ISSUED FOR DESIGN
C
13.08.2013
MAYM
DEKU
EOG
ISSUED FOR IDC
B
19.06.2013
MAYM
DEKU
EOG
ISSUED FOR IDC
A
24.04.2013
MAYM
DEKU
EOG
REASON FOR ISSUE
REVISION
REV. DATE
PREP. BY
CHECKED
Document Family:
ANST Project:
APPROVED No. of pages
22
Doc. type:
FT CATCHER FPSO FEED
FD – FD – Design Design Criteria and Philosophy Discipline:
Unit:
L - Piping & Layout System no:
IMO No: Client:
00 PREMIER OIL UK LIMITED Document Title:
PIPING DESIGN PREMISE
Client Doc. No.:
DB10
Doc. No.:
4251-FD-00379827
Rev C
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379 827
Rev.:
C
TABLE OF CONTENTS 1
SCOPE
3
2
ORGANISATION
3
3
RESPONSIBILITIES
3
3.1 3.2
Content............................................................................................................3 Implementation................................................................................................3
4
HOLD LIST
3
5
REFERENCE DOCUMENTS
3
5.1 5.2
6
PROCESS PIPING 6.1 6.2 6.3 6.4 6.5 6.6 6.7 6.8 6.9 6.10
7
9
10
18
General.......................................................................................................... .......................................................................................................... 18 Butt Weld Connections ................................................................ .................................................................................. .................. 18 Socket Weld Connections ............................................................................. ............................................................................. 19 Flange Connections ...................................................................................... 19 Threaded Connections .................................................................................. .................................................................................. 20
INSPECTION INSPECTIO N AND TESTING 10.1
16
General.......................................................................................................... .......................................................................................................... 16 Steam & Condensate Piping ......................................................................... ......................................................................... 17 Feed W ater Piping System ........................................................................... 18
PIPING CONNECTIONS 9.1 9.2 9.3 9.4 9.5
14
Seawater, Utility Water and Potable W ater Piping ....................................... 14 Utility Air a nd Instrument Air Piping .............................................................. 15 Operational Requirements of Instrument Air:................................................ 15 Heating Media Piping .................................................................................... .................................................................................... 15 Fire W ater System ........................................................................................ 16 eck Drains ..................................................................................................... 16
MARINE PIPING 8.1 8.2 8.3
6
Pipe Design ..................................................................................................... ..................................................................................................... 6 Line Sizing .............................................................................................. ....................................................................................................... ......... 6 Layout and Clearance ..................................................................................... ..................................................................................... 7 Thermal Expansion and Support Su pport .................................................................... 9 Process Drains and Vents ........................................................... ............................................................................... .................... 9 Closed Drain System .................................................................................... 10 Strainers ............................................................... ........................................................................................................ ......................................... 10 Valves............................................................................................................ ............................................................................................................ 11 Pressure Safety Valves (PSVS) ............................................................. .................................................................... ....... 13 Piping to Pumps, Vessels and Equipment Equipm ent .................................................... 13
UTILITY PIPING 7.1 7.2 7.3 7.4 7.5 7.6
8
Definitions........................................................................................................ 5 Definitions........................................................................................................ Abbreviations .................................................................................................. .................................................................................................. 5
21
Drawing Layout ............................................................... ............................................................................................. .............................. 21
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
1
4251-FD-00379827
Rev.:
C
Scope The purpose of this document is to define the minimum requirements for the design of piping to be installed on Catcher FPSO, located offshore UK continental shelf whose design life shall be 20 years minimum.
2
Organisation This Piping Design premise applies to Catcher project team and Contractors, which manage, design, engineer, construction and deliver assets to BWO or BWO Client.
3
Responsibilities
3.1
Content Catcher Project Engineering Manager is responsible for the content and the continuous updating of this premise. The document shall not be altered or omitted without this position’s consent.
3.2
Implementation All discipline leads are responsible for the implementation of this premise. T ypical users are BWO engineering team and sub-contractors; construction, commissioning and operations personnel. Lead Piping & Layout will facilitate this process.
4
HOLD List Documents on hold to be issued in the Execution fase.
5
Controlled Bolt Torquing and Tensioning Procedure
Paining Specification
Specification for Pressure Testing and Flushing of Pipes
Specification for the Examination of Piping and Structural Weld joints
Reference Documents The design of piping systems and the piping material data sheets shall be in accordance with the latest edition of the codes and standards listed below. A particular code or standard that will apply during the course of design and fabrication shall be the latest revision published at the time of design start.
4251-FD-00380109
Drain Philosophy
4251-FD-00379626
Safety Philosophy
4251-FD-00379835
Active Fire Protection Philosophy
4251-FD-00380207
Pipe Support Design Premise
4251-FD-00379659
Piping Stress Analysis Philosophy
4251-SA-00379621
Piping & Valve Material specification for Topside
4251-SA-00380674
Piping & Valve Material specification for Marine
4251-FD-00379822
Eathing, Bonding, Screening and Lightning Protection
Philosophy
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
4119-FD-00291687
4251-HOLD
Controlled Bolt Torquing and Tensioning Procedure
4251-HOLD
Paining Specification
4251-HOLD
Specification for Pressure Testing and Flushing of
C
Process Design Philosophy
Pipes
4251-HOLD
Specification for the Examination of Piping and Structural Weld joints
4256-SA-00379829 Insulation Specification for Pipework and Vessels
American Society Of Mechanical Engineers (ASME)
B1.20.1
Pipe Threads, General Purpose (Inch)
B16.5
Pipe Flanges and Flanged Fittings, NPS ½ through NPS 24
B16.9
Factory-Made Wrought Steel Butt-Welding Fittings
B16.11
Forged Fittings, Socket-Welding and Threaded
B16.20
Metallic Gaskets for Pipe Flanges – Ring-Joint, Spiral Wound and Jacketed
B16.21
Nonmetallic Flat Gaskets for Pipe Flanges
B16.25
Butt-Welding Ends
B16.47
Large Diameter Steel Flanges NPS 26 through NPS 60
B31.3
Process Piping
B31.4
Pipeline Transportation Systems for Liquid Hydrocarbons and Other Liquids
B31.8
Gas Transmission & Distribution Piping Systems
B31.1
Power Piping
B36.10
Welded and Seamless Wrought Steel Pipe
B36.19
Stainless Steel Pipe
American Petroleum Institute (API)
RP 14C
Recommended Practice for Analysis, Design, Installation and Testing Of Basic Surface Safety Systems for Offshore Production Platforms
RP 14E
Recommended Practice for Design Production Platform Piping Systems
RP 14J
Recommended Practice for Design and Hazards Analysis for Offshore Production Facilities
RP 520
Part I & II - Sizing, Selection, and Installation of Pressure-Relieving Devices
RP 521
Guide for Pressure Relieving and Depressuring Systems
Std 590
Steel Line Blanks
and
Installation
of Offshore
Manufacturers Standardization Society of the Valve and Fittings Industry (MSS)
SP-44
Steel Pipeline Flanges.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
National Association of Corrosion Engineers
NACE:
MR 01-75 / ISO 15156-1
National Fire Protection Association (NFPA)
5.1
NFPA 13 NFPA 15 NFPA 24
Installation of Sprinkler Systems Water Spray Fixed Systems for Fire Protection Private Service Mains and Their Appurtenances
Definitions Conflicts If conflicts occur between the specification, data sheets and the referenced codes and standards, the most stringent requirements shall apply.
5.2
Abbreviations
AARH
Arithmetric Average Roughenes Height
API
American Petroleum Institute
ASME
American Society of Mechanical Engineers
ASTM
American Society for Testing and Materials
BOP
Bottom Of Pipe
BWO
BW Offshore
CS
Carbon Steel
FF
Flat Faced
FPSO
Floating Production Storage & Offloading
FRP
Fibre Reinforced Pipe
MPI
Magnetic Particle Inspection
NDT
Non Destructive Testing
NFPA
nal Fire Protection Association
NPSH
Net Positive Suction Head
PD
Positive Displacement
P& ID
Piping & Instrument Diagram
PSE
Pressure Safety Element
PSV
Pressure Safety Valve
PWHT
Post Welded Heat Treatment
RF
Raised Face
RT
Rediography Test
RTJ
Ring Type Joint
SOL
Sockolet
SS
Stainless Steel
TOL
Tredolet
TOP
Top of Pipe
UT
Ultrasonic Test
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
6
Process Piping
6.1
Pipe Design
6.1.1
Materials
Rev.:
C
Pipe, fittings and valves for services specified shall conform to that of the Piping & Valve Material Specification for Topside (4251-SA-00379621) and Piping & Valve Material Specification for Marine (4251-SA-00380674)
6.1.2
Design Pressures Operating pressure and design pressure for piping systems and pressure safety device set points shall be determined by BW Offshore Pte Ltd (BWO) with the Contractors assistance, and shall be as specified on the P&ID and/or Line List.
6.1.3
Design Temperatures Design temperatures downstream of a pressure safety valve (PSV), control valve, or other pressure reducing shall be as specified on the P&ID and/or Line List.
6.1.4
Loads Piping systems shall be designed for lines filled with water for hydro testing, except for flare headers and any other large diameter vapour lines which may be Nitrogen tested as approved by BWO. Piping systems on FPSO’s located in seismically active areas shall be designed to withstand horizontal and vertical seismic accelerations in addition to gravity and operating loads. Piping systems on floating facilities shall be designed to meet the motion criteria as defined in the Structural Design Basis. Transportation and installation loads shall be considered in the design. Pipe Stress Analysis Philosophy (4251-FD-00379659) should be referred to for calculation piping loads.
6.1.5
Isolation Blinds Permanent Figure of 8 spectacle blinds or spade and spacer shall be provided dividing the piping as shown on the P&IDs.
6.1.6
Visual Inspection All pipe spools shall be visually inspected followed by applicable NDT such as RT,UT,MPI etc. prior to PWHT.
6.2
Line Sizing
6.2.1
General Pipe Sized Pipe sizes, 1 1/4, 2 1/2, 3 1/2, 5 and 7 inch, shall not be used except with prior approval of BWO. As a general rule, all run and rack piping shall be 2-inch m inimum.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
If non-standard pipe sizes are part of purchased equipment, connecting pipe shall be transitioned to the next standard size as soon as possible. Minimum pipe sizes shall be ½ inch or ¾ inch except for the following may dictate:
Instrument drains and vents Instrument tubing lines Pressure gauge lines Sample lines Chemical injection lines Rotating equipment components
Minimum pressure ratings for ¾-inch and smaller pipe fittings shall be 3000 psi.
6.2.2
Fluid Flow Line Sizes Except for vents, flares, relief lines and fiberglass reinforced piping, single and multi-phase fluid piping shall be sized by the methods outlined in API RP 14E. Vents, flares and relief line piping shall be sized in accordance with API RP 521. Typical fiberglass piping system are operated at flow velocities between 3 & 12 ft./sec.
6.3
Layout and Clearance
6.3.1
Piping Layout The Layout shall be developed with the following aims:
Ensure that the arrangement and functionality provided by the layout satisfies all safety, operations and maintenance requirements with minimum impact on space, weight and cost. Piping shall be oriented either facility forward / aft or facility port side / starboard side Piping shall not be oriented diagonally in the horizontal or vertical plane without prior approval of BWO. Un-insulated and insulated lines shall be located such that line reference points (bottom of pipe) are at the same elevation as bottom of pipe of adjacent un-insulated lines. (i.e. on shoes). Piping running facility forward or facility aft shall have a minimum of 600mm vertical separation (BOP / BOP) or 200mm clear (TOP / BOP) from piping running facility east or facility west, unless otherwise approved by BWO. Space shall be allocated at an early stage for primary and secondary escape routes, access ways, main pipe/cable racks/trunks and main ductwork as well as main penetration areas. Plated deck penetrations shall: Employ seal welded deck penetration sleeves 150mm above deck and 25mm below deck Have a minimum 50mm gap between sleeve and pip. Grated deck pipe penetration sleeves shall: Be tack-welded to grating Extend 50mm above and 50mm below grating Be split to permit passage of a flange for the pipe Gratings shall be galvanized after installation of penetration sleeve Piping shall be arranged to achieve the shortest, most efficient and distribution effective pipe runs imposed by process logic and equipment layout. Piping arrangements around process vessels shall permit access to manholes and openings in vessels with sufficient space to move davit supported covers out of the way.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
C
All piping and tubing shall be arranged to facilitate supporting and design shall provide for servicing or removal of instruments, pump casings, orifice plates, heat exchanger bundles, filter elements and other equipment parts and appurtenances. Layout shall allow for equipment staging areas near cranes, where available, on each deck. Piping shall consider the following safety concerns: Crane lifts and other logistical operations over piping / vessels. Direct fired equipment, engine and turbine exhausts and potentially hazardous mechanical equipment in vicinity. Local atmospheric vents, blowdown and relief of hydrocarbons relative to FPSO orientation, potential ignition sources, seasonal wind directions, helicopter flights paths and building air intakes. Piping layout to avoid obstruction of Deluge Spray Pattern and Flame detection. Piping layout should be such that it should avoid any dead legs.
The drain system shall operate satisfactory during the planned trim condition of the vessel. The minimum slope to be as per the Drain Philosophy (4251-FD-00380109)
6.3.2
Rev.:
Accessibility Access to equipment valves and instruments shall be provided for operations, disassembly and removal. Control valves, relief valves, shutdown valves and lubricated valves shall be located such that the valves may be serviced or replaced. Larger valves mush have necessary permanent lifting arrangements if not temporary arrangements can be reasonable provided. Except for drain and vent valves used solely for construction and start-up purposes, access to valves, controls and instruments shall be provided from deck level and if necessary, by means of ladder stairways, walkways or elevated landings. Gauge glasses, temperature indicators and pressure gauges/instrument local indicators shall be visible from:
Deck of skid edge Related control instruments Ladders
Process sampling and drain connections shall be accessible from deck or elevated platform. Drain and sampling effluent shall be captured by the open drains system by tubing to drain or skid pan.
6.3.3
Clearances The following minimum clearances (with modules) in Table 1 shall be provided, unless otherwise specifically approved by BWO: Table 1 Mini mum C learances
Application Personnel access for main escape routes, overhead
Clearance from Bottom of Pipe or Bottom of Insulation to Deck 2.3 m
(including bottom of associated pipe supports) Personnel
access for
secondary escape,
2.1m
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
overhead (including bottom of associated pipe supports) A minimum of 50mm clearance, including insulation and flanges, shall be provided between adjacent piping runs. Pipe spacing and bottom elevation shall take into account insulation thickness and movement due to thermal expansion or contraction. Lines with orifice meter assemblies, Space and spacer and spectacle blinds shall have sufficient operational clearance and clearance for installation and removal.
6.3.4
Clear Passageways Passageways for personnel access and movement and designated escape or evacuation routes within modules shall be a minimum as per of 1.0m wide and secondary access shall be a min. of 0.8m wide with overhead clearance indicated in Table 1. Also see: 4256-FD-00372546 Safety Philosophy
Low elevation piping and / or pipe stiles shall not be permitted in designated escape or evacuation routes. Low elevation piping in other passageways may only be used with BWO approval. Pipe stile must be used. Dead ends not to exceed 7m in length on Topside Modules.
6.3.5
Earthing For Earthing requirements see: 4251-FD-00379822 Earthing, Bonding, Screening and Lightning protection Philosophy.
6.4
Thermal Expansion and Support For pipe thermal expansion: Refer Piping Stress analysis report and/ or applicable code.
For pipe support requirements see: 4251-FD-00380207 Piping Support Design Premise.
6.5
Process Drains and Vents
6.5.1
Process Piping Drains Drain valves shall be installed between isolation valves and either side of Pressure Reducing valves where liquid may be trapped. In addition, if any other places where piping layout feel the chances of liquid traping or drop out, a drain should be provided. Bleed rings may be used for this purpose if a location is not otherwise available for a TOL or SOL. Low point drains shall conform to the following minimum size connection in Table 2: Table 2 Minimum Si ze Connections
Line Size
Drain Size
Up to 11/2
¾
2 to 6
1
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
8 and larger
C
1 1/2
Operational low point drains in process service shall be piped with block valves to the closed drains system. Vent, relief, flare and gas compressor suction lines shall be designed to avoid low point liquid traps. BWO must approve unavoidable traps, an operational low point drain shall be installed at low points. P&IDs shall be revised to include operational high point vents and low point drains after completion of the piping design layout. To be included on as- built P&ID’s. Low point drains shall be installed at the end of the Instrument Air and Utility Air headers.
6.5.2
Process Vessel Drains Multiple drain valves on horizontal pressure vessels shall:
Be manifold together Be connected to the closed drain system. Have both ends of manifold blind flanged for clean out or local draining to skid pan.
Vessel drain connections not connected to closed drain system shall have a valve with a blind flange installed.
6.5.3
Vents High points of lines shall have ¾ inch minimum vent connections. Valve vents shall be installed where periodic vapour accumulation may be detrimental to downstream equipment such as pumps and heat exchangers. Vents required during start-up or operation shall be equipped with a valve. Vents required only for hydro testing may be plugged without a valve. valves shall be piped to the process vent system.
Frequently operated
Elevation of vents to meet Hazardous area requirements. See:
6.5.4
4251-FD-00379626
Safety philosophy
Plugs Drain and vent valves not piped to specific locations shall be plugged, capped or blind flanged as appropriate.
6.6
Closed Drain System
6.6.1
For Closed Drain requirements see:
6.7
4251-FD-00380109
Strainers
Drain Philosophy
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
6.7.1
4251-FD-00379827
Rev.:
C
Temporary and Permanent Strainers Temporary and permanent strainers shall have net open area equal to or greater than 150% of cross sectional area of inline piping. Suction lines to rotating equipment (compressors, pumps, etc) shall have temporary or permanent strainers. Piping layout should allow easy removal of strainers for maintenance and replacement.
6.7.2
Temporary Strainers Temporary strainers shall be provided upstream of pumps, plate heat exchangers, control valves with noise abatement trim and other items subject to plugging. Piping shall be arranged to permit removal of temporary strainers from flanged joints without altering pipe, pipe supports or equipment alignment.
6.7.3
Permanent Strainers Piping normally carrying fluids containing materials detrimental to the operation of instruments and equipment shall have permanent strainers upstream of instruments and equipment. Permanent strainers shall be installed upstream of turbine of PD meter in produced liquid service. The strainer mesh size shall be as per instrument requirements.
6.8
Valves
6.8.1
General If piping specification changes at a valve, the valve shall be rated for the higher pressure and coincident temperature specification. Specification changes shall be indicated on the P&IDs. The first process valve (root valve) from process piping header or vessel shall be ½ inch or ¾ inch minimum consistent with Section 3.2.1. Unless otherwise approved by BWO, small valves shall not have bodies that screw apart. Face – Face and End – End dimensions of butt welded and flanged valves shall be as per ASME B16.10.
6.8.2
Ball Valves Except as specified on P&IDs, ball valve shall be used for shutoff service, including block on well manifolds and vents and drains in pressure classes through ASME 2500 and API 5000. These valves shall normally be reduced port. Unless otherwise specified, full port ball valves to be used in the following applications:
Lines requiring pigging. Horizontal lines sloped for continuous draining. Inlet to meter runs. Inlet and outlet of pressure safety valves (PSVs), rupture disc (PSEs) and blowdown valves. Pump or compressor suction.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
6.8.3
Rev.:
C
Reduction of pressure drop when necessary to meet design criteria. Full port valves shall be identified on P&IDs.
Butterfly Valves Butterfly valves shall:
6.8.4
Only be used in low pressure, non-critical water service. Be lug type valve installed with cap screws such that the piping may be removed from either side without releasing the valve.
Check Valves The following shall apply for the use of check valves in Table 3: Table 3
C heck Valves
Application
Check Valve
½ to 2
Swing
½ to 1½
Piston
2 to 24
Dual Plate Wafer
Centrifugal pumps
Swing
Reciprocating Pumps
Piston
Centrifugal Compressors
Piston
Reciprocating Compressors
Piston
Swing check valves shall not be used in vertical pipe spools.
6.8.5
Globe Valve Globe valves shall:
Be used only where throttling is required. Not to be used to provide tight shutoff.
Manual breakdown valves shall be specified as globe valves. Bypass valves shall be globe valves when bypass to Control Valves
6.8.6
Miscellaneous Valves Except for low pressure service where ball valves shall be used, sample valves shall be needle valves. Sample valves shall be located upstream of control valves. Generally chemical injection points should be located as far upstream in a piping run as practical in order to maximize mixing.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
6.9
4251-FD-00379827
Rev.:
C
Pressure Safety Valves (PSV S) ’
For Pressure Safety Valves see:
6.9.1
4119-FD-00291687
Process Design Philosophy
Block Valves PSV’s shall have an upstream full port block valve that can lock in the open position for single PSVs. For spared PSVs e.g. 2x 100%, the upstream block valves shall be able to be locked in the open and the closed position. A bleed valve shall be installed between the inlet isolation valve and the PSV to allow in-situ testing. PSV’s shall have a downstream full port block valve that will lock in the open position. A bleed valve shall be installed between the PSV and the downstream isolation valve.
6.9.2
Operational Requirements PSVs shall be mounted at the same elevation or higher than the relief header.
6.10
Piping to Pumps, Vessels and Equipment
6.10.1 Pump Piping Pump suction lines shall be:
Sized and arranged to meet pump NPSH requirements. Routed to pumps without creating vapour traps in line. Routed to low continuously up or continuously down to the pump suction.
Check valves in pump discharge lines shall be located between pump and first block valve. Piping at pumps shall have flexibility such that expansion or dead loads shall not imposed excessive strain on pump casings. If arrangements do not permit easy removal of pump, piping shall have removable spool pieces. Flanged check valves or flange fittings between discharge and suction block valves and pump may be used in lieu of spool pieces. Pump casing and auxiliary drain connections on non-hydrocarbon pumps shall be piped to open drain headers. Eccentric reducers on horizontal pump suctions shall be installed with top flat (TF).
6.10.2 Positive Displacement Type Compressor Piping Suction and discharge piping of positive displacement type compressors shall provide clearance for removal of unit and pulling rotor without dismantling pipe. Piping shall not obstruct compressor, instrumentation and seal oil components. Lube oil return piping shall be sloped for gravity flow and have no pockets from the compressor or turbine to the reservoir.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
6.10.3 Vessel Piping Vessel vents shall be piped to vent system. Distance between inlet and outlet nozzles on horizontal separators and surge vessels shall be maximized. Piping layout and supports shall not interfere with access to vessel man ways, gauge glasses, primary level instruments and other facilities for operation and maintenance of units. Spectacle blinds shall be provided when indicated on the P&IDs and piping arrangement drawings.
6.10.4 Heat Exchange Piping Exchanger orientation and piping shall provide for operating access, maintenance clearance, pulling the tube bundle, rodding or replacement of tubes with no or minimal dismantling of piping. Cooling water shall be configured such that exchanger remains full of water during a water supply failure. Gases shall be self-venting from exchanger. Valve drains and vents shall be provided on both sides. Valve chemical cleaning connections shall be provided as necessary. Process design shall consider relief requirements resulting from possible tubing leaks.
7
Utility Piping
7.1
Seawater, Utility Water and Potable Water Piping
7.1.1
Operational Requirements Seawater piping where seawater contains oxygen should be off material as per material selection report. Where Carbon steel pipe is used, this must be internally coated. If not rubber line or glass flake coated then suitable epoxy coating must be applied internally based on BWO approval. All piping material shall be as per P&ID and material selection report. Seawater Pump Discharge Piping Seawater pump discharge piping shall be arranged to permit disassembly and access by lift equipment for pulling the motor, column pipe, line shaft (if applicable) and pump. Overhead piping shall be arranged to permit disassembly and access by lift equipment for pulling the pump assembly.
7.1.2
Utility Water Stations Utility water stations shall have:
¾ inch hose connections with ball valve and globe valve. 15m lengths of hose.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
Processes or utilities requiring potable water shall have a hose connection. connections to the potable water system shall not be permitted.
C
Permanent pipe
All branch connections from the potable water header shall be from the bottom of the header.
7.2
Utility Air and Instrument Air Piping
7.3
Operational Requirements of Instrument Air: Instrument air supply and distribution piping systems shall be designed in accordance with the Piping & Valve Material Specification to meet the requirement of miscellaneous instrument items. Service or utility air systems shall be provided:
To meet demands of pneumatic tools, pneumatic pumps and air starters. For equipment cleaning. For backup supply to emergency control system. Where indicated by BWO.
Branch connections shall have isolation valves immediately adjacent to air header, and shall be from the top of the header. Auto water drain to be provided at low points of piping loops.
7.3.1
Layout Requirements Utility air stations shall have:
¾ inch hose connections complete with ball valve and quick disconnect. 15m lengths of air hose.
Workshops and designated working areas shall be provided with minimum of two utility air stations.
7.4
Heating Media Piping Heating media and steam piping shall be insulated in accordance with Insulation Specification for Pipework and Vessels (4251-SA-00379829). Steam piping shall be run to prevent pockets. Condensate shall be collected at low point by use of steam trap. Drain point shall be from the bottom of the header and steam take-offs from the top. Steam traps shall be accessible from deck or platform. The high operating temperature of this type of piping may require special considerations related to:
Expansion Temperature gradients with and without thermal insulation in flanges, gaskets and bolts Bolt pretension loads in flanges
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
7.5
Fire Water System
7.5.1
Operational Requirements
Rev.:
C
Sprinkler and water spray system design and arrangement shall be in accordance with NFPA Standard 13 and NFPA Standard 15 as applicable. Sizes of distribution mains, laterals and risers shall be calculated to provide required flow rates and pressures for the highest point in firewater piping system. Lockable deluge isolation valves shall be installed to allow testing of the deluge valve without deluging equipment. Each section of piping that can be isolated shall contain high point and low point connections for flushing and draining each section. A drain or vent shall be located immediately downstream of the deluge valve. Branch connections for deluge nozzles shall be attached to distribution header above header pipe centre. No connections shall be permitted on lower portion of the piping.
7.5.2
Firewater Piping Layout Firewater ring main shall be configured to take advantage of the natural protection afforded by structural members, buildings and unclassified equipment or vessels. To benefit from the physical protection and fire protection provided by a flooded deck, firewater ring mains and laterals on solid decks shall be located below the deck that required firewater service. Isolation and by-pass valves serving fire main and laterals shall be accessible from deck level. For Firewater stations location see:
4251-FD-00379835
Active Fire Protection Philosophy
7.6
Deck Drains
7.6.1
For Deck Drain requirements see:
4251-FD-00380109
8
Marine Piping
8.1
General
Drain Philosophy
JIS standard will be used for all marine and utility pipes due to construction issues in shipyard.
8.1.1
Materials Pipe, fittings and valves for services specified shall conform to that of the Piping & Valve Material Specification.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
8.1.2
4251-FD-00379827
Rev.:
C
Design Pressures Operating pressure and design pressure for piping systems shall be determined by BW Offshore Pte Ltd (BWO) with the Contractors assistance, and shall be as specified on the P&ID and/or Line List.
8.1.3
Design Temperatures Operating and Design temperatures shall be as specified on the P&ID and/or Line List.
8.1.4
Loads Piping systems shall be designed for lines filled with water for hydro testing or with air for pneumatic testing, as applicable. Piping systems on FPSO’s located in seismically active areas shall be designed to withstand horizontal and vertical seismic accelerations in addition to gravity and operating loads. Piping systems on floating facilities shall be designed to meet the motion criteria as defined in the Structural Design Basis. Transportation and installation loads shall be considered in the design. Pipe Stress Analysis Philosophy (4251-FD-00379659) should be referred to for calculation piping loads.
8.1.5
Isolation Blinds Permanent Figure of 8 spectacle blinds or spade and spacer shall be provided dividing the piping as shown on the P&IDs.
8.1.6
Visual Inspection All pipe spools shall be visually inspected followed by applicable NDT such as RT,UT,MPI etc. prior to PWHT, as applicable.
8.2
Steam & Condensate Piping Steam and condensate pipes to be designed to withstand the design internal pressures and temperatures in accordance with applicable codes and Class rules. In addition they are designed to take account of ample expansion and contraction without causing undue strain in pipe. 4251-FD-00379659 - Piping stress analysis Philosophy should be referred to in calculating piping load and finalising pipe routing and supports. Steam pipe penetration through bulkhead and deck shall be designed with allowance for expansion and minimize the heat transfer to adjacent deck or bulkhead. Branch off main steam headers shall be from the top of the header to obtain dry steam and avoid carrying over of condensate.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
Each branch line shall have an isolation valve installed near the main header to allow maintenance work without shutdown of main steam supply. Condensate piping shall be attached to the lowest point of the equipment serviced and routed to the steam trap so that condensate will flow by gravity to the trap. For Steam line, all isolation valves of size 6” and over should have a warming through byp ass.
8.3
Feed Water Piping System Feed water pipe between boiler and the required stop valve and screw down check valve, including these valves, are to be designed for a pressure not less than the smaller of the following:
9
1.25 times the maximum allowable working pressure of the boiler Maximum allowable working pressure of the boiler plus 15.5 bar (15.8 kgf/ cm sq., 225 psi) In no case is the feed water piping from the feed water pump to the boiler to be designed to a pressure less than the feed pump relief valve setting or the shut-off head of the feed pump
Piping Connections
9.1
General Hydrocarbon piping 2-inch and larger shall be of butt-welded construction. Except for services described in Section 4.3, pipe sizes 1-1/2 inch and smaller maybe screwed. Except where instruments may connect, pipe connections shall be ¾ inch minimum. Thermowells mounted on lines below 4 inch size shall be blown or swage up to 4 inch.
9.2
Butt Weld Connections
9.2.1
Materials Butt weld fittings for piping shall:
9.2.2
Conform to ASME B16.9 Be as specified in the Piping & Valve Material Specification for the particular class of service intended
Elbows Mitered elbows:
Shall not be used in pressurized piping without prior approval of BWO May be used in open deck drain systems Short radius elbows as per ASME B16.28 shall be used only where space is limited and with prior approval of BWO
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
9.2.3
4251-FD-00379827
Rev.:
C
Bevels Pipe ends for butt-welded of pipe and fittings shall be beveled in accordance with ASME B16.25 and as required by ASME B31.3.
9.3
Socket Weld Connections
9.3.1
General Unless otherwise approved by BWO, piping 1-1/2 inch or less in diameter shall be socket welded for the following services:
Hydrocarbon service above 250°F Hydrocarbon service ASME Class 900 and above pressure rating Glycol service Heating medium fluids Lube oil systems
However, for vibration service, socket weld connections are not recommended.
9.4
Flange Connections
9.4.1
Materials Flanges up to 24 inches for ASME Class 150 – 2500 shall:
Conform to ASME B16.5 Be as specified in the Piping and Valve Material Specification for the particular class of service intended
Flanges 26 inches and larger shall:
Conform to ASME B16.47 Series A Be as specified in the Piping and Valve Material Specification for particular class of service intended
At the direction and / or agreement of BWO and Class Society, proprietary end connectors such as Techlok, Re-Flange, Graylok or Taper Lok may be used to attain weight and space savings as well as design flexibility.
9.4.2
Flange Faces Raised face (RF) flanges shall have 125 – 250 AARH smooth finish faces in accordance with ASME B16.5. Ring type joint (RTJ) flanges shall have standard grooving in accordance with ASME B16.20. Flanges mating with flat faced (FF) flanges, such as case steel pump nozzle or Bondstrand fiberglass flanges shall be flat faced type. A connecting RF flange can be used to mate with a pumps integral FF flange – Client. Unless otherwise specified, flange bolt holes shall straddle normal horizontal and vertical centreline of pipe.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
9.4.3
4251-FD-00379827
Rev.:
C
Flange Bolts Length of stud bolts shall be in accordance with ASME B16.5 plus 6mm. Bolt threads shall extend 3mm past nuts on both ends when tightened in place. Bolts and nuts shall be Hot Dip Galvanised. Refer to Controlled Bolt Torquing and Tensioning Procedure ( HOLD).
9.4.4
Weld Neck Flanges Weld neck flanges shall be preferred for all services. Weld neck bore shall match inside diameter of connecting pipe.
9.4.5
Reducing Flanges If welded reducers, swage nipples or standard fittings cannot be used, reducing flanges or flanged fittings may only be used with prior approval of BWO.
9.4.6
Slip-On Flanges Slip-On Flanges can be used for low pressure system upon approval by BWO.
9.4.7
Flange Blinds Spectacle blinds, rather than spade-type blinds, shall be used for permanent installation (consider a max weight limit of 25kg for handling purposes). Thickness of blinds shall be calculated in accordance with ASME B31.3. Blind flanges shall be in accordance with ASME B16.5. Spectacles, blanks and spacers shall be in accordance with API Std. 590 and ASME B31.3.
9.4.8
Flange Gaskets Insulating flange gasket sets shall be provided to isolate dissimilar materials.
Piping from pipelines. Bridge connected piping between platforms. For mating flanges of dissimilar materials (CS to SS).
Full-face gaskets shall be used at flat face flange connections. Gaskets for RF (Spiral Wound Gasket) and RTJ flanges shall be in accordance with ASME B16.20. Flange gaskets shall meet the requirements for the service specified in the Piping & Valve Material Specification.
9.5
Threaded Connections
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
9.5.1
4251-FD-00379827
Rev.:
C
Materials Swage and pipe nipples shall be in accordance with piping material specifications for the class of service stated in Piping & Valve Material Specification. Forged steel screwed fittings shall:
Conform to ASME B16.11. Be in accordance with individual pipe specifications for the class service stated in Piping & Valve Material Specification.
Pipe nipples that support gauges, valves or other devices shall be schedule 160 minimum. Square head plugs, threaded bushings, close thread (all-thread) pipe nipples and street ells shall not be used. Swage nipples shall be used instead of threaded bushings. Threaded pipe connections shall have standard pipe taper threads in accordance with ASME B1.20.1.
9.5.2
Unions Screwed piping shall incorporate unions for ease of removal of equipment. Unions shall:
9.5.3
Be located on the low pressure side of block valves. Not be installed between a pressure vessel and the first block valve.
Vibration Threaded piping shall not be used in hydrocarbon services. Nipples, regardless of length, connected to a reciprocating pump or other equipment and piping where vibration is anticipated shall be securely braced. Piping 1 inch and less shall have adequate support. Pipe racks with widely spaced pipe rack supports shall incorporate intermediate supports. Threaded piping is not recommended in vibration services.
10 Inspection and Testing
10.1
Refer (HOLD) Specification for the Examination of Piping and Structural Weld Joints Refer (HOLD) Specification for Pressure testing and Flushing of Pipes
Drawing Layout P&IDs shall be arranged in a neat and logical manner with piping shown in most direct and efficient layout. The following shall be adhered to as closely as practical. Process flow and various inter-connections of pipe shall represent the physical layout of the process system as closely as practical.
Ft Catcher FPSO FEED PIPING DESIGN PREMISE Doc. No:
4251-FD-00379827
Rev.:
C
Initial layout of process vessels and equipment shall provide adequate space to add instruments, controls and accessories as required. Drawings shall be kept legible and easy to interpret without resorting to miniature fonts to show necessary information. Adequate space shall be provided for transferring equipment information to P&IDs. Equipment design data shall be collected as early as practical for inclusion in the drawings consistent with the P&ID legend and drafting practices. Boundary edges for skid mounted vessels and equipment shall be shown with process and utility connections shown terminating at the skid edge with the flange or pipe connection size indicated. Process lines carrying associated gases and vapors shall be arranged across the top of the process vessels and equipment or at top of sheet, to include vent, relief and blowdown lines. Process lines handling liquids and two-phase flow shall be shown below the process vessels and equipment, or at bottom of sheet. Adequate space across the top of the sheet shall be reserved for inserting equipment and vessel title blocks and descriptions. Process lines / instrument loop interconnections carried forward or backward to the next sheet shall carry line continuation blocks. Process lines not having a connection to a process vessel, equipment or other process line shall:
Not be shown on the drawing. Be identified on the previous sheet with a line continuation block identifying the sheet number to which the line will be continued on.
Line continuation block shall be shaped to indicate the direction of flow. Finalized P&IDs shall be such quality as to permit shot-down reproductions to A3 size Figure of 8 spectacle blinds shall be shown on P&IDs at flanged locations dividing hydrotest systems for permanent reference. P &ID shall indicate Spec break clearly, wherever applicable.