbon copy Address(es) = Email Server = 1.2.3.4 Subject Prefix = Celerra Notification Sender Address =
If the Recipient Address (es) field is empty, email notifications has not been configured and does not need to be enabled. If you want to configure email notifications, use the /nas/bin/nas_emailuser command or Celerra Manager to configure it. If the Recipient Address (es) field is populated, email notifications was enabled. Re-enable email notifications: a. Enable email notifications: /nas/bin/nas_emailuser -modify -enabled yes
Sample output: OK
b. Verify that email notification works: /nas/bin/nas_emailuser -info
Sample output: Service Enabled = Yes Recipient Address(es) = [email protected] Carbon Copy Address(es) = Email Server = 1.2.3.4 Subject Prefix = Celerra Notification Sender Address =
Enabling CallHome or ConnectHome and Email notifications
21
Enabling CallHome or ConnectHome and Email notifications
c. Test the configuration and verify that the configured Recipient Address(es) received the test email: /nas/bin/nas_emailuser -test
Sample output: OK
22
Replacing a Standby Power Supply
Returning the failed part
Returning the failed part Ship the failed part to your service provider as described in the instructions that were included with the replacement part.
Returning the failed part
23
Copyright © 2009 - 2010 EMC Corporation. All rights reserved. Published September 2010 EMC believes the information in this publication is accurate as of its publication date. The information is subject to change without notice. THE INFORMATION IN THIS PUBLICATION IS PROVIDED "AS IS." EMC CORPORATION MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND WITH RESPECT TO THE INFORMATION IN THIS PUBLICATION, AND SPECIFICALLY DISCLAIMS IMPLIED WARRANTIES OF MERCHANTABILITY OR FITNESS FOR A PARTICULAR PURPOSE. Use, copying, and distribution of any EMC software described in this publication requires an applicable software license. For the most up-to-date regulatory document for your product line, go to the Technical Documentation and Advisories section on EMC Powerlink. For the most up-to-date listing of EMC product names, see EMC Corporation Trademarks on EMC.com. All other trademarks used herein are the property of their respective owners. Corporate Headquarters: Hopkinton, MA 01748-9103
24
Replacing a Standby Power Supply