PEKERJAAN PERLINTASAN PIPA MELALUI SUNGAI JEMBATAN PIPA 172
Item Paket Lokasi
Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. TIPE D : :
NO
URAIAN BAHAN
I 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 7 8 9 10 11 12 13 14
III 1 2
173
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan batu kosong Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Sub Total I Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Loose Flange ND. 300 mm, steel Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange socket ND. 300 mm, PVC RRJ Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total II Pekerjaan lain-lain. Pengecatan pipa Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
Item Paket s
Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa.
Satuan
Volume
ls m3 m3 m3 m3 m3 m3 m2
1.00 5.44 2.04 2.04 3.40 0.40 3.75 5.70
m m bh bh bh bh bh bh bh bh bh bh bh ls
16.00 6.00 8.00 4.00 2.00 1.00 2.00 2.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Lokasi NO
Kampung Cibacang, Patok 32. URAIAN BAHAN
I 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3 4 5 6 7 8 9 10 11 12
IV 1 2
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 160 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.340 dimodifikasi dari bahan profil baja IWF. 250.175.7.11 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 300 mm all flange, CI. Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III Pekerjaan lain-lain. Pengecatan pipa dan konstruksi baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.47 2.74 2.74 3.40 2.74 0.38
set
4.00
kg
882.00
kg kg kg kg kg ls
91.74 42.73 56.95 73.70 41.88 1.00
m m bh bh bh bh bh bh bh bh bh ls
16.00 6.00 7.00 4.00 2.00 8.00 1.00 2.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
174
Item Paket Lokasi NO
Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Kampung Cibacang, Patok 32. URAIAN BAHAN
I 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3 4 5 6 7 8 9 10 11 12
IV 1
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.340 dimodifikasi dari bahan profil baja IWF. 250.175.7.11 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 300 mm all flange, CI. Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III Pekerjaan lain-lain. Pengecatan pipa dan konstruksi baja
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.44 2.04 2.04 3.40 3.75 5.70
set
4.00
kg
1,234.00
kg kg kg kg kg ls
128.50 59.20 80.20 117.92 67.00 1.00
m m bh bh bh bh bh bh bh bh bh ls
20.00 6.00 11.00 4.00 2.00 8.00 1.00 2.00 1.00 1.00 2.00 1.00
ls
1.00
2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
175
Item Paket Lokasi NO 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3 4 5 6 7 8 9 10 11
2.00
Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Kampung Cibacang, Patok 32. URAIAN BAHAN
I
unit
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.340 dimodifikasi dari bahan profil baja IWF. 250.175.7.11 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 300 mm all flange, CI. Street box Inside dia. 100 mm, CI.
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.44 2.04 2.04 3.40 3.75 5.70
set
4.00
kg
1,411.20
kg kg kg kg kg ls
146.78 68.36 91.12 117.92 67.00 1.00
m m bh bh bh bh bh bh bh bh bh
22.00 6.00 11.00 4.00 2.00 8.00 1.00 2.00 1.00 1.00 2.00
12 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
176
Item Paket Lokasi NO 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3 4 5
1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Kampung Cibacang, Patok 32. URAIAN BAHAN
I
ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 160 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.340 dimodifikasi dari bahan profil baja IWF. 250.175.7.11 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.47 2.74 2.74 3.40 2.74 0.38
set
4.00
kg
1,587.60
kg kg kg kg kg ls
165.12 76.91 102.50 132.66 75.36 1.00
m m bh bh bh
24.00 6.00 12.00 4.00 2.00
6 7 8 9 10 11 12
Loose Flange ND. 300 mm, steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 300 mm all flange, CI. Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
177
Item Paket Lokasi NO 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3
8.00 1.00 2.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Desa Jatiwangi, Patok 172. URAIAN BAHAN
I
bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur.
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.47 2.74 2.74 3.40 2.74 0.38
set
4.00
kg
1,764.22
kg kg kg kg kg ls
183.54 85.44 113.88 147.38 83.72 1.00
m m bh
26.00 6.00 14.00
4 5 6 7 8 9 10 11 12 13
Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, Steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Flange socket ND. 100 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
178
Item Paket Lokasi NO 1 2 3 4 5 6 7 8 9 10 11
II 1 2 3 3 4 5
4.00 2.00 8.00 1.00 2.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Jembatan Balenyengked, Patok 172. URAIAN BAHAN
I
bh bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Bongkaran beton masif dan pasangan batu. Pasangan Batu kosong Pasangan Batu, Spesi 1 : 4. Urugan pasir dipadatkan Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Baja Canal C.160.60.7,6. 10,5 Ikatan angin, baja siku L.60.60.6. Plat penegar Gelagar induk, tebal 10 mm Plat sambung gelagar induk (3 titik smb)
Satuan
Volume
ls m3 m3 m3 m3 m3 m3 m3 m3 m3 m3
1.00 19.24 1.10 1.10 18.14 9.15 3.15 11.50 1.57 17.48 8.00
set
4.00
kg
1,908.40
kg kg kg kg
391.04 302.98 255.30 60.32
6 Biaya Erection Konstruksi. Sub Total II III Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 300 mm 2 Pipa PVC ND. 100 mm, S.12.5 (RRJ) 3 Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. termasuk bantalan kayu 8/15 cm 4 Bend 11 1/4 all flange ND. 300 mm, steel 5 Bend 45 all flange ND. 300 mm, steel 6 Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ 7 Loose Flange ND. 300 mm, Steel 8 Tee all flange ND. 300 x 100 mm, CI 9 Flange adaptor ND. 300 mm, CI 10 Flange spigot ND. 300 mm, PVC 11 Gate Valve ND. 300 mm all flange, CI. 12 Gate Valve ND. 100 mm all flange, CI. 13 Air Valve (Double) ND. 50 mm all flange, CI 14 Loose Flange ND. 100 mm, Steel 15 Flange socket ND. 100 mm, PVC RRJ 16 Street box Inside dia. 100 mm, CI. 17 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
179
Item Paket Lokasi NO 1 2 3 4 5 6 7 8 9
1.00
m m bh
36.00 6.00 14.00
bh bh bh bh bh bh bh bh bh bh bh bh bh ls
2.00 2.00 2.00 10.00 1.00 4.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Kp. Lempar, Desa Cijambe, Patok 40. URAIAN BAHAN
I
ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu kosong Pasangan Batu, Spesi 1 : 4. Urugan pasir dipadatkan Plesteran Spesi 1 : 2, tebal 15 mm.
Satuan ls m3 m3 m3 m3 m3 m3 m3 m3
Volume 1.00 15.59 1.10 1.10 2.64 12.20 1.32 14.00
II 1 2 3 3 4 5 6 III 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
IV 1 2
180
Item Paket Lokasi NO
Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Baja Canal C.160.60.7,6. 10,5 Ikatan angin, baja siku L.60.60.6. Plat penegar Gelagar induk, tebal 10 mm Plat sambung gelagar induk (3 titik smb) Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. termasuk bantalan kayu 8/15 cm Bend 11 1/4 all flange ND. 300 mm, steel Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, Steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange spigot ND. 300 mm, PVC Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Air Valve (Double) ND. 50 mm all flange, CI Loose Flange ND. 100 mm, Steel Flange socket ND. 100 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III Pekerjaan lain-lain. Pengecatan pipa dan konstruksi baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
set
4.00
kg
1,908.40
kg kg kg kg ls
391.04 302.98 255.30 60.32 1.00
m m bh
36.00 6.00 14.00
bh bh bh bh bh bh bh bh bh bh bh bh bh ls
2.00 2.00 2.00 10.00 1.00 4.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus). Pemasangan Pipa Transmisi dan Jembatan Pipa. Kp. Lempar, Desa Cijambe, Patok 40. URAIAN BAHAN
Satuan
Volume
I 1 2 3 4 5 6 7 8 9 10 11
II 1 2 3 3 4 5 6 III 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
IV 1 2
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Bongkaran beton masif dan pasangan batu. Pasangan Batu kosong Pasangan Batu, Spesi 1 : 4. Urugan pasir dipadatkan Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Baja Canal C.160.60.7,6. 10,5 Ikatan angin, baja siku L.60.60.6. Plat penegar Gelagar induk, tebal 10 mm Plat sambung gelagar induk (3 titik smb) Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. termasuk bantalan kayu 8/15 cm Bend 11 1/4 all flange ND. 300 mm, steel Bend 45 all flange ND. 300 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, Steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Flange spigot ND. 300 mm, PVC Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Air Valve (Double) ND. 50 mm all flange, CI Loose Flange ND. 100 mm, Steel Flange socket ND. 100 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III Pekerjaan lain-lain. Pengecatan pipa dan konstruksi baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar).
ls m3 m3 m3 m3 m3 m3 m3 m3 m3 m3
1.00 15.59 1.10 1.10 9.15 2.64 16.50 1.32 17.00 9.52
set
4.00
kg
1,908.40
kg kg kg kg ls
391.04 302.98 255.30 60.32 1.00
m m bh
36.00 6.00 14.00
bh bh bh bh bh bh bh bh bh bh bh bh bh ls
2.00 2.00 2.00 10.00 1.00 4.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Sub Total IV Total I + II + III + IV
181
Item Paket Lokasi NO
Jembatan Pipa, ND. 250 mm, Bentang = 50,00 m : : URAIAN BAHAN
I 1 2 3 4 5 6 7 8 9 10 11
II 1 2 3 3 4 5 6 III 1 2 3 4 5 6 7 8 9 10 11
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Bongkaran beton masif dan pasangan batu. Pasangan Batu kosong Pasangan Batu, Spesi 1 : 4. Urugan pasir dipadatkan Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Baja Canal C.160.60.7,6. 10,5 Ikatan angin, baja siku L.60.60.6. Plat penegar Gelagar induk, tebal 10 mm Plat sambung gelagar induk (3 titik smb) Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 250 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 250 mm, plat baja 3 x 50 mm + baut mur. termasuk bantalan kayu 8/15 cm Bend 45 all flange ND. 250 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 250 mm, Steel Tee all flange ND. 250 x 100 mm, CI Flange adaptor ND. 250 mm, CI Flange spigot ND. 250 mm, PVC Gate Valve ND. 250 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI.
Satuan
Volume
ls m3 m3 m3 m3 m3 m3 m3 m3 m3 m3
1.00 26.87 8.06 8.06 18.81 9.15 2.64 20.70 1.32 36.00 17.46
set
8.00
kg
6,250.00
kg kg kg kg ls
1,002.00 582.50 491.00 125.00 1.00
m m bh
67.00 35.00 58.00
bh bh bh bh bh bh bh bh
4.00 2.00 16.00 1.00 4.00 1.00 1.00 1.00
12 13 14 15 16
Air Valve (Double) ND. 50 mm all flange, CI Loose Flange ND. 100 mm, Steel Flange socket ND. 100 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
182
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 3 4 5 6 7 III 1 2 3 4
1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Desa Jatiwangi, Patok 172. URAIAN BAHAN
I
bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Bongkaran beton masif dan pasangan batu. Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.400 dimodifikasi dari bahan profil baja IWF. 300.200.9.14 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 300 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 300 mm, Steel
Satuan
Volume
ls m3 m3 m3 m3 m3 m3 m3
1.00 3.80 5.40 2.74 2.74 3.40 4.94 0.38
set
8.00
kg
2,930.00
kg kg kg kg kg ls
215.76 100.46 133.96 148.59 84.40 1.00
m m bh bh
33.00 6.00 14.00 4.00
5 6 7 8 9 10 11 12 13
Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 300 mm, Steel Tee all flange ND. 300 x 100 mm, CI Flange adaptor ND. 300 mm, CI Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Flange socket ND. 100 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
183
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 7 8 9 10 11 12 13
2.00 6.00 1.00 2.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m. : : URAIAN BAHAN
I
bh bh bh bh bh bh bh bh ls
Satuan
Volume
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan batu kosong Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm.
ls m3 m3 m3 m3 m3 m3 m2
1.00 5.44 2.04 2.04 3.40 0.40 3.75 5.70
Sub Total I Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories Pipa Steel ND. 250 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Loose Flange ND. 250 mm, steel Bend 45 all flange ND. 250 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Tee all flange ND. 250 x 100 mm, CI Flange adaptor ND. 250 mm, CI Flange socket ND. 250 mm, PVC RRJ Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 250 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street box Inside dia. 100 mm, CI.
m m bh bh bh bh bh bh bh bh bh bh bh
16.00 6.00 8.00 4.00 2.00 1.00 2.00 2.00 1.00 1.00 1.00 1.00 2.00
14 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total II III Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
184
Item Paket Lokasi NO 1 2 3 4 5 6 7
II 1 2 3 3 4 5 6 7 III 1 2 3 4 5 6 7 8
1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Kampung Cibacang, Patok 32. URAIAN BAHAN
I
ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 160 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk, Profil baja Honey Comb, HC.340 dimodifikasi dari bahan profil baja IWF. 250.175.7.11 Gelagar melintang, IWF.100.100.6.8. Ikatan angin, baja siku L.50.50.5. Plat penegar prol HC, tebal 10 mm Plat sambung gelagar induk HC.340 (2 titik smb) Plat penutup HC, 2 x (150 x 32) tebal 10 mm. Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa GS. ND. 200 mm Pipa PVC ND. 100 mm, S.12.5 (RRJ) Klem pipa ND. 200 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 200 mm, steel Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Loose Flange ND. 200 mm, steel Tee all flange ND. 200 x 100 mm, CI Flange adaptor ND. 200 mm, CI
Satuan
Volume
ls m3 m3 m3 m3 m3 m3
1.00 5.47 2.74 2.74 3.40 2.74 0.38
set
4.00
kg
882.00
kg kg kg kg kg ls
91.74 42.73 56.95 73.70 41.88 1.00
m m bh bh bh bh bh bh
16.00 6.00 7.00 4.00 2.00 8.00 1.00 2.00
9 10 11 12
Flange socket ND. 100 mm, PVC RRJ Gate Valve ND. 200 mm all flange, CI. Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 200 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
185
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 3 4 5 6 III 1 2 3 4 5 6 7
1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m. : : URAIAN BAHAN
I
bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF250.125.6.9. Gelagar melintang, Canal 165.65.7,5.10 Ikatan angin, baja siku L.50.50.5. Plat penegar profil IWF Plat sambung gelagar t = 9 mm Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 150 mm ASTM A120, t = 7 mm Pipa PVC ND. 75 mm, S.12.5 (RRJ) Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur. Bend 11 1/4 all flange ND. 150 mm, steel Bend 22,5 all flange ND. 150 mm, steel Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Loose Flange ND. 150 mm, Steel
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 15.48 1.10 1.10 14.37 16.50 36.96 12.91
set
8.00
kg kg kg kg kg ls
1,805.60 394.80 344.60 38.30 282.60 1.00
m m bh bh bh bh bh
33.00 6.00 15.00 4.00 2.00 2.00 10.00
8 9 10 11 12 13 14 15 16
Tee all flange ND. 150 x 100 mm, CI Flange adaptor ND. 150 mm, CI Gate Valve ND. 150 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Flange socket ND. 150 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
186
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 III 1 2 3
1.00 2.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 150 mm, Bentang = 15,00 m. : : URAIAN BAHAN
I
bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF250.125.6.9. Plat dudukan pipa Plat penegar profil IWF Plat sambung gelagar t = 9 mm Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 150 mm ASTM A120, t = 7 mm Pipa PVC ND. 75 mm, S.12.5 (RRJ) Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur.
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 2.60 0.65 0.65 2.20 1.25 8.00 0.78
set
4.00
kg kg kg kg ls
444.00 34.50 58.50 37.50 1.00
m m bh
20.00 6.00 5.00
4 5 6 7 8 9 10 11 12 13 14 15 16
Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Loose Flange ND. 150 mm, Steel Tee all socket ND. 150x75 mm, CI Flange adaptor ND. 150 mm, CI Gate Valve ND. 150 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Flange socket ND. 150 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange spigot ND. 150 mm, PVC Flange spigot ND. 75 mm, PVC Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
187
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 7 8 9
1.00 6.00 1.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. Desa Jatiwangi, Patok 172. URAIAN BAHAN
I
bh bh bh bh bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 150 mm ASTM A120, t = 7 mm Pipa PVC ND. 75 mm, S.12.5 (RRJ) Loose Flange ND. 150 mm, Steel Bend 45 all flange ND. 150 mm, steel Bend 45 flange spigot ND. 150 mm, steel Bend 90 all socket ND. 75 mm, PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Tee all socket ND. 150x75 mm, CI Flange adaptor ND. 150 mm, CI
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 4.80 1.60 1.60 3.20 3.89 4.70 -
m m bh bh bh bh bh bh bh
16.00 6.00 4.00 2.00 2.00 1.00 1.00 1.00 1.00
10 11 12 13 14 15 16 17 18
Flange socket ND. 150 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange spigot ND. 150 mm, PVC Flange spigot ND. 75 mm, PVC Gate Valve ND. 150 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street Box Inside Dia. 150 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III III Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
188
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 7 8 9 10 11 12 13
1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 150 mm ASTM A120, t = 7 mm Pipa PVC ND. 75 mm, S.12.5 (RRJ) Loose Flange ND. 150 mm, Steel Bend 45 all flange ND. 150 mm, steel Bend 45 flange spigot ND. 150 mm, steel Bend 90 all socket ND. 75 mm, PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Tee all socket ND. 150x75 mm, CI Flange adaptor ND. 150 mm, CI Flange socket ND. 150 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange spigot ND. 150 mm, PVC Flange spigot ND. 75 mm, PVC
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 4.80 1.60 1.60 3.20 3.89 4.70 -
m m bh bh bh bh bh bh bh bh bh bh bh
10.00 6.00 4.00 2.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00
14 15 16 17 18
Gate Valve ND. 150 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street Box Inside Dia. 150 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III III Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
189
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 III 1 2 3 4 5 6 7
1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 12,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF200.1005,5.8. Plat dudukan pipa Plat penegar profil IWF Plat sambung gelagar t = 9 mm Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 100 mm ASTM A120, t = 7 mm Pipa PVC ND. 75 mm, S.12.5 (RRJ) Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 100 mm, steel Bend 90 all socket ND. 75 mm, PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Loose Flange ND. 100 mm, Steel
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 2.60 0.65 0.65 2.20 1.25 10.00 0.78
set
2.00
kg kg kg kg ls
213.00 22.00 15.00 1.00
m m bh bh bh bh bh
18.00 6.00 5.00 4.00 1.00 1.00 6.00
8 9 10 11 12 13 14 15 16 17 18
Tee all socket ND. 100x75 mm, CI Flange adaptor ND. 100 mm, CI Gate Valve ND. 100 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Flange socket ND. 100 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange spigot ND. 100 mm, PVC Flange spigot ND. 75 mm, PVC Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
190
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4 5 6 III 1
1.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
bh bh bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF200.1005,5.8. Plat dudukan pipa Plat penegar profil IWF Plat sambung gelagar t = 9 mm Biaya Erection Konstruksi. Sub Total II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 100 mm ASTM A120, t = 7 mm
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 2.60 0.65 0.65 2.20 1.25 0.78
set
2.00
kg kg kg kg ls
170.40 16.70 10.50 1.00
m
16.00
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Pipa PVC ND. 75 mm, S.12.5 (RRJ) Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. Bend 45 all flange ND. 100 mm, steel Bend 90 all socket ND. 75 mm, PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Loose Flange ND. 100 mm, Steel Tee all socket ND. 100x75 mm, CI Flange adaptor ND. 100 mm, CI Gate Valve ND. 100 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Flange socket ND. 100 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange spigot ND. 100 mm, PVC Flange spigot ND. 75 mm, PVC Street box Inside dia. 100 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
191
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4
6.00 5.00 4.00 1.00 1.00 6.00 1.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF200.100.5,5.8. Plat dudukan pipa Plat penegar profil IWF
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 2.60 0.65 0.65 2.20 1.25 0.78
set
2.00
kg kg kg
149.20 16.70 -
5 Plat sambung gelagar t = 9 mm 6 Biaya Erection Konstruksi. Sub Total II III Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm 2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) 3 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. 4 Bend 45 all flange ND. 100 mm, steel 5 Bend 90 all socket ND. 75 mm, PVC 6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ 7 Loose Flange ND. 100 mm, Steel 8 Tee all socket ND. 100x75 mm, CI 9 Flange adaptor ND. 100 mm, CI 10 Gate Valve ND. 100 mm all flange, CI. 11 Gate Valve ND. 75 mm all flange, CI. 12 Air Valve ND. 25 mm all flange, CI 13 Flange socket ND. 100 mm, PVC RRJ 14 Flange socket ND. 75 mm, PVC RRJ 15 Flange spigot ND. 100 mm, PVC 16 Flange spigot ND. 75 mm, PVC 17 Street box Inside dia. 100 mm, CI. 18 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
192
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II
10.50 1.00
m m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
15.00 6.00 5.00 4.00 1.00 1.00 6.00 1.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
kg ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan
Satuan ls m3 m3 m3 m3 m3 m2 m3
Volume 1.00 2.60 0.65 0.65 2.20 1.25 0.78
Konstruksi Rangka Baja. 1 Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. 2 Gelagar induk IWF200.100.5,5.8. 3 Plat dudukan pipa 4 Plat penegar profil IWF 5 Plat sambung gelagar t = 9 mm 6 Biaya Erection Konstruksi. Sub Total II III Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm 2 Pipa PVC ND. 75 mm, S.12.5 (RRJ) 3 Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. 4 Bend 45 all flange ND. 100 mm, steel 5 Bend 90 all socket ND. 75 mm, PVC 6 Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ 7 Loose Flange ND. 100 mm, Steel 8 Tee all socket ND. 100x75 mm, CI 9 Flange adaptor ND. 100 mm, CI 10 Gate Valve ND. 100 mm all flange, CI. 11 Gate Valve ND. 75 mm all flange, CI. 12 Air Valve ND. 25 mm all flange, CI 13 Flange socket ND. 100 mm, PVC RRJ 14 Flange socket ND. 75 mm, PVC RRJ 15 Flange spigot ND. 100 mm, PVC 16 Flange spigot ND. 75 mm, PVC 17 Street box Inside dia. 100 mm, CI. 18 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
193
Item Paket Lokasi NO 1 2 3 4 5
2.00
kg kg kg kg ls
127.80 13.20 10.50 1.00
m m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
14.00 6.00 5.00 4.00 1.00 1.00 6.00 1.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
set
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi
Satuan ls m3 m3 m3 m3
Volume 1.00 3.00 1.20 1.20 1.80
6 Pasangan Batu, Spesi 1 : 4. 7 Plesteran Spesi 1 : 2, tebal 15 mm. 8 Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm 2 Pipa PVC ND. 50 mm, S.12.5 (RRJ) Loose Flange ND. 100 mm, Steel Bend 45 all flange ND. 100 mm, steel Bend 45 flange spigot ND. 100 mm, steel Bend 90° all socket ND 50 mm PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Tee all socket ND 100 mm x 50 mm PVC Flange adaptor ND. 100 mm, CI 3 Flange socket ND. 100 mm, PVC RRJ 4 Flange socket ND. 50 mm, PVC RRJ 5 Flange spigot ND. 100 mm, PVC 6 Flange spigot ND. 50 mm, PVC 7 Gate Valve ND. 100 mm all flange, CI. 8 Gate Valve ND. 50 mm all flange, CI. 9 Air Valve ND. 25 mm all flange, CI 10 Street Box Inside Dia. 150 mm, CI. 11 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III III Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
194
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
2.20 2.80 -
m m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
11.00 6.00 4.00 2.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
m3 m2 m3
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3.
Satuan ls m3 m3 m3 m3 m3 m2 m3
Volume 1.00 3.00 1.20 1.20 1.80 2.20 2.80 -
II 1 2
3 4 5 6 7 8 9 10 11
III 1 2
195
Item Paket Lokasi NO
Sub Total I Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. Pipa Steel ND. 100 mm ASTM A120, t = 7 mm Pipa PVC ND. 50 mm, S.12.5 (RRJ) Loose Flange ND. 100 mm, Steel Bend 45 all flange ND. 100 mm, steel Bend 45 all flange ND. 100 mm, steel Bend 90° all socket ND 50 mm PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Tee all socket ND 100 mm x 50 mm PVC Flange adaptor ND. 100 mm, CI Flange socket ND. 100 mm, PVC RRJ Flange socket ND. 50 mm, PVC RRJ Flange spigot ND. 100 mm, PVC Flange spigot ND. 50 mm, PVC Gate Valve ND. 100 mm all flange, CI. Gate Valve ND. 50 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street Box Inside Dia. 150 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III Pekerjaan lain-lain. Pengecatan pipa dan konstruksi baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
m m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
10.00 6.00 4.00 2.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I II Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 100 mm ASTM A120, t = 7 mm
Satuan
Volume
I
1 2 3 4 5 6 7 8
ls m3 m3 m3 m3 m3 m2 m3
1.00 3.00 1.20 1.20 1.80 2.20 2.80 -
m
9.00
2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
Pipa PVC ND. 50 mm, S.12.5 (RRJ) Loose Flange ND. 100 mm, Steel Bend 45 all flange ND. 100 mm, steel Bend 45 flange spigot ND. 100 mm, steel Bend 90° all socket ND 50 mm PVC Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Tee all socket ND 100 mm x 50 mm PVC Flange adaptor ND. 100 mm, CI Flange socket ND. 100 mm, PVC RRJ Flange socket ND. 50 mm, PVC RRJ Flange spigot ND. 100 mm, PVC Flange spigot ND. 50 mm, PVC Gate Valve ND. 100 mm all flange, CI. Gate Valve ND. 50 mm all flange, CI. Air Valve ND. 25 mm all flange, CI Street Box Inside Dia. 150 mm, CI. Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III III Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total III Total I + II + III
196
Item Paket Lokasi NO 1 2 3 4 5 6 7 8
II 1 2 3 4
6.00 4.00 2.00 2.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m. Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
m bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
Pekerjaan Tanah dan pasangan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Pemadatan tanah perlapis 25 cm Buangan tanah disekitar lokasi Pasangan Batu, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 15 mm. Beton Bertulang K225, Pilar Jembatan 50/50. camp. 1:2:3 baja U.24, 125 kg/m3. Sub Total I Pekerjaan Pengadaan dan Pemasangan Konstruksi Rangka Baja. Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. baut 40 cm (dilas pada plat), mur M.22. Gelagar induk IWF200.200.8.12 Plat dudukan pipa Profil Siku 60.60.6
Satuan
Volume
ls m3 m3 m3 m3 m3 m2 m3
1.00 2.60 0.65 0.65 2.20 1.25 0.78
set
2.00
kg kg kg
748.50 13.00 173.40
5 Plat sambung gelagar t = 9 mm 6 Biaya Erection Konstruksi. Sub Total II III Pekerjaan Pengadaan dan Pemasangan Pipa dan Accessories. 1 Pipa Steel ND. 75 mm ASTM A120, t = 7 mm 2 Pipa PVC ND. 50 mm, S.12.5 (RRJ) 3 Klem pipa Dia. 75 mm, plat baja 3 x 50 mm + baut mur. 4 Bend 45 all flange ND.75 mm, steel 5 Bend 90 all socket ND. 75 mm, PVC 6 Bend 90 Socket/spigot ND. 50 mm, PVC.RRJ 7 Loose Flange ND. 75 mm, Steel 8 Tee all socket ND. 75x75 mm, CI 9 Flange adaptor ND. 75 mm, CI 10 Gate Valve ND. 75 mm all flange, CI. 11 Gate Valve ND. 50 mm all flange, CI. 12 Air Valve ND. 25 mm all flange, CI 13 Flange socket ND. 75 mm, PVC RRJ 14 Flange spigot ND. 75 mm, PVC 15 Flange spigot ND. 50 mm, PVC 16 Street box Inside dia. 100 mm, CI. 17 Pemasangan pipa, fitting & accessories termasuk pengadaan baut, mur, ring, paking dan thrusblock. Sub Total III IV Pekerjaan lain-lain. 1 Pengecatan pipa dan konstruksi baja 2 Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Sub Total IV Total I + II + III + IV
kg ls
12.90 1.00
m m bh bh bh bh bh bh bh bh bh bh bh bh bh bh ls
24.00 6.00 5.00 4.00 1.00 1.00 6.00 1.00 2.00 1.00 1.00 1.00 2.00 1.00 1.00 2.00 1.00
ls unit
1.00 2.00
MELALUI SUNGAI
36,437,560
Harga Satuan [Rp] 75,000 19,680 8,620 12,300 7,875 145,690 480,990 27,200
Jumlah [Rp] 75,000 107,059 17,585 25,092 26,775 58,276 1,803,713 155,040 2,268,540
625,000 34,000 360,000 1,300,000 85,100 839,000 753,260 792,700 90,000 8,100,000 1,700,000 475,500 127,700 650,000
10,000,000 204,000 2,880,000 5,200,000 170,200 839,000 1,506,520 1,585,400 90,000 8,100,000 1,700,000 475,500 255,400 650,000 33,656,020
100,000 206,500
100,000 413,000 513,000 36,437,560
46,112,329
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 3,238,083
Jumlah [Rp] 100,000 107,650 23,619 33,702 26,775 1,317,913 1,230,472 2,840,130
261,800
1,047,200
6,559
5,785,299
5,756 5,756 5,756 5,756 5,756 1,350,000
528,064 245,958 327,809 424,224 241,065 1,350,000 9,949,619
625,000 34,000 87,780 1,300,000 85,100 360,000 839,000 753,260 90,000 8,100,000 127,700 2,800,000
10,000,000 204,000 614,460 5,200,000 170,200 2,880,000 839,000 1,506,520 90,000 8,100,000 255,400 2,800,000 32,659,580
250,000 206,500
250,000 413,000 663,000 46,112,329
52,046,808
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200
Jumlah [Rp] 100,000 107,059 17,585 25,092 26,775 1,803,713 155,040 2,235,264
261,800
1,047,200
6,559
8,094,171
5,756 5,756 5,756 5,756 5,756 1,890,000
739,658 340,761 461,638 678,758 385,658 1,890,000 13,637,844
625,000 34,000 87,780 1,300,000 85,100 360,000 839,000 753,260 90,000 8,100,000 127,700 2,800,000
12,500,000 204,000 965,580 5,200,000 170,200 2,880,000 839,000 1,506,520 90,000 8,100,000 255,400 2,800,000 35,510,700
250,000
250,000
206,500
413,000 663,000 52,046,808
54,949,919
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200
Jumlah [Rp] 100,000 107,059 17,585 25,092 26,775 1,803,713 155,040 2,235,264
261,800
1,047,200
6,559
9,256,478
5,756 5,756 5,756 5,756 5,756 2,160,000
844,879 393,486 524,495 678,758 385,658 2,160,000 15,290,955
625,000 34,000 87,780 1,300,000 85,100 360,000 839,000 753,260 90,000 8,100,000 127,700
13,750,000 204,000 965,580 5,200,000 170,200 2,880,000 839,000 1,506,520 90,000 8,100,000 255,400
2,800,000
2,800,000 36,760,700
250,000 206,500
250,000 413,000 663,000 54,949,919
56,442,794
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 3,238,083
Jumlah [Rp] 100,000 107,650 23,619 33,702 26,775 1,317,913 1,230,472 2,840,130
261,800
1,047,200
6,559
10,413,538
5,756 2,430,000
950,446 2,430,000 14,841,184
625,000 34,000 87,780 1,300,000 85,100
15,000,000 204,000 1,053,360 5,200,000 170,200
360,000 839,000 753,260 90,000 8,100,000 127,700 2,800,000
2,880,000 839,000 1,506,520 90,000 8,100,000 255,400 2,800,000 38,098,480
250,000 206,500
250,000 413,000 663,000 56,442,794
63,630,420
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 3,238,083
Jumlah [Rp] 100,000 107,650 23,619 33,702 26,775 1,317,913 1,230,472 2,840,130
261,800
1,047,200
6,559
11,572,041
5,756 5,756 5,756 5,756 5,756 2,700,000
1,056,473 491,800 655,504 848,333 481,900 2,700,000 18,853,251
625,000 34,000 87,780
16,250,000 204,000 1,228,920
1,300,000 85,100 360,000 839,000 753,260 8,100,000 1,700,000 90,000 127,700 2,800,000
5,200,000 170,200 2,880,000 839,000 1,506,520 8,100,000 1,700,000 90,000 255,400 2,800,000 41,224,040
300,000 206,500
300,000 413,000 713,000 63,630,420
107,669,431
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 88,700 145,690 480,990 101,830 27,200 3,238,083
Jumlah [Rp] 100,000 378,643 9,482 13,530 142,853 811,605 458,924 5,531,385 159,873 475,456 25,914,381 33,996,131
261,800
1,047,200
6,559
12,517,760
5,756 5,756 5,756 5,756
2,250,862 1,743,980 1,469,530 347,207
3,240,000
3,240,000 22,616,540
625,000 34,000 87,780
22,500,000 204,000 1,228,920
585,600 1,300,000 85,100 360,000 839,000 753,260 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 127,700 2,800,000
1,171,200 2,600,000 170,200 3,600,000 839,000 3,013,040 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 255,400 2,800,000 50,343,760
300,000 206,500
300,000 413,000 713,000 107,669,431
81,141,038
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 145,690 480,990 101,830 27,200
Jumlah [Rp] 100,000 306,811 9,482 13,530 384,622 5,868,078 134,416 380,800
7,197,738
261,800
1,047,200
6,559
12,517,760
5,756 5,756 5,756 5,756 3,510,000
2,250,862 1,743,980 1,469,530 347,207 3,510,000 22,886,540
625,000 34,000 87,780
22,500,000 204,000 1,228,920
585,600 1,300,000 85,100 360,000 839,000 753,260 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 127,700 2,800,000
1,171,200 2,600,000 170,200 3,600,000 839,000 3,013,040 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 255,400 2,800,000 50,343,760
300,000 206,500
300,000 413,000 713,000 81,141,038
114,929,054
Harga Satuan [Rp]
Jumlah [Rp]
100,000 19,680 8,620 12,300 7,875 88,700 145,690 480,990 101,830 27,200 3,238,083
100,000 306,811 9,482 13,530 811,605 384,622 7,936,335 134,416 462,400 30,826,553 40,985,754
261,800
1,047,200
6,559
12,517,760
5,756 5,756 5,756 5,756 3,510,000
2,250,862 1,743,980 1,469,530 347,207 3,510,000 22,886,540
625,000 34,000 87,780
22,500,000 204,000 1,228,920
585,600 1,300,000 85,100 360,000 839,000 753,260 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 127,700 2,800,000
1,171,200 2,600,000 170,200 3,600,000 839,000 3,013,040 699,000 8,100,000 1,700,000 1,250,000 123,000 90,000 255,400 2,800,000 50,343,760
300,000 206,500
300,000 413,000
713,000 114,929,054
196,169,306
Harga Satuan [Rp] 450,000 19,680 8,620 12,300 7,875 88,700 145,690 480,990 101,830 27,200 3,238,083
Jumlah [Rp] 450,000 528,802 69,486 99,150 148,121 811,605 384,622 9,956,493 134,416 979,200 56,536,935 70,098,829
261,800
2,094,400
6,559
40,995,599
5,756 5,756 5,756 5,756 5,000,000
5,767,603 3,352,923 2,826,241 719,511 5,000,000 60,756,277
550,000 34,000 22,500
36,850,000 1,190,000 1,305,000
685,000 85,100 310,000 520,500 595,000 430,100 6,800,000 1,700,000
2,740,000 170,200 4,960,000 520,500 2,380,000 430,100 6,800,000 1,700,000
1,250,000 123,000 90,000 127,700 3,750,000
1,250,000 123,000 90,000 255,400 3,750,000 64,514,200
350,000 150,000
350,000 450,000 800,000 196,169,306
78,961,988
Harga Satuan [Rp] 100,000 19,680 88,700 8,620 12,300 7,875 480,990 3,238,083
Jumlah [Rp] 100,000 74,784 478,980 23,619 33,702 26,775 2,376,091 1,230,472 4,344,422
261,800
2,094,400
6,559
19,218,737
5,756 5,756 5,756 5,756 5,756 3,780,000
1,241,934 578,257 771,086 855,298 485,814 3,780,000 29,025,526
625,000 34,000 87,780 1,300,000
20,625,000 204,000 1,228,920 5,200,000
85,100 360,000 839,000 753,260 8,100,000 1,700,000 90,000 127,700 2,800,000
170,200 2,160,000 839,000 1,506,520 8,100,000 1,700,000 90,000 255,400 2,800,000 44,879,040
300,000 206,500
300,000 413,000 713,000 78,961,988
30,699,740
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 145,690 480,990 27,200
Jumlah [Rp] 100,000 107,059 17,585 25,092 26,775 58,276 1,803,713 155,040 2,293,540
550,000 34,000 310,000 685,000 85,100 520,500 595,000 483,800 90,000 6,800,000 1,700,000 475,500 127,700
8,800,000 204,000 2,480,000 2,740,000 170,200 520,500 1,190,000 967,600 90,000 6,800,000 1,700,000 475,500 255,400
1,350,000
1,350,000 27,743,200
250,000 206,500
250,000 413,000 663,000 30,699,740
33,008,763
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 3,238,083
Jumlah [Rp] 100,000 107,650 23,619 33,702 26,775 1,317,913 1,230,472 2,840,130
261,800
1,047,200
6,559
5,785,299
5,756 5,756 5,756 5,756 5,756 1,350,000
528,064 245,958 327,809 424,224 241,065 1,350,000 9,949,619
472,500 34,000 79,002 305,000 85,100 225,000 426,000 368,200
7,560,000 204,000 553,014 1,220,000 170,200 1,800,000 426,000 736,400
90,000 4,250,000 127,700 2,500,000
90,000 4,250,000 255,400 2,500,000 19,765,014
250,000 102,000
250,000 204,000 454,000 33,008,763
98,179,223
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 304,646 9,482 13,530 113,164 7,936,335 1,005,312 41,803,656 51,286,125
261,800
2,094,400
6,559 5,756 5,756 5,756 5,756 4,500,000
11,843,465 2,272,505 1,983,549 220,458 1,626,671 4,500,000 24,541,048
244,000 28,000 20,250 262,600 285,000 41,200 190,000
8,052,000 168,000 303,750 1,050,400 570,000 82,400 1,900,000
488,000 255,600 2,150,000 970,000 475,500 198,300 94,100 127,700 4,320,000
488,000 511,200 2,150,000 970,000 475,500 198,300 94,100 255,400 4,320,000 21,589,050
350,000 206,500
350,000 413,000 763,000 98,179,223
24,069,481
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 217,600 2,525,705 3,526,633
261,800
1,047,200
6,559 5,756 5,756 5,756 1,400,000
2,912,327 198,585 336,731 215,853 1,400,000 6,110,697
244,000 28,000 20,250
4,880,000 168,000 101,250
41,200 190,000 286,000 255,600 2,150,000 970,000 475,500 198,300 94,100 175,600 85,600 127,700 2,350,000
41,200 1,140,000 286,000 511,200 2,150,000 970,000 475,500 198,300 94,100 175,600 85,600 255,400 2,350,000 13,882,150
350,000 150,000
250,000 300,000 550,000 24,069,481
16,048,227
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 94,464 13,792 19,680 25,200 1,871,051 127,840 2,252,027
244,000 28,000 190,000 167,000 225,600 36,500 41,200 286,000 255,600
3,904,000 168,000 760,000 334,000 451,200 36,500 41,200 286,000 255,600
198,300 94,100 175,600 85,600 2,150,000 970,000 475,500 148,800 2,350,000
198,300 94,100 175,600 85,600 2,150,000 970,000 475,500 297,600 2,350,000 13,033,200
350,000 206,500
350,000 413,000 763,000 16,048,227
14,584,227
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 94,464 13,792 19,680 25,200 1,871,051 127,840 2,252,027
244,000 28,000 190,000 167,000 225,600 36,500 41,200 286,000 255,600 198,300 94,100 175,600 85,600
2,440,000 168,000 760,000 334,000 451,200 36,500 41,200 286,000 255,600 198,300 94,100 175,600 85,600
2,150,000 970,000 475,500 148,800 2,350,000
2,150,000 970,000 475,500 297,600 2,350,000 11,569,200
350,000 206,500
350,000 413,000 763,000 14,584,227
18,552,748
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 272,000 2,525,705 3,581,033
261,800
523,600
6,559 5,756 5,756 5,756 1,850,000
1,397,130 126,634 86,341 1,850,000 3,983,705
139,000 28,000 71,102 75,000 36,500 41,200 123,000
2,502,000 168,000 355,509 300,000 36,500 41,200 738,000
215,300 220,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 127,700 1,750,000
215,300 440,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 255,400 1,750,000 10,325,009
250,000 206,500
250,000 413,000 663,000 18,552,748
18,216,912
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 2,525,705 3,309,033
261,800
523,600
6,559 5,756 5,756 5,756 1,850,000
1,117,704 96,127 60,439 1,850,000 3,647,870
139,000
2,224,000
28,000 71,102 75,000 36,500 41,200 123,000 215,300 220,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 127,700 2,200,000
168,000 355,509 300,000 36,500 41,200 738,000 215,300 440,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 255,400 2,200,000 10,497,009
350,000 206,500
350,000 413,000 763,000 18,216,912
18,088,855
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 2,525,705 3,309,033
261,800
523,600
6,559 5,756 5,756
978,647 96,127 -
5,756 2,000,000
60,439 2,000,000 3,658,813
139,000 28,000 71,102 75,000 36,500 41,200 123,000 215,300 220,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 127,700 2,200,000
2,085,000 168,000 355,509 300,000 36,500 41,200 738,000 215,300 440,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 255,400 2,200,000 10,358,009
350,000 206,500
350,000 413,000 763,000 18,088,855
17,489,340
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 2,525,705 3,309,033
261,800
523,600
6,559 5,756 5,756 5,756 1,850,000
838,278 75,980 60,439 1,850,000 3,348,297
139,000 28,000 71,102 75,000 36,500 41,200 123,000 215,300 220,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 127,700 2,200,000
1,946,000 168,000 355,509 300,000 36,500 41,200 738,000 215,300 440,000 1,700,000 970,000 475,500 90,000 94,100 107,900 85,600 255,400 2,200,000 10,219,009
200,000 206,500
200,000 413,000 613,000 17,489,340
10,395,657
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875
Jumlah [Rp] 100,000 59,040 10,344 14,760 14,175
480,990 27,200 3,238,083
1,058,178 76,160 1,332,657
139,000 12,000 123,000 75,000 198,600 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 148,800 2,200,000
1,529,000 72,000 492,000 150,000 397,200 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 297,600 2,200,000 8,450,000
200,000 206,500
200,000 413,000 613,000 10,395,657
10,009,457
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 59,040 10,344 14,760 14,175 1,058,178 76,160 -
1,332,657
139,000 12,000 123,000 75,000 75,000 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 148,800 2,200,000
1,390,000 72,000 492,000 150,000 150,000 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 297,600 2,200,000 8,063,800
200,000 206,500
200,000 413,000 613,000 10,009,457
10,117,657
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 59,040 10,344 14,760 14,175 1,058,178 76,160 1,332,657
139,000
1,251,000
12,000 123,000 75,000 198,600 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 148,800 2,200,000
72,000 492,000 150,000 397,200 8,200 41,200 12,800 220,000 90,000 68,200 107,900 62,400 1,700,000 526,000 475,500 297,600 2,200,000 8,172,000
200,000 206,500
200,000 413,000 613,000 10,117,657
21,084,755
Harga Satuan [Rp] 100,000 19,680 8,620 12,300 7,875 480,990 27,200 3,238,083
Jumlah [Rp] 100,000 51,168 5,603 7,995 17,325 601,238 2,525,705 3,309,033
261,800
523,600
6,559 5,756 5,756
4,909,633 74,829 998,106
5,756 2,025,000
74,254 2,025,000 8,605,422
98,000 12,000 16,500 126,800 36,500 19,000 97,000 98,000 147,500 970,000 526,000 475,500 94,100 85,600 62,400 127,700 2,000,000
2,352,000 72,000 82,500 507,200 36,500 19,000 582,000 98,000 295,000 970,000 526,000 475,500 188,200 85,600 62,400 255,400 2,000,000 8,607,300
150,000 206,500
150,000 413,000 563,000 21,084,755
HARGA SATUAN UPAH DAN BAHAN BANGUNAN
A. HARGA SATUAN UPAH NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
URAIAN Pekerja Pekerja semi terampil Pekerja terampil Tukang batu semi terampil Tukang batu Kepala tukang batu Tukang kayu semi terampil Tukang kayu Kepala tukang kayu Tukang cat/pelitur semi terampil Tukang cat/pelitur Kepala tukang cat/pelitur Tukang besi beton semi terampil Tukang besi beton Kepala tukang besi beton Tukang besi profil semi terampil Tukang besi profil Kepala tukang besi profil Tukang las tidak bersertifikat Tukang las Tukang pipa Mandor Operator semi terampil Operator terampil Pembantu operator Sopir Pembantu sopir Penjaga Malam
SATUAN Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari Orang/Hari
HARGA [Rp] 25,000 33,300 37,500 38,300 38,300 41,700 41,700 42,500 45,800 41,700 42,500 45,800 41,700 45,800 50,000 42,500 45,800 50,000 41,700 50,000 37,500 37,500 45,800 50,000 50,000 50,000 33,300 33,300
B. BIAYA OPERASI DAN KEPEMILIKAN ALAT NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
URAIAN Air Compressor 150 M3 Concrete Mixer 0,25 M3 Concrete Vibrator Dump Truck 3,5 Ton Hydraulic Excavator 1,3 M3 Jack Hammer Pickup Truck Plat Bed Truck 4 Ton Plate Vibrator Tamper Pressure Pump 20 Bar Stone Crusher 20 Ton/Jam Tandem Roller 6 - 10 Ton Tree Wheel Roller 51 HP Vibro Roller 600 Kg Water Pump (Dia. 5 Cm) Water Tank Truck 5000 Ltr Welding Mechine 500A Biaya Anggkutan
SATUAN per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per jam per m3
HARGA [Rp] 15,600 17,900 7,300 47,900 109,300 15,600 47,900 50,000 4,200 10,400 36,400 47,900 21,900 15,600 10,400 31,200 16,700 22,800
Perusahaan Daerah Air Minum Tirta Galuh Ciamis Direktur Utama
Ir. Triani PD
C. HARGA SATUAN BAHAN BANGUNAN. NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 57
URAIAN Abu batu/Filler Angkur baut M16 Anyaman bambu belah Asbes Eternit 100 x 100 cm Aspal Bahan cairan spay uji las (2 tube) Bata merah lokal Batu belah 15/20 Batu bronjong Batu koral kali Batu pecah 0,5 - 1 Batu pecah 1 - 2 Batu pecah 2 - 3 Baut mur M12 Besi Plat Besi profil Ex DN (SII) Besi siku Besi strip 3 mm Besi tulangan polos Cat besi Coltar primer anti karat Genteng bubungan Genteng Pres Karbit Kawat beton Kawat bronjong 3 mm Kawat las listrik Kayu bakar Kayu bekisting Kayu Borneo Kayu dolken dia. 8 cm 4 m Kayu Kamper medan Kayu Multiplek 4 mm (122 x 242 cm) Kayu Papan Multiplek 16 mm Keramik 20x20 kelas I Kerikil sungai tersaring Kerikil sungai tidak disaring Kertas ampelas besi Kuas Lem kayu Meni besi Minyak bakar Minyak cat Minyak tanah Mozaik 30x30 cm Paku biasa Pasir beton Pasir pasang Pasir urug Paving block natural 8 cm Tanah merah
NO 51 52 53 54 55
URAIAN Pelumas Pipa PVC D Dia. 4" Porselin 10x10 cm Portland cement Premium
SATUAN m3 bh m2 bh kg unit bh m3 m3 m3 m3 m3 m3 bh kg kg kg kg kg kg kg bh bh kg kg kg kg m3 m3 m3 btg m3 lbr lbr m2 m3 m3 bh bh kg kg ltr kg ltr bh kg m3 m3 m3 m2 m3
SATUAN ltr m dos zak ltr
HARGA [Rp] 139,900 29,200 10,800 10,000 5,800 149,900 400 95,800 95,800 87,500 108,300 136,600 136,600 29,200 11,500 6,000 6,000 6,000 6,200 40,800 12,900 5,700 3,900 6,100 12,500 20,000 11,100 82,500 1,457,800 2,633,900 25,000 3,956,800 45,600 228,200 62,500 79,100 75,000 5,400 11,200 25,000 12,900 2,400 3,200 1,700 8,000 10,800 133,300 116,600 78,300 65,800 33,700
HARGA [Rp] 10,800 56,900 49,100 48,300 4,500
56 58 59 60 61
Solar Tangki Vibreglass kapasitas 0.6 m3. Tangki Vibreglass kapasitas 1 m3. Terpentin Tiner
ltr unit unit kg kg
4,300 1,041,300 1,249,500 3,200 37,500
Perusahaan Daerah Air Minum Tirta Galuh Ciamis Direktur Utama
Ir. Triani PD
HARGA SATUAN UPAH DAN BAHAN BANGUNAN PIPA DAN ACCESSORIES D. HARGA SATUAN PIPA FITTING DAN ACCESSORIES. NO 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 47 55
URAIAN Air Valve (Double) ND. 50 mm all flange, CI Air Valve ND. 25 mm all flange, CI Bend 11 1/4 all flange ND. 150 mm, steel Bend 11 1/4 all flange ND. 300 mm, steel Bend 11 1/4 Socket/spigot ND. 75 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 100 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 150 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 200 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 250 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 300 mm, PVC.RRJ Bend 11 1/4 Socket/spigot ND. 400 mm, PVC.RRJ Bend 22,5 all flange ND. 150 mm, steel Bend 22,5 all flange ND. 250 mm, steel Bend 22,5 all flange ND. 300 mm, steel Bend 22,5 Socket/spigot ND. 75 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 100 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 150 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 200 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 250 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 300 mm, PVC.RRJ Bend 22,5 Socket/spigot ND. 400 mm, PVC.RRJ Bend 45 all flange ND. 100 mm, steel Bend 45 all flange ND. 150 mm, steel Bend 45 all flange ND. 200 mm, steel Bend 45 all flange ND. 250 mm, steel Bend 45 all flange ND. 300 mm, steel Bend 45 flange spigot ND. 100 mm, steel Bend 45 flange spigot ND. 150 mm, steel Bend 45 Socket/spigot ND. 150 mm, PVC.RRJ Bend 45 Socket/spigot ND. 200 mm, PVC.RRJ Bend 45 Socket/spigot ND. 300 mm, PVC.RRJ Bend 45 Socket/spigot ND. 400 mm, PVC.RRJ Bend 90 all flange ND. 100 mm, steel Bend 90 all flange ND. 150 mm, steel Bend 90 all flange ND. 200 mm, steel Bend 90 all flange ND. 250 mm, Steel Bend 90 all flange ND. 300 mm CI. Bend 90 ND. 150 mm, GS. Bend 90 ND. 250 mm, GS. Bend 90 ND. 300 mm GS. Bend 90 ND. 350 mm Steel. Bend 90 Socket/spigot ND. 50 mm, PVC.RRJ Bend 90 Socket/spigot ND. 75 mm, PVC.RRJ Bend 90 Socket/spigot ND. 100 mm, PVC.RRJ Bend 90 Socket/spigot ND. 200 mm, PVC.RRJ Bend 90 Socket/spigot ND. 250 mm, PVC.RRJ Bend 90 Socket/spigot ND. 300 mm, PVC.RRJ Bend 90 Socket/spigot ND. 400 mm, PVC.RRJ Bend 90 all socket ND. 75 mm, PVC Blind flange ND. 50 mm, PVC Blind flange ND. 75 mm, PVC Blind flange ND. 100 mm, PVC Blind flange ND. 250 mm, Steel Blind flange ND. 300 mm, Steel Blind flange ND. 400 mm, Steel Dop ND. 50 mm, PVC RRJ
SATUAN bh bh bh bh unit unit unit unit unit unit unit bh bh bh unit unit unit unit unit unit unit bh bh bh bh bh bh bh unit unit unit unit bh bh bh bh bh bh bh bh bh unit unit unit unit unit unit unit unit bh bh bh bh bh bh bh
HARGA [Rp] 1,250,000 475,500 262,600 585,600 26,400 41,000 114,900 199,900 351,000 563,700 1,180,000 285,000 395,000 625,000 29,800 46,400 134,700 228,800 393,500 679,700 1,230,000 75,000 167,000 305,000 685,000 1,300,000 198,600 225,600 160,200 371,300 838,900 1,360,000 85,000 230,000 375,000 765,000 1,750,000 268,000 386,200 650,000 715,000 19,000 41,200 85,100 491,600 706,300 1,270,000 1,420,000 36,500 51,000 65,000 76,100 178,500 228,300 345,000 14,800
NO 48 56 49 57 50 51 52 53 54 55 56 57 58 59 60 61 62
URAIAN Dop ND. 75 mm, PVC RRJ Dop ND. 100 mm, PVC RRJ Flange adaptor ND. 50 mm, CI Flange adaptor ND. 75 mm, CI Flange adaptor ND. 100 mm, CI Flange adaptor ND. 150 mm, CI Flange adaptor ND. 200 mm, CI Flange adaptor ND. 250 mm, CI Flange adaptor ND. 300 mm, CI Flange adaptor ND. 350 mm, CI Flange adaptor ND. 400 mm, CI Flange socket ND. 50 mm, PVC RRJ Flange socket ND. 75 mm, PVC RRJ Flange socket ND. 100 mm, PVC RRJ Flange socket ND. 150 mm, PVC RRJ Flange socket ND. 200 mm, PVC RRJ Flange socket ND. 250 mm, PVC RRJ
SATUAN bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh
HARGA [Rp] 27,000 52,400 80,000 147,500 220,000 255,600 368,200 595,000 753,260 1,030,000 1,265,000 68,200 94,100 90,000 198,300 294,000 483,800
NO 63 64 64 65 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123
URAIAN Flange socket ND. 300 mm, PVC RRJ Flange socket ND. 350 mm, PVC RRJ Flange socket ND. 400 mm, PVC RRJ Flange spigot ND. 50 mm, PVC Flange spigot ND. 75 mm, PVC Flange spigot ND. 100 mm, PVC Flange spigot ND. 150 mm, PVC Flange spigot ND. 200 mm, PVC Flange spigot ND. 250 mm, PVC Flange spigot ND. 300 mm, PVC Flange spigot ND. 400 mm, CI. Gate Valve ND. 50 mm all flange, CI. Gate Valve ND. 75 mm all flange, CI. Gate Valve ND. 100 mm all flange, CI. Gate Valve ND. 150 mm all flange, CI. Gate Valve ND. 200 mm all flange, CI. Gate Valve ND. 250 mm all flange, CI. Gate Valve ND. 300 mm all flange, CI. Gate Valve ND. 350 mm all flange, CI. Gate Valve ND. 400 mm all flange, CI. Giboult Joint ND. 50 mm, CI Giboult Joint ND. 75 mm, CI Giboult Joint ND. 100 mm, CI Giboult Joint ND. 150 mm, CI Giboult Joint ND. 200 mm, CI Giboult Joint ND. 250 mm, CI Giboult Joint ND. 300 mm, CI Giboult Joint ND. 400 mm, CI Klem pipa ND. 400 mm, plat baja 3 x 50 mm + baut mur. Klem pipa ND. 300 mm, plat baja 3 x 50 mm + baut mur. Klem pipa ND. 250 mm, plat baja 3 x 50 mm + baut mur. Klem pipa ND. 200 mm, plat baja 3 x 50 mm + baut mur. Klem pipa ND. 150 mm, plat baja 3 x 50 mm + baut mur. Klem pipa ND. 100 mm, plat baja 3 x 50 mm + baut mur. Loose Flange ND. 75 mm, Steel Loose Flange ND. 100 mm, Steel Loose Flange ND. 150 mm, Steel Loose Flange ND. 200 mm, Steel Loose Flange ND. 250 mm, Steel Loose Flange ND. 300 mm, Steel Loose Flange ND. 350 mm, Steel Loose Flange ND. 400 mm, Steel Baut, mur dan ring , baja hitam mutu tinggi Pipa GS. ND. 200 mm Pipa GS. ND. 250 mm Pipa GS. ND. 300 mm Pipa PVC ND. 50 mm, S.8 (RRJ) Pipa PVC ND. 75 mm, S.8 (RRJ) Pipa PVC ND. 100 mm, S.8 (RRJ) Pipa PVC ND. 150 mm, S.8 (RRJ) Pipa PVC ND. 200 mm, S.8 (RRJ) Pipa PVC ND. 250 mm, S.8 (RRJ) Pipa PVC ND. 300 mm, S.8 (RRJ) Pipa PVC ND. 400 mm, S.8 (RRJ) Pipa PVC ND. 50 mm, S.10 (RRJ) Pipa PVC ND. 75 mm, S.10 (RRJ) Pipa PVC ND. 100 mm, S.10 (RRJ) Pipa PVC ND. 150 mm, S.10 (RRJ) Pipa PVC ND. 200 mm, S.10 (RRJ) Pipa PVC ND. 250 mm, S.10 (RRJ) Pipa PVC ND. 300 mm, S.10 (RRJ) Pipa PVC ND. 400 mm, S.10 (RRJ) Pipa PVC ND. 50 mm, S.12.5 (RRJ)
SATUAN bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh m m m m m m m m m m m m m m m m m m m m
HARGA [Rp] 792,700 820,000 980,000 62,400 85,600 107,900 175,600 263,400 430,100 699,000 865,000 526,000 970,000 1,700,000 2,150,000 4,250,000 6,800,000 8,100,000 15,600,000 20,225,000 76,200 120,000 178,600 215,000 312,500 475,600 605,000 1,265,000 96,558 87,780 22,500 79,002 20,250 71,102 97,000 123,000 190,000 225,000 310,000 360,000 400,000 480,000 4,000 472,500 532,800 665,800
389,200 15,000 26,100 40,400 85,250 140,000 210,000 333,250 564,100 12,000
NO 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139
URAIAN Pipa PVC ND. 75 mm, S.12.5 (RRJ) Pipa PVC ND. 100 mm, S.12.5 (RRJ) Pipa PVC ND. 150 mm, S.12.5 (RRJ) Pipa PVC ND. 200 mm, S.12.5 (RRJ) Pipa PVC ND. 250 mm, S.12.5 (RRJ) Pipa PVC ND. 300 mm, S.12.5 (RRJ) Pipa PVC ND. 400 mm, S.12.5 (RRJ) Pipa Steel ND. 50 mm Pipa Steel ND. 75 mm Pipa Steel ND. 100 mm Pipa Steel ND. 150 mm Pipa Steel ND. 200 mm Pipa Steel ND. 250 mm Pipa Steel ND. 300 mm Pipa Steel ND. 350 mm Pipa Steel ND. 400 mm
SATUAN m m m m m m m m m m m m m m m m
HARGA [Rp] 28,000 34,000 72,000 114,000 179,000 230,000 534,000 47,000 98,000 139,000 244,000 268,000 550,000 625,000 815,000 1,079,000
NO 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200
URAIAN Pudle flange ND. 100 mm, steel tebal 3 mm Pudle flange ND. 150 mm, steel tebal 3 mm Pudle flange ND. 250 mm, steel tebal 3 mm Pudle flange ND. 300 mm, steel tebal 5 mm Pudle flange ND. 350 mm, steel tebal 5 mm Pudle flange ND. 400 mm, steel tebal 5 mm Reducer all Flange ND. 150x100 mm, CI Reducer all Flange ND. 300x250 mm, CI Reducer all Flange ND. 350x250 mm, CI Reducer all Flange ND. 350x300 mm, CI Reducer all Flange ND. 400x300 mm, CI Reducer all Socket ND. 400x350 mm, CI Reducer all Socket ND. 75x50 mm, PVC.RRJ Reducer all Socket ND. 100x50 mm, PVC.RRJ Reducer all Socket ND. 100x75 mm, PVC.RRJ Reducer all Socket ND. 150x100 mm, PVC.RRJ Reducer all Socket ND. 150x75 mm, PVC.RRJ Reducer all Socket ND. 200x100 mm, PVC.RRJ Reducer all Socket ND. 200x150 mm, PVC.RRJ Reducer all Socket ND. 250x150 mm, PVC.RRJ Reducer all Socket ND. 250x200 mm, PVC.RRJ Reducer all Socket ND. 300x200 mm, PVC.RRJ Reducer all Socket ND. 300x250 mm, PVC.RRJ Reducer all Socket ND. 350x250 mm, PVC.RRJ Street box Inside dia. 100 mm, CI. Street box Inside dia. 150 mm, CI. Tee all flange ND. 100 x 100 mm, CI Tee all flange ND. 150 x 75 mm, CI Tee all flange ND. 150 x 100 mm, CI Tee all flange ND. 150 x 150 mm, CI Tee all flange ND. 200 x 100 mm, CI Tee all flange ND. 200 x 150 mm, CI Tee all flange ND. 250 x 100 mm, CI Tee all flange ND. 250 x 250 mm, CI Tee all flange ND. 300 x 100 mm, CI Tee all flange ND. 300 x 150 mm, CI Tee all flange ND. 300 x 300 mm CI. Tee all flange ND. 350 x 250 mm CI. Tee all flange ND. 350 x 350 mm CI. Tee all socket ND. 75x75 mm, CI Tee all socket ND. 100x75 mm, CI Tee all socket ND. 150x75 mm, CI Tee all socket ND. 200x100 mm, CI Tee all socket ND. 300x100 mm, CI Tee all socket ND. 300x50 mm, CI Tee all socket ND. 400x400 mm, CI Tee double socket and flange end ND. 100x100 mm, PVC Tee double socket and flange end ND. 100x50 mm, PVC Tee double socket and flange end ND. 100x75 mm, PVC Tee double socket and flange end ND. 150x100 mm, PVC Tee double socket and flange end ND. 150x75 mm, PVC Tee double socket and flange end ND. 200x100 mm, PVC Tee double socket and flange end ND. 250x250 mm, PVC Tee double socket and flange end ND. 50x50 mm, PVC Tee double socket and flange end ND. 75x50 mm, PVC Tee double socket and flange end ND. 75x75 mm, PVC Tee Y all flange ND. 300 x 300 mm CI. Wall pipe all flange ND. 300 mm CI. Wall pipe all flange ND. 350 mm CI. Water meter 1/2" Water meter induk ND. 50 mm
SATUAN bh bh bh bh bh bh unit unit unit bh unit unit unit unit unit unit unit unit unit unit unit unit unit unit bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh bh unit unit
HARGA [Rp] 34,200 44,900 64,200 127,150 149,250 173,100 243,800 630,000 740,500 965,000 1,354,000 1,468,000 30,700 43,700 45,000 84,000 80,200 130,800 134,200 223,400 234,900 377,400 386,800 510,000 127,700 148,800 136,300 320,000 488,000 424,500 426,000 595,000 520,500 815,000 839,000 866,000 912,500 910,000 965,000 98,000 215,300 286,000 326,800 564,000 386,000 768,000 380,000 260,000 325,000 426,000 375,000 510,000 1,125,000 76,000 110,000 146,000 1,145,000 760,800 895,600 145,750 8,200,000
NO 201 202 203 204 205 206
URAIAN Water meter induk ND. 75 mm Water meter induk ND. 100 mm Water meter induk ND. 150 mm Water meter induk ND. 200 mm Water meter induk ND. 250 mm Water meter induk ND. 300 mm
SATUAN unit unit unit unit unit unit
HARGA [Rp] 9,750,000 11,150,000 19,800,000 22,200,000 38,400,000 48,000,000
Item Paket Lokasi
: TAPING POINT : :
NO
URAIAN BAHAN Kebutuhan Accessories Tee all flange 250 x 250 Gate Valve dia 250 mm Pipa Steel dia 250 mm loose Flange dia 250 mm Flange Socket dia 250 mm
Jumlah
Satuan
bh bh bh bh bh
Volume
1.00 3.00 18.00 5.00 2.00
Harga Satuan [Rp]
729,000.00 8,022,000.00 385,000.00 520,000.00 422,600.00
Jumlah [Rp]
729,000.00 24,066,000.00 6,930,000.00 2,600,000.00 845,200.00
35,170,200.00
PEKERJAAN PERLINTASAN PIPA MELALAUI JALAN CROSSING JALAN BOR HORIZONTAL 197
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 50,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 21.00 19.95 18.95 19.95 8.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 3.00 16.00 3.00 2.00 8.00
m bh m3
50.00 4.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 400 mm 2 Loose flange ND. 400 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
198
Item Paket Lokasi NO
Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I 1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
Satuan ls m3 m3 m3 m3 m1
Volume 1.00 8.40 7.98 7.58 7.98 3.00
II 1 2 3 4 5 6 III
IV
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 400 mm 2 Loose flange ND. 400 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
ls ah jam oh oh oh
1.00 3.00 16.00 3.00 2.00 8.00
m bh m3
20.00 2.00 0.20
ls
1.00
Total I + II + III + IV
199
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 8.40 7.98 7.58 7.98 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 8.00
m bh m3
15.00 2.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 300 mm 2 Loose flange ND. 300 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
200
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 18,00 m : :
NO
URAIAN BAHAN
I 1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
1 2 3 4 5 6 7
Pekerjaan Pengeboran Horisontal Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya Pengeboran Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
1 2 3 4
II
III
IV
Satuan
Volume
ls m3 m3 m3 m3 m1
1.00 18.00 17.10 16.25 17.10 27.00
ls hari meter jam oh oh oh
1.00 20.00 18.00 24.00 2.00 2.00 8.00
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 300 mm Loose flange ND. 300 mm, Steel Pemasangan Thrusblock Flange socket ND. 300 mm
m bh bh bh
18.00 2.00 2.00 2.00
Pek. Lain-lain. Perbaikan dan perbersihan saluran akibat pekerjaan.
ls
1.00
Total I + II + III + IV
201
Item Paket Lokasi NO
URAIAN BAHAN
I 1 2 3 4 5 6 II
Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m : :
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m Pekerjaan Pengeboran Horisontal
Satuan ls m3 m3 m3 m3 m1
Volume 1.00 12.00 8.40 4.20 8.40 8.00
1 2 3 4 5 6 7
Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya Pengeboran Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
1 2 3 4
III
IV
ls hari meter jam oh oh oh
1.00 20.00 18.00 24.00 2.00 2.00 8.00
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 100 mm Loose flange ND. 100 mm, Steel Pemasangan Thrusblock Flange socket ND. 100 mm
m bh bh bh
10.00 2.00 2.00 2.00
Pek. Lain-lain. Perbaikan dan perbersihan saluran akibat pekerjaan.
ls
1.00
Total I + II + III + IV
202
Item Paket Lokasi NO
URAIAN BAHAN
I
IV
Satuan
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 8.40 7.98 7.58 7.98 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 8.00
m bh m3
15.00 2.00 0.20
ls
1.00
II
III
Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 250 mm 2 Loose flange ND. 250 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
Total I + II + III + IV
203
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 8.00
m bh m3
12.00 2.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 250 mm 2 Loose flange ND. 250 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
204
Item Paket Lokasi NO
URAIAN BAHAN
I 1 2 3 4 5 6 II
Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
Pekerjaan Pengeboran Horisontal, L 2.5 m 1 Transportasi alat ke lokasi pekerjaan.
Satuan
Volume
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
ls
1.00
2 3 4 5 6 III
IV
Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 250 mm 2 Loose flange ND. 250 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
ah jam oh oh oh
2.00 12.00 2.00 1.50 8.00
m bh m3
10.00 2.00 0.20
ls
1.00
Total I + II + III + IV
205
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 8.00
m bh m3
15.00 2.00 0.20
ls
1.00
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 200 mm 2 Loose flange ND. 200 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
206
Volume
1 2 3 4 5 6 II
III
Satuan
Item Paket
Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa.
Lokasi
:
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 7.00
m bh m3
10.00 2.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 150 mm 2 Loose flange ND. 150 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
207
Item Paket Lokasi NO
URAIAN BAHAN
I
Satuan
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 1.75 1.66 1.58 1.66 5.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 7.00
II
III
Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 25,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pengadaan dan Pemasangan Pipa & Acc.
1 Pipa Steel ND. 150 mm 2 Loose flange ND. 150 mm, Steel 3 Pemasangan Thrusblock IV
Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
m bh m3
25.00 6.00 2.00
ls
1.00
Total I + II + III + IV 208
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 12.00 2.00 1.50 7.00
m bh m3
10.00 2.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 150 mm 2 Loose flange ND. 150 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
209
Item Paket Lokasi NO
Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I 1 2 3 4
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan
Satuan ls m3 m3 m3
Volume 1.00 5.60 5.32 5.05
5 Pemadatan tanah perlapis 25 cm 6 Pemasangan turap kayu pengaman galian 1.5 m II 1 2 3 4 5 6 III
IV
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 150 mm 2 Loose flange ND. 150 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
m3 m1
5.32 3.00
ls ah jam oh oh oh
1.00 2.00 9.00 1.50 1.50 6.00
m bh m3
7.00 2.00 0.20
ls
1.00
Total I + II + III + IV
210
Item Paket Lokasi NO
URAIAN BAHAN
I
IV
Satuan
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 9.00 2.00 1.50 6.00
m bh m3
10.00 2.00 0.20
ls
1.00
II
III
Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 100 mm 2 Loose flange ND. 100 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
Total I + II + III + IV
211
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
IV
Volume
1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
1 2 3 4 5 6
Pekerjaan Pengeboran Horisontal, L 2.5 m Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
ls ah jam oh oh oh
1.00 2.00 9.00 2.00 1.50 6.00
m bh m3
7.00 2.00 0.20
ls
1.00
II
III
Satuan
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 100 mm 2 Loose flange ND. 100 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan. Total I + II + III + IV
212
Item Paket Lokasi NO
URAIAN BAHAN
I 1 2 3 4 5 6 II
Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
Pekerjaan Pengeboran Horisontal, L 2.5 m 1 Transportasi alat ke lokasi pekerjaan. 2 Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll)
Satuan
Volume
ls m3 m3 m3 m3 m1
1.00 5.60 5.32 5.05 5.32 3.00
ls ah
1.00 2.00
3 4 5 6 III
IV
Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
Pengadaan dan Pemasangan Pipa & Acc. 1 Pipa Steel ND. 100 mm 2 Loose flange ND. 100 mm, Steel 3 Pemasangan Thrusblock Pengadaan Lain-lain. 2 Perbaikan dan perbersihan saluran akibat pekerjaan.
jam oh oh oh
9.00 2.00 1.50 5.00
m bh m3
10.00 2.00 0.20
ls
1.00
Total I + II + III + IV
CROSSING BIASA 213
Item Paket Lokasi NO
URAIAN BAHAN
I
214
I
Volume
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 7.20 8.64 6.36 2.28 6.36 3.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 300 mm Bend 90 all flange ND. 300 mm CI. Loose flange ND. 300 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
6.00 2.00 2.00 0.20
ls jam ls
1.00 48.00 1.00
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III + IV
Item Paket Lokasi NO
Satuan
1 2 3 4 5 6 7 II
III
Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN Pekerjaan Tanah dan Persiapan
Satuan
Volume
1 2 3 4 5 6 7
Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 6.00 7.20 5.30 1.90 5.30 4.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 300 mm Bend 90 all flange ND. 300 mm CI. Loose flange ND. 300 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
5.00 2.00 2.00 0.20
ls jam ls
1.00 48.00 1.00
II
III
215
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III + IV
Item Paket Lokasi NO
URAIAN BAHAN
I
216
Satuan
Volume
1 2 3 4 5 6 7
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 6.00 5.76 4.24 1.52 4.24 2.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 300 mm Bend 90 all flange ND. 300 mm CI. Loose flange ND. 300 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
4.00 2.00 2.00 0.20
ls jam ls
1.00 48.00 1.00
II
III
Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III + IV
Item Paket Lokasi
Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
NO
URAIAN BAHAN
I
217
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 4.80 5.76 3.86 1.90 3.86 2.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 250 mm Bend 90 ND. 250 mm, GS. Flange adaptor ND. 250 mm, CI Pemasangan Thrusblock
m3 unit bh m3
4.00 2.00 2.00 0.20
ls jam ls
1.00 48.00 1.00
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III
Item Paket Lokasi NO
Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
Satuan
Volume
1 2 3 4 5 6 7
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 18.00 21.60 19.70 1.90 19.70 6.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 150 mm Bend 90 all flange ND. 150 mm, Steel Loose flange ND. 250 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
15.00 2.00 2.00 0.20
ls jam ls
1.00 48.00 1.00
II
III
Volume
1 2 3 4 5 6 7 II
III
Satuan
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III
218
Item Paket Lokasi NO
URAIAN BAHAN
I
219
Volume
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 7.20 8.64 6.36 2.28 6.36 6.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 150 mm Bend 90 all flange ND. 150 mm, Steel Loose flange ND. 250 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
6.00 2.00 2.00 0.20
ls jam ls
1.00 18.00 1.00
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir Total I + II + III
Item Paket Lokasi NO
Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. : URAIAN BAHAN
I
Satuan
Volume
1 2 3 4 5 6 7
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Bongkaran perkerasan Jalan kelas III Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
ls m2 m3 m3 m3 m3 m1
1.00 4.20 7.92 5.64 2.28 5.64 2.00
1 2 3 4
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 50 mm Bend 90 all flange ND. 50 mm, Steel Loose flange ND. 250 mm, Steel Pemasangan Thrusblock
m3 unit bh m3
6.00 2.00 2.00 0.20
ls jam ls
1.00 18.00 1.00
II
III
Satuan
1 2 3 4 5 6 7 II
III
Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m Pemasangan Pipa Transmisi dan Jembatan Pipa. :
Pengadaan Lain-lain. 1 Transportasi alat ke lokasi pekerjaan. 2 Biaya operasi Pompa Air 3 Perbersihan akhir
Total I + II + III
ALAUI JALAN
64,996,555
Harga Satuan [Rp]
Jumlah [Rp]
250,000 19,680 8,620 101,830 12,300 50,670
250,000 413,280 171,969 1,929,933 245,385 405,360
1,500,000 350,000 10,400 25,000 37,500 25,000
1,500,000 1,050,000 166,400 75,000 75,000 200,000
1,079,000 480,000 721,137
53,950,000 1,920,000 144,227
2,500,000
2,500,000 64,996,555 24,981,864
Harga Satuan [Rp] 25,000 19,680 8,620 101,830 12,300 50,670
Jumlah [Rp] 25,000 165,312 68,788 771,973 98,154 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 150,000 166,400 75,000 75,000 200,000
1,079,000 480,000 721,137
21,580,000 960,000 144,227
250,000
250,000 24,981,864
12,351,514
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 165,312 68,788 771,973 98,154 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 200,000
625,000 360,000 721,137
9,375,000 720,000 144,227
200,000
200,000 12,351,514
31,514,290
Harga Satuan [Rp]
Jumlah [Rp]
250,000 19,680 8,620 101,830 12,300 50,670
250,000 354,240 147,402 1,654,228 210,330 1,368,090
1,500,000 260,000 350,000 10,400 25,000 37,500 25,000
1,500,000 5,200,000 6,300,000 249,600 50,000 75,000 200,000
625,000 360,000 75,000 792,700
11,250,000 720,000 150,000 1,585,400
250,000
250,000 31,514,290
6,785,534
Harga Satuan [Rp] 250,000 19,680 8,620 101,830 12,300 50,670
Jumlah [Rp] 250,000 236,160 72,408 427,686 103,320 405,360
500,000 50,000 65,000 10,400 25,000 37,500 25,000
500,000 1,000,000 1,170,000 249,600 50,000 75,000 200,000
139,000 123,000 65,000 90,000
1,390,000 246,000 130,000 180,000
100,000
100,000 6,785,534
11,176,514
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 165,312 68,788 771,973 98,154 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 200,000
550,000 310,000 721,137
8,250,000 620,000 144,227
250,000
250,000
11,176,514
9,108,439
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 200,000
550,000 310,000 721,137
6,600,000 620,000 144,227
200,000
200,000 9,108,439
8,058,439
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000
100,000
50,000 10,400 25,000 37,500 25,000
100,000 124,800 50,000 56,250 200,000
550,000 310,000 721,137
5,500,000 620,000 144,227
250,000
250,000 8,058,439
6,358,439
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 200,000
268,000 225,000 721,137
4,020,000 450,000 144,227
200,000
200,000 6,358,439
4,683,439
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 175,000
244,000 190,000 721,137
2,440,000 380,000 144,227
200,000
200,000 4,683,439 13,521,722
Harga Satuan [Rp]
Jumlah [Rp]
250,000 19,680 8,620 101,830 12,300 50,670
250,000 34,440 14,331 160,828 20,449 253,350
750,000 1,250,000 10,400 25,000 37,500 25,000
750,000 2,500,000 124,800 50,000 56,250 175,000
244,000 190,000 721,137
6,100,000 1,140,000 1,442,274
450,000
450,000 13,521,722 4,633,439
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 124,800 50,000 56,250 175,000
244,000 190,000 721,137
2,440,000 380,000 144,227
150,000
150,000 4,633,439
3,932,739
Harga Satuan [Rp] 25,000 19,680 8,620 101,830
Jumlah [Rp] 25,000 110,208 45,858 514,649
12,300 50,670
65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 93,600 37,500 56,250 150,000
244,000 190,000 721,137
1,708,000 380,000 144,227
250,000
250,000 3,932,739
3,393,239
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 93,600 50,000 56,250 150,000
139,000 123,000 721,137
1,390,000 246,000 144,227
150,000
150,000
3,393,239
3,076,239
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000 10,400 25,000 37,500 25,000
100,000 100,000 93,600 50,000 56,250 150,000
139,000 123,000 721,137
973,000 246,000 144,227
250,000
250,000 3,076,239
3,468,239
Harga Satuan [Rp]
Jumlah [Rp]
25,000 19,680 8,620 101,830 12,300 50,670
25,000 110,208 45,858 514,649 65,436 152,010
100,000 50,000
100,000 100,000
10,400 25,000 37,500 25,000
93,600 50,000 56,250 125,000
139,000 123,000 721,137
1,390,000 246,000 144,227
250,000
250,000 3,468,239
9,792,392
Harga Satuan [Rp]
Jumlah [Rp]
100,000 19,680 19,680 8,620 101,830 12,300 50,670
100,000 141,696 170,035 54,823 232,172 78,228 152,010
625,000 1,750,000 360,000 721,137
3,750,000 3,500,000 720,000 144,227
150,000 10,400 100,000
150,000 499,200 100,000 9,792,392
9,105,236
Harga Satuan [Rp]
Jumlah [Rp]
100,000 19,680 19,680 8,620 101,830 12,300 50,670
100,000 118,080 141,696 45,686 193,477 65,190 202,680
625,000 1,750,000 360,000 721,137
3,125,000 3,500,000 720,000 144,227
150,000 10,400 100,000
150,000 499,200 100,000 9,105,236
8,289,687
Harga Satuan [Rp]
Jumlah [Rp]
100,000 19,680 19,680 8,620 101,830 12,300 50,670
100,000 118,080 113,357 36,549 154,782 52,152 101,340
625,000 1,750,000 360,000 721,137
2,500,000 3,500,000 720,000 144,227
150,000 10,400 100,000
150,000 499,200 100,000 8,289,687
5,739,216
Harga Satuan [Rp]
Jumlah [Rp]
100,000 19,680 19,680 8,620 101,830 12,300 50,670
100,000 94,464 113,357 33,273 193,477 47,478 101,340
550,000 386,200 595,000 721,137
2,200,000 772,400 1,190,000 144,227
150,000 10,400 100,000
150,000 499,200 100,000 5,739,216
8,664,736
Harga Satuan [Rp]
Jumlah [Rp]
100,000 88,700 19,680 8,620 101,830 12,300 50,670
100,000 1,596,600 425,088 169,814 193,477 242,310 304,020
244,000 230,000 310,000 721,137
3,660,000 460,000 620,000 144,227
150,000 10,400 100,000
150,000 499,200 100,000 8,664,736
4,703,346
Harga Satuan [Rp]
Jumlah [Rp]
100,000 88,700 19,680 8,620 101,830 12,300 50,670
100,000 638,640 170,035 54,823 232,172 78,228 304,020
244,000 230,000 310,000 721,137
1,464,000 460,000 620,000 144,227
150,000 10,400 100,000
150,000 187,200 100,000 4,703,346
2,527,334
Harga Satuan [Rp]
Jumlah [Rp]
100,000 88,700 19,680 8,620 101,830 12,300 50,670
100,000 372,540 155,866 48,617 232,172 69,372 101,340
47,000 32,000 310,000 721,137
282,000 64,000 620,000 144,227
75,000 10,400 75,000
75,000 187,200 75,000
2,527,334
Item Paket Lokasi
Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m : :
NO
URAIAN BAHAN
I 1 2 3 4 5 6
Pekerjaan Tanah dan Persiapan Setting Out dan penyiapan lokasi. Galian tanah biasa Urugan tanah kembali Urugan pasir dipadatkan Pemadatan tanah perlapis 25 cm Pemasangan turap kayu pengaman galian 1.5 m
1 2 3 4 5 6 7
Pekerjaan Pengeboran Horisontal Transportasi alat ke lokasi pekerjaan. Sewa peralatan Bor (pipa, slang, jangkar, sling, tenda, dll) Biaya Pengeboran Biaya operasi Pompa Air Tukang ahli bor Tukang pipa Pekerja
1 2 3 4
II
III
IV
Satuan
Volume
Harga Satuan [Rp]
Jumlah [Rp]
ls m3 m3 m3 m3 m1
1.00 12.00 8.40 4.20 8.40 8.00
250,000 19,680 #N/A #N/A #N/A #N/A
250,000 236,160 #N/A #N/A #N/A #N/A
ls hari meter jam oh oh oh
1.00 20.00 18.00 24.00 2.00 2.00 8.00
500,000 50,000 65,000 5,729 25,000 #N/A #N/A
500,000 1,000,000 1,170,000 137,492 50,000 #N/A #N/A
Pengadaan dan Pemasangan Pipa & Acc. Pipa Steel ND. 100 mm Loose flange ND. 100 mm, Steel Pemasangan Thrusblock Flange socket ND. 100 mm
m bh bh bh
10.00 2.00 2.00 2.00
139,000 123,000 65,000 90,000
1,390,000 246,000 130,000 180,000
Pek. Lain-lain. Perbaikan dan perbersihan saluran akibat pekerjaan.
ls
1.00
100,000
100,000
Total I + II + III + IV
#N/A
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
URAIAN PEKERJAAN Pekerjaan Persiapan, Tanah dan Bongkaran Pembersihan lokasi secara manual Mengukur dan memasang bouwplank Galian tanah biasa Galian tanah keras Galian tanah berbatu Galian dasar sungai berbatu Urugan tanah kembali Pemadatan tanah perlapis 25 cm Urugan tanah didatangkan dipadatkan Urugan pasir dipadatkan Buangan tanah disekitar lokasi Pemasangan turap kayu pengaman galian 1.5 m Bongkaran beton masif dan pasangan batu. Bongkaran perkerasan jalan kelas III (40 cm) Bongkaran perkerasan jalan kelas I (15 cm) Bongkaran perkerasan Paving Block tebal 8 cm.
SATUAN
B 17 18 19 20 21 22 23 24 25 26 27
Pekerjaan Pasangan. Pasangan Batu kosong Pasangan Batu Bronjong. Pasangan Batu, Spesi 1 : 4. Pasangan Batu, Spesi 1 : 3. Pasangan Bata, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 10 mm. Plesteran Spesi 1 : 2, tebal 15 mm. Siaran, Spesi 1 : 1, tebal 10 mm. Pasang Keramik 20x20 cm Pasang lantai Mozaik 30x30 cm Pasang Porselin 10x10 cm
1 M3 1 m3 1 m3 1 m3 1 m3 1 m2 1 m2 1 m2 1 m2 1 m2 1 m2
C 28 29 30 31 32 33 34 35 36 37 38 39 40
Pekerjaan Beton Adukan Beton, Campuran 1:2:2,5. (K225) Adukan Beton, Campuran 1:2:3. (K175) Adukan Beton, Campuran 1:2:5. (K125) Pembesian tulangan beton, mutu baja U24. Cetakan Beton (non eksposed). Cetakan Beton (eksposed). Perancah tinggi 3,00 m. Beton Bertulang K225, Pilar Jembatan 50/50. Beton Bertulang K225, Support pipa 30/30. Beton Bertulang K225, Kepala Pilar Jembatan 50/130. Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm) Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3. Plat lantai beton bertulang, K225 baja U24 (103 kg/m3)
1 m3 1 m3 1 m3 1 Kg. 1 M2 1 M2 1 M2 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3
1M2 1M1 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1 M1 1 M3 1 M2 1 M2 1 M2
41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
Plat lantai beton bertulang, K225 baja U24 (129 kg/m3) Plat lantai beton bertulang, K225 baja U24 (168 kg/m3) Plat lantai beton bertulang, K225 baja U24 (183 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3) Kolom beton bertulang, K225 baja U24 (152 kg/m3) Balok beton bertulang, K225 baja U24 (165 kg/m3) Sloof beton bertulang, K225 baja U24 (174 kg/m3) Sloof beton bertulang, K175 baja U24 (148 kg/m3) Kolom/balok ringbalk, K175 baja U24 (148 kg/m3) Plat Atap beton bertulang, K225 baja U24 (90 kg/m3) Plat Atap beton bertulang, K225 baja U24 (189 kg/m3) Lisplank beton bertulang, K175 baja U24 (90 kg/m3)
1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3
D
Pekerjaan Konstruksi Baja
56 57 58 59 60 61 62 63 64 65 66
Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart) Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah). Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian). Pekerjaan pemotongan plat baja tebal 5 mm Pengecatan besi/pipa anti karat (exterior painting). Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m Pekerjaan konstruksi rangka baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur. Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5
1 M3 1 M' 1 M' 1 M' 1 M2 1 kg 1 kg 1 unit 1 unit 1 unit 1 unit
E 67 68 69 70 71 72 73 74 75
Pekerjaan Kayu Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm. Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15. Rangka kusen pintu dan jendela, Kayu Kamper medan Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3 Penutup bubungan Lisplank, kayu borne 2x3/20 Daun Pintu double triplek, rangka borneo 3/6 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7 Daun jendala kaca, kayu 3/10 dan profil 2/3.
1 m' 1 M3 1 M3 1 M2 1 M2 1 m1 1 bh 1 M3 1 M2
F 76 77 78 79 80
Pekerjaan Pemasangan Pipa Baja Pengangkutan pipa baja ke lokasi galian. Penyambungan Pipa Las Flange Pipa Dia. 250 mm Penyambungan Pipa Las Flange Pipa Dia. 300 mm Pemasangan Pipa GI ND. 250 mm, diatas tumpuan Pemasangan Pipa GI ND. 300 mm, diatas tumpuan
1 kg 1 M' 1 M' 1 M' 1 M'
81 82 83
Pemasangan GI Dia. 250 mm, Galian tanah biasa. Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III.
1 M' 1 M' 1 M'
84 85
Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block.
1 M' 1 M'
86 87 88 89 90 91 92 93
Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
G 94 95 96 97 98 99 100 101
Pekerjaan Pemasangan Pipa PVC Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
102 103 104 105 106 107 108 109
Penyambungan pipa PVC Dia. 50 mm didalam galian Penyambungan pipa PVC Dia. 75 mm didalam galian Penyambungan pipa PVC Dia. 100 mm didalam galian Penyambungan pipa PVC Dia. 150 mm didalam galian Penyambungan pipa PVC Dia. 200 mm didalam galian Penyambungan pipa PVC Dia. 250 mm didalam galian Penyambungan pipa PVC Dia. 300 mm didalam galian Penyambungan pipa PVC Dia. 400 mm didalam galian
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
110 111 112 113 114 115 116 117 118
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
119 120 121 122 123 124 125 126 127
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
128 129 130 131 132 133 134 135
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
136 137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 H 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171
Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. Pekerjaan Perkerasan Jalan. Pemadatan tanah dasar menggunakan Stamper Pemadatan standart Bina Marga menggunakan alat berat Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2. Lapis Pondasi bawah Onderlaght, tebal 15 cm. Lapis Pondasi bawah onderlaght, tebal 30 cm. Lapis Pondasi Atas Steinslaght , tebal 7 cm. Lapis Perkerasan Macadam, tebal 5 cm. Lapis PENETRASI , tebal 3 cm. Perbaikan Perkerasan jalan kelas III Perbaikan Perkerasan jalan kelas I Pemasangan kembali Paving Block (30% rusak diganti baru) Perbaikan paving blok, pemasangan pipa dia. 400 mm Perbaikan paving blok, pemasangan pipa dia. 300 mm Perbaikan paving blok, pemasangan pipa dia. 250 mm Perbaikan paving blok, pemasangan pipa dia. 200 mm Jalan inspeksi, beton rabat tebal 10 cm
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1M2 1M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2
H 172 173 174
Pekerjaan Perlintasan Pipa Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. TIPE D Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m.
1 unit 1 unit 1 unit
175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195 196
Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus). Jembatan Pipa, ND. 250 mm, Bentang = 50,00 m Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m. Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 15,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 12,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m. Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m.
1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit
197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219
Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 50,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 18,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 25,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m
1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit
HARGA 780.00 9,450.00 19,680.00 26,870.00 39,370.00 71,250.00 8,620.00 12,300.00 83,410.00 101,830.00 7,875.00 50,670.00 88,700.00 22,640.00 24,840.00 4,310.00
145,690.00 296,210.00 480,990.00 514,950.00 560,760.00 25,420.00 27,200.00 27,380.00 104,290.00 132,060.00 95,070.00
780,210.00 648,570.00 594,330.00 15,470.17 63,403.59 146,161.86 195,772.69 3,238,083.33 2,938,126.54 3,532,016.56 721,137.18 657,733.59 2,410,177.97
2,812,402.39 3,415,739.02 3,647,791.57 4,323,509.54 4,335,366.86 4,443,658.05 5,588,450.63 5,128,956.59 5,478,275.74 4,232,862.63 4,967,069.96 3,673,636.78 4,123,847.88 5,655,394.71 5,883,438.00
200,435.00 102,847.50 143,997.00 46,378.75 46,234.56 9,375.87 8,926.64 206,500.00 261,800.00 87,780.00 788,720.00
96,313.47 3,979,820.00 6,167,540.00 178,770.00 62,230.00 58,240.00 537,350.00 111,340.00 140,100.00
170.00 49,468.75 56,535.71 60,200.00 68,900.00 106,600.00 124,100.00 133,300.00
131,500.00 119,000.00 165,800.00 120,400.00 137,300.00 136,700.00 144,000.00 133,000.00 2,590.00 2,820.00
330.00 363.00 396.00 462.00 561.00 693.00 858.00 1,023.00 750.00 787.50 937.50 1,312.50 1,500.00 1,800.00 2,062.50 2,250.00 26,900.00 29,000.00 34,300.00 40,300.00 41,000.00 44,800.00 54,500.00 57,000.00 62,100.00 35,700.00 37,900.00 44,800.00 52,000.00 53,000.00 59,400.00 72,700.00 76,200.00 85,700.00
34,000.00 36,300.00 42,300.00 48,300.00 51,000.00 58,200.00 69,200.00
36,800.00 40,600.00 53,800.00 63,600.00 69,300.00 78,300.00 63,000.00 66,900.00 83,500.00 64,900.00 72,300.00 83,200.00 1,640.00 1,650.00 2,020.00 2,100.00 2,410.00 2,660.00 2,790.00 3,210.00 5,643.75 1,050.30 5,193.02 20,970.00 36,369.00 23,985.49 33,558.13 24,101.38 54,528.13 69,056.87 30,675.11 30,675.11 27,607.60 24,540.09 21,472.58 101,374.24
36,437,559.50 46,112,328.53 52,046,807.69
54,949,918.57 56,442,793.52 63,630,420.21 107,669,431.04 81,141,038.27 114,929,053.55 196,169,305.96 78,961,987.60 30,699,739.50 33,008,762.53 98,179,222.73 24,069,480.73 16,048,227.10 14,584,227.10 18,552,747.88 18,216,912.19 18,088,855.11 17,489,339.86 10,395,657.00 10,009,457.00 10,117,657.00 21,084,755.38 64,996,555 24,981,864 12,351,514 31,514,290 6,785,534 11,176,514 9,108,439 8,058,439 6,358,439 4,683,439 13,521,722 4,633,439 3,932,739 3,393,239 3,076,239 3,468,239 9,792,392 9,105,236 8,289,687 5,739,216 8,664,736 4,703,346 2,527,334
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO
URAIAN PEKERJAAN
SATUAN
HARGA
A 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
Pekerjaan Persiapan, Tanah dan Bongkaran Pembersihan lokasi secara manual Mengukur dan memasang bouwplank Galian tanah biasa Galian tanah keras Galian tanah berbatu Galian dasar sungai berbatu Urugan tanah kembali Pemadatan tanah perlapis 25 cm Urugan tanah didatangkan dipadatkan Urugan pasir dipadatkan Buangan tanah disekitar lokasi Pemasangan turap kayu pengaman galian 1.5 m Bongkaran beton masif dan pasangan batu. Bongkaran perkerasan jalan kelas III (40 cm) Bongkaran perkerasan jalan kelas I (15 cm) Bongkaran perkerasan Paving Block tebal 8 cm.
1M2 1M1 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1M3 1 M1 1 M3 1 M2 1 M2 1 M2
780.00 9,450.00 19,680.00 26,870.00 39,370.00 71,250.00 8,620.00 12,300.00 83,410.00 101,830.00 7,875.00 50,670.00 88,700.00 22,640.00 24,840.00 4,310.00
B 17 18 19 20 21 22 23 24 25 26 27
Pekerjaan Pasangan. Pasangan Batu kosong Pasangan Batu Bronjong. Pasangan Batu, Spesi 1 : 4. Pasangan Batu, Spesi 1 : 3. Pasangan Bata, Spesi 1 : 4. Plesteran Spesi 1 : 2, tebal 10 mm. Plesteran Spesi 1 : 2, tebal 15 mm. Siaran, Spesi 1 : 1, tebal 10 mm. Pasang Keramik 20x20 cm Pasang lantai Mozaik 30x30 cm Pasang Porselin 10x10 cm
1 M3 1 m3 1 m3 1 m3 1 m3 1 m2 1 m2 1 m2 1 m2 1 m2 1 m2
145,690.00 296,210.00 480,990.00 514,950.00 560,760.00 25,420.00 27,200.00 27,380.00 104,290.00 132,060.00 95,070.00
C 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55
Pekerjaan Beton Adukan Beton, Campuran 1:2:2,5. (K225) Adukan Beton, Campuran 1:2:3. (K175) Adukan Beton, Campuran 1:2:5. (K125) Pembesian tulangan beton, mutu baja U24. Cetakan Beton (non eksposed). Cetakan Beton (eksposed). Perancah tinggi 3,00 m. Beton Bertulang K225, Pilar Jembatan 50/50. Beton Bertulang K225, Support pipa 30/30. Beton Bertulang K225, Kepala Pilar Jembatan 50/130. Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm) Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3. Plat lantai beton bertulang, K225 baja U24 (103 kg/m3) Plat lantai beton bertulang, K225 baja U24 (129 kg/m3) Plat lantai beton bertulang, K225 baja U24 (168 kg/m3) Plat lantai beton bertulang, K225 baja U24 (183 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3) Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3) Kolom beton bertulang, K225 baja U24 (152 kg/m3) Balok beton bertulang, K225 baja U24 (165 kg/m3) Sloof beton bertulang, K225 baja U24 (174 kg/m3) Sloof beton bertulang, K175 baja U24 (148 kg/m3) Kolom/balok ringbalk, K175 baja U24 (148 kg/m3) Plat Atap beton bertulang, K225 baja U24 (90 kg/m3) Plat Atap beton bertulang, K225 baja U24 (189 kg/m3) Lisplank beton bertulang, K175 baja U24 (90 kg/m3)
1 m3 1 m3 1 m3 1 Kg. 1 M2 1 M2 1 M2 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3 1 M3
780,210.00 648,570.00 594,330.00 15,470.17 63,403.59 146,161.86 195,772.69 3,238,083.33 2,938,126.54 3,532,016.56 721,137.18 657,733.59 2,410,177.97 2,812,402.39 3,415,739.02 3,647,791.57 4,323,509.54 4,335,366.86 4,443,658.05 5,588,450.63 5,128,956.59 5,478,275.74 4,232,862.63 4,967,069.96 3,673,636.78 4,123,847.88 5,655,394.71 5,883,438.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO D
URAIAN PEKERJAAN
SATUAN
Pekerjaan Konstruksi Baja
56 57 58 59 60 61 62 63 64 65 66
Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart) Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah). Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian). Pekerjaan pemotongan plat baja tebal 5 mm Pengecatan besi/pipa anti karat (exterior painting). Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m Pekerjaan konstruksi rangka baja Bar Matahari Pipa Dia. 300 mm (sesuai gambar). Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur. Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5
1 M3 1 M' 1 M' 1 M' 1 M2 1 kg 1 kg 1 unit 1 unit 1 unit 1 unit
HARGA
200,435.00 102,847.50 143,997.00 46,378.75 46,234.56 9,375.87 8,926.64 206,500.00 261,800.00 87,780.00 788,720.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO
URAIAN PEKERJAAN
SATUAN
HARGA
E 67 68 69 70 71 72 73 74 75
Pekerjaan Kayu Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm. Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15. Rangka kusen pintu dan jendela, Kayu Kamper medan Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3 Penutup bubungan Lisplank, kayu borne 2x3/20 Daun Pintu double triplek, rangka borneo 3/6 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7 Daun jendala kaca, kayu 3/10 dan profil 2/3.
1 m' 1 M3 1 M3 1 M2 1 M2 1 m1 1 bh 1 M3 1 M2
96,313.47 3,979,820.00 6,167,540.00 178,770.00 62,230.00 58,240.00 537,350.00 111,340.00 140,100.00
F 76 77 78 79 80
Pekerjaan Pemasangan Pipa Baja Pengangkutan pipa baja ke lokasi galian. Penyambungan Pipa Las Flange Pipa Dia. 250 mm Penyambungan Pipa Las Flange Pipa Dia. 300 mm Pemasangan Pipa GI ND. 250 mm, diatas tumpuan Pemasangan Pipa GI ND. 300 mm, diatas tumpuan
1 kg 1 M' 1 M' 1 M' 1 M'
170.00 49,468.75 56,535.71 60,200.00 68,900.00
81 82 83 84 85
Pemasangan GI Dia. 250 mm, Galian tanah biasa. Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block.
1 M' 1 M' 1 M' 1 M' 1 M'
106,600.00 124,100.00 133,300.00 131,500.00 119,000.00
86 87 88 89 90 91 92 93
Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
165,800.00 120,400.00 137,300.00 136,700.00 144,000.00 133,000.00 2,590.00 2,820.00
G 94 95 96 97 98 99 100 101
Pekerjaan Pemasangan Pipa PVC Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
330.00 363.00 396.00 462.00 561.00 693.00 858.00 1,023.00
102 103 104 105 106 107 108 109
Penyambungan pipa PVC Dia. 50 mm didalam galian Penyambungan pipa PVC Dia. 75 mm didalam galian Penyambungan pipa PVC Dia. 100 mm didalam galian Penyambungan pipa PVC Dia. 150 mm didalam galian Penyambungan pipa PVC Dia. 200 mm didalam galian Penyambungan pipa PVC Dia. 250 mm didalam galian Penyambungan pipa PVC Dia. 300 mm didalam galian Penyambungan pipa PVC Dia. 400 mm didalam galian
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
750.00 787.50 937.50 1,312.50 1,500.00 1,800.00 2,062.50 2,250.00
110 111 112 113 114 115 116 117 118
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
26,900.00 29,000.00 34,300.00 40,300.00 41,000.00 44,800.00 54,500.00 57,000.00 62,100.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO 119 120 121 122 123 124 125 126 127
URAIAN PEKERJAAN Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras
SATUAN 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
HARGA 35,700.00 37,900.00 44,800.00 52,000.00 53,000.00 59,400.00 72,700.00 76,200.00 85,700.00
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO
URAIAN PEKERJAAN
SATUAN
HARGA
128 129 130 131 132 133 134 135
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
34,000.00 36,300.00 42,300.00 48,300.00 51,000.00 58,200.00 69,200.00
136 137 138 139 140 141
Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
36,800.00 40,600.00 53,800.00 63,600.00 69,300.00 78,300.00
142 143 144
Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III.
1 M' 1 M' 1 M'
63,000.00 66,900.00 83,500.00
145 146 147 148 149 150 151 152
Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm.
1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M' 1 M'
64,900.00 72,300.00 83,200.00 1,640.00 1,650.00 2,020.00 2,100.00 2,410.00
H 153 154 155 156 157 158 159 160 161 162 163 164 165 166 167 168 169 170 171
Pekerjaan Perkerasan Jalan. #N/A #N/A #N/A 1M2 1M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2 1 M2
#N/A #N/A #N/A 5,643.75 1,050.30 5,193.02 20,970.00 36,369.00 23,985.49 33,558.13 24,101.38 54,528.13 69,056.87 30,675.11 30,675.11 27,607.60 24,540.09 21,472.58 101,374.24
#N/A #N/A #N/A Pemadatan tanah dasar menggunakan Stamper Pemadatan standart Bina Marga menggunakan alat berat Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2. Lapis Pondasi bawah Onderlaght, tebal 15 cm. Lapis Pondasi bawah onderlaght, tebal 30 cm. Lapis Pondasi Atas Steinslaght , tebal 7 cm. Lapis Perkerasan Macadam, tebal 5 cm. Lapis PENETRASI , tebal 3 cm. Perbaikan Perkerasan jalan kelas III Perbaikan Perkerasan jalan kelas I Pemasangan kembali Paving Block (30% rusak diganti baru) Perbaikan paving blok, pemasangan pipa dia. 400 mm Perbaikan paving blok, pemasangan pipa dia. 300 mm Perbaikan paving blok, pemasangan pipa dia. 250 mm Perbaikan paving blok, pemasangan pipa dia. 200 mm Jalan inspeksi, beton rabat tebal 10 cm
REKAP DAFTAR HARGA SATUAN PEKERJAAN PENDUKUNG NO H 172 173 174 175 176 177 178 179 180 181 182 183 184 185 186 187 188 189 190 191 192 193 194 195
URAIAN PEKERJAAN Pekerjaan Perlintasan Pipa Jembatan Pipa, ND. 300 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 14,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 16,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 18,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 20,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 24,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m. Jembatan Pipa, ND. 300 mm, Bentang = 26,00 m (Pondasi khusus). Jembatan Pipa, ND. 300 mm, Bentang = 28,00 m. Jembatan Pipa, ND. 250 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 200 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 32,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 150 mm, Bentang = 3,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 10,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 8,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 7,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 6,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 5,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 4,00 m. Jembatan Pipa, ND. 100 mm, Bentang = 3,00 m. Jembatan Pipa, ND. 75 mm, Bentang = 15,00 m.
196 197 198 199 200 201 202 203 204 205 206 207 208 209 210 211 212 213 214 215 216 217 218 219 220 221
SATUAN
HARGA
1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit
34,310,099 40,175,189 46,324,564 49,309,275 53,411,379 57,674,320 85,731,227 73,889,429 89,062,116 71,955,876 25,657,479 31,170,719 71,649,790 21,960,837 17,276,014 15,224,014 18,596,146 17,790,313 17,553,306 16,844,841 10,498,676 10,389,526 10,002,776 19,950,940
Syphon Pipa, ND. 300 mm, Bentang 1,50 m (Type A). Syphon Pipa, ND. 250 mm, Bentang 1,50 m (Type A). Syphon Pipa, ND. 200 mm, Bentang 1,50 m (Type A). Syphon Pipa, ND. 150 mm, Bentang 1,50 m (Type A). Syphon Pipa, ND. 100 mm, Bentang 1,50 m (Type A). Syphon Pipa, ND. 100 mm, Bentang 2,50 m (Type A). Crossing Jalan (Bor Horisontal) Pipa, ND. 400 mm, L = 20,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 15,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 300 mm, L = 6,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 15,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 12,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 250 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 200 mm, L = 10,00 m
1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit
1,963,728 1,867,028 1,721,028 1,359,028 1,063,928 1,878,036 21,944,585 11,642,170 5,411,820 9,432,170 7,669,020 6,669,020 7,928,020
Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 150 mm, L = 7,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 10,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 100 mm, L = 7,00 m Crossing Jalan (Bor Horisontal) Pipa, ND. 50 mm, L = 10,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 6,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 5,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 300 mm, L = 4,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 250 mm, L = 4,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 15,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 150 mm, L = 6,00 m Crossing Jalan (Type Open Cut) Pipa, ND. 50 mm, L = 7,00 m
1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit 1 unit
4,637,020 6,297,020 3,621,333 3,512,333 2,868,483 3,602,333 6,896,417 6,198,701 5,444,716 5,013,828 7,690,963 4,019,233 1,710,507
ANALISA HARGA SATUAN PEKERJAAN Pekerjaan Lokasi No A 1
2
3
4
5
6
7
8
9
10
Uraian Pekerjaan
Harga Satuan
Jumlah
PEKERJAAN TANAH DAN PERSIAPAN 1M2 Pembersihan lokasi secara manual 0.030 Oh Pekerja 0.001 Oh Mandor Jumlah Dibulatkan Mengukur dan memasang bouwplank 1M1 0.006 Oh Kayu Bekisting 0.006 Oh Pekerja 0.015 Oh Mandor Jumlah Dibulatkan 1M3 Galian tanah biasa 0.750 oh Pekerja 0.025 oh Mandor Jumlah Dibulatkan Galian tanah keras 1M3 1.000 oh Pekerja 0.050 oh Mandor Jumlah Dibulatkan 1M3 Galian tanah berbatu 1.500 oh Pekerja 0.050 oh Mandor Jumlah Dibulatkan 1M3 Galian dasar sungai berbatu 1.750 oh Pekerja 0.100 oh Mandor 0.050 oh Alat bantu (pompa, kisdam turap, dll) Jumlah Dibulatkan 1M3 0.330 0.010
Urugan tanah kembali oh Pekerja oh Mandor Jumlah Dibulatkan
1M3 0.160 0.160 0.160 0.008
Pemadatan tanah perlapis 25 cm jam Plate Vibrator Tamper oh Operator semi terampil oh Pekerja oh Mandor Jumlah Dibulatkan
1M3 1.2 0.300 0.010 1.000 1.000
1M3
Urugan tanah didatangkan dipadatkan m3 Tanah merah oh Pekerja oh Mandor M3 Pemadatan perlapis 25 cm M3 Biaya Anggkutan Jumlah Dibulatkan
Urugan pasir dipadatkan
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp.
750.00 37.50 787.50 780.00
@ Rp. @ Rp.
1,457,800.00 = Rp. 25,000.00 = Rp. 37,500.00 = Rp.
8,746.80 150.00 562.50 9,459.30 9,450.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp.
18,750.00 937.50 19,687.50 19,680.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp.
25,000.00 1,875.00 26,875.00 26,870.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp.
37,500.00 1,875.00 39,375.00 39,370.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp. = Rp.
43,750.00 3,750.00 23,750.00 71,250.00 71,250.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp.
8,250.00 375.00 8,625.00 8,620.00
@ Rp. @ Rp. @ Rp. @ Rp.
4,200.00 45,800.00 25,000.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp.
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
33,700.00 25,000.00 37,500.00 12,300.00 22,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
672.00 7,328.00 4,000.00 300.00 12,300.00 12,300.00
40,440.00 7,500.00 375.00 12,300.00 22,800.00 83,415.00 83,410.00
No
Uraian Pekerjaan 1.2 0.300 0.010
11
1M3 0.300 0.010
m3 Pasir urug oh Pekerja oh Mandor Jumlah Dibulatkan Buangan tanah disekitar lokasi oh Pekerja oh Mandor Jumlah Dibulatkan
Harga Satuan @ Rp. @ Rp. @ Rp.
Jumlah
78,300.00 = Rp. 25,000.00 = Rp. 37,500.00 = Rp. = Rp.
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp. = Rp.
93,960.00 7,500.00 375.00 101,835.00 101,830.00
7,500.00 375.00 7,875.00 7,870.00
No 12
Uraian Pekerjaan 1 M1 2.000 0.500 0.500 0.250 0.020
13
14
15
16
B 17
18
19
20
Pemasangan turap kayu pengaman galian 1.5 m m2 Anyaman bambu belah kg Paku biasa oh Pekerja oh Tukang kayu semi terampil oh Mandor Jumlah Dibulatkan
1 M3 Bongkaran beton masif dan pasangan batu. 2.000 oh Pekerja 0.200 oh Mandor 2.000 jam Jack Hammer Jumlah Dibulatkan 1 M2 Bongkaran perkerasan jalan kelas III (40 cm) 0.750 oh Pekerja 0.075 oh Mandor Alat bantu Jumlah Dibulatkan 1 M2 Bongkaran perkerasan jalan kelas I (15 cm) 0.500 oh Pekerja 0.100 oh Operator terampil 0.100 oh Pembantu operator 0.075 jam Jack Hammer 0.075 jam Air Compressor 150 M3 Jumlah Dibulatkan
Harga Satuan
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
10,800.00 10,800.00 25,000.00 41,700.00 37,500.00
Jumlah
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,600.00 5,400.00 12,500.00 10,425.00 750.00 50,675.00 50,670.00
@ Rp. @ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp. 15,600.00 = Rp.
50,000.00 7,500.00 31,200.00 88,700.00 88,700.00
@ Rp. @ Rp.
25,000.00 = Rp. 37,500.00 = Rp. = Rp.
18,750.00 2,812.50 1,078.13 22,640.63 22,640.00
@ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 50,000.00 50,000.00 15,600.00 15,600.00
= Rp. = Rp. = Rp. = Rp. = Rp.
12,500.00 5,000.00 5,000.00 1,170.00 1,170.00 24,840.00 24,840.00
25,000.00 = Rp. 37,500.00 = Rp.
3,750.00 562.50 4,312.50 4,310.00
@ Rp. @ Rp. @ Rp.
95,800.00 = Rp. 25,000.00 = Rp. 37,500.00 = Rp.
105,380.00 37,500.00 2,812.50 145,692.50 145,690.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 37,500.00 37,500.00 95,800.00 20,000.00
= Rp. = Rp. = Rp. = Rp. = Rp.
50,000.00 37,500.00 3,750.00 114,960.00 90,000.00 296,210.00 296,210.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
95,800.00 116,600.00 48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
114,960.00 60,865.20 157,458.00 90,000.00 45,960.00 5,004.00 6,750.00 480,997.20 480,990.00
@ Rp. @ Rp.
95,800.00 = Rp. 116,600.00 = Rp.
114,960.00 56,667.60
1 M2 Bongkaran perkerasan Paving Block tebal 8 cm. 0.150 oh Pekerja @ Rp. 0.015 oh Mandor @ Rp. Jumlah Dibulatkan
PEKERJAAN PASANGAN DAN PLESTERAN 1 M3 1.100 1.500 0.075
Pasangan Batu kosong m3 Batu belah 15/20 oh Pekerja oh Mandor Jumlah Dibulatkan
1 m3 2.000 1.000 0.100 1.200 4.500
Pasangan Batu Bronjong. oh Pekerja oh Pekerja terampil oh Mandor m3 Batu bronjong Kg Kawat bronjong 3 mm Jumlah Dibulatkan
1 m3 1.200 0.522 3.260 3.600 1.200 0.120 0.180
Pasangan Batu, Spesi 1 : 4. m3 Batu belah 15/20 m3 Pasir pasang zak Portland Cement oh Pekerja oh Tukang Batu oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m3 1.200 0.486
Pasangan Batu, Spesi 1 : 3. m3 Batu belah 15/20 m3 Pasir pasang
No
Uraian Pekerjaan 4.050 3.600 1.200 0.120 0.180
zak oh oh oh oh
Portland Cement Pekerja Tukang batu Kepala Tukang Batu Mandor Jumlah Dibulatkan
Harga Satuan @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp.
195,615.00 90,000.00 45,960.00 5,004.00 6,750.00 514,956.60 514,950.00
No
21
22
23
24
25
26
27
Uraian Pekerjaan
1 m3 450.000 0.378 3.148 4.500 1.500 0.150 0.225
Pasangan Bata, Spesi 1 : 4. m3 Bata merah lokal m3 Pasir pasang zak Portland Cement oh Pekerja oh Tukang batu oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 0.012 0.143 0.400 0.150 0.015 0.020
Plesteran Spesi 1 : 2, tebal 10 mm. m3 Pasir pasang zak Portland Cement oh Pekerja oh Tukang batu oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 0.019 0.163 0.400 0.150 0.015 0.020
Plesteran Spesi 1 : 2, tebal 15 mm. m3 Pasir pasang zak Portland Cement oh Pekerja oh Tukang Batu oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 0.060 0.082 0.150 0.300 0.015 0.015
Siaran, Spesi 1 : 1, tebal 10 mm. m3 Pasir pasang zak Portland Cement oh Pekerja oh Tukang batu semi terampil oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 1.000 0.035 0.248 0.500 0.250 0.075
Pasang Keramik 20x20 cm m2 Keramik 20x20 kelas I m3 Pasir pasang zak Portland Cement oh Pekerja oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 11.000 0.035 0.248 0.500 0.300 0.080
Pasang lantai Mozaik 30x30 cm bh Mozaik 30x30 cm m3 Pasir pasang zak Portland Cement oh Pekerja oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
1 m2 1.000 0.035 0.248 0.250 0.500 0.075
Pasang Porselin 10x10 cm dos Porselin 10x10 cm m3 Pasir pasang zak Portland Cement oh Pekerja oh Kepala Tukang Batu oh Mandor Jumlah Dibulatkan
Harga Satuan
Jumlah
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
400.00 116,600.00 48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
180,000.00 44,074.80 152,048.40 112,500.00 57,450.00 6,255.00 8,437.50 560,765.70 560,760.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
116,600.00 48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,399.20 6,906.90 10,000.00 5,745.00 625.50 750.00 25,426.60 25,420.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
116,600.00 48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,215.40 7,872.90 10,000.00 5,745.00 625.50 750.00 27,208.80 27,200.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
116,600.00 48,300.00 25,000.00 38,300.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
6,996.00 3,960.60 3,750.00 11,490.00 625.50 562.50 27,384.60 27,380.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
62,500.00 116,600.00 48,300.00 25,000.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
62,500.00 4,081.00 11,978.40 12,500.00 10,425.00 2,812.50 104,296.90 104,290.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
8,000.00 116,600.00 48,300.00 25,000.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
88,000.00 4,081.00 11,978.40 12,500.00 12,510.00 3,000.00 132,069.40 132,060.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
49,100.00 116,600.00 48,300.00 25,000.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
49,100.00 4,081.00 11,978.40 6,250.00 20,850.00 2,812.50 95,071.90 95,070.00
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No C 28
29
30
31
Uraian Pekerjaan PEKERJAAN BETON 1 m3 Adukan Beton, Campuran 1:2:2,5. (K225) 6.000 oh Pekerja 0.600 oh Tukang Batu 0.050 oh Kepala Tukang Batu 0.300 oh Mandor 0.492 m3 Pasir beton 0.820 m3 Batu pecah 1 - 2 8.200 zak Portland Cement 0.200 ah Concrete Mixer 0,25 m3 0.200 ah Concrete Vibrator 1.000 ls Alat bantu Jumlah Dibulatkan 1 m3 6.000 0.600 0.050 0.300 0.522 0.836 5.400 0.200 0.200 1.000
Adukan Beton, Campuran 1:2:3. (K175) oh Pekerja oh Tukang Batu oh Kepala Tukang Batu oh Mandor m3 Pasir beton m3 Batu pecah 1 - 2 zak Portland Cement ah Concrete Mixer 0,25 m3 ah Concrete Vibrator ls Alat bantu Jumlah Dibulatkan
1 m3 6.000 0.600 0.050 0.300 0.588 0.842 4.100 0.200 0.200 1.000
Adukan Beton, Campuran 1:2:5. (K125) oh Pekerja oh Tukang Batu oh Kepala Tukang Batu oh Mandor m3 Pasir beton m3 Batu pecah 1 - 2 zak Portland Cement ah Concrete Mixer 0,25 m3 ah Concrete Vibrator ls Alat bantu Jumlah Dibulatkan
1 Kg. 100 Kg. 9.000 9.000 3.000 1.000 110.0 2.000 1.000
Harga Satuan
Jumlah
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 38,300.00 41,700.00 37,500.00 133,300.00 136,600.00 48,300.00 17,900.00 7,300.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 22,980.00 2,085.00 11,250.00 65,583.60 112,012.00 396,060.00 3,580.00 1,460.00 15,199.41 780,210.01 780,210.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 38,300.00 41,700.00 37,500.00 133,300.00 136,600.00 48,300.00 17,900.00 7,300.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 22,980.00 2,085.00 11,250.00 69,582.60 114,197.60 260,820.00 3,580.00 1,460.00 12,618.30 648,573.50 648,570.00
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 38,300.00 41,700.00 37,500.00 133,300.00 136,600.00 48,300.00 17,900.00 7,300.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 22,980.00 2,085.00 11,250.00 78,380.40 115,017.20 198,030.00 3,580.00 1,460.00 11,554.85 594,337.45 594,330.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
225,000.00 412,200.00 150,000.00 37,500.00 682,000.00 25,000.00 15,317.00 1,547,017.00 15,470.17
Pembesian tulangan beton, mutu baja U24. Pekerjaan pemotongan, pembengkokan dan pemasangan tulangan beton. oh Pekerja @ Rp. 25,000.00 oh Tukang Besi Beton @ Rp. 45,800.00 oh Kepala tukang besi beton @ Rp. 50,000.00 oh Mandor @ Rp. 37,500.00 Kg Besi tulangan polos @ Rp. 6,200.00 Kg Kawat beton @ Rp. 12,500.00 ls Alat bantu Jumlah Harga Satuan per 1 kg
No 32
33
34
35
36
37
38
39
Uraian Pekerjaan 1 M2 100 M2 6.000 5.000 0.500 0.100 3.960 5.000 1.000
Cetakan Beton (non eksposed). Cetakan Beton (non eksposed). oh Pekerja oh Tukang Kayu oh Kepala tukang kayu oh Mandor m3 Kayu Bekisting Kg Paku biasa ls Alat bantu Jumlah Harga Satuan per 1 m2
1 M2 100 M2 6.000 5.000 0.500 0.100 36.960 3.740 5.000 1.000
Cetakan Beton (eksposed). Cetakan Beton ( eksposed). oh Pekerja oh Tukang Kayu oh Kepala tukang kayu oh Mandor m3 Kayu Papan Multiplek 16 mm m3 Kayu Bekisting Kg Paku biasa ls Alat bantu Jumlah Harga Satuan per 1 m2
1 M2 100 M2 6.000 2.000 0.100 0.100 400 6.300 5.000 1.000
Perancah tinggi 3,00 m. Perancah tinggi 3,00 m. oh Pekerja oh Tukang kayu semi terampil oh Kepala Tukang kayu oh Mandor btg Kayu dolken dia. 8 cm 4 m m3 Kayu bekisting Kg Paku biasa ls Alat bantu Jumlah Harga Satuan per 1 m2
Harga Satuan
Jumlah
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 42,500.00 45,800.00 37,500.00 1,457,800.00 10,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 212,500.00 22,900.00 3,750.00 5,772,888.00 54,000.00 124,320.76 6,340,358.76 63,403.59
@ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp. @ Rp.
25,000.00 42,500.00 45,800.00 37,500.00 228,200.00 1,457,800.00 10,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 212,500.00 22,900.00 3,750.00 8,434,272.00 5,452,172.00 54,000.00 286,591.88 14,616,185.88 146,161.86
25,000.00 41,700.00 45,800.00 37,500.00 25,000.00 1,457,800.00 10,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
150,000.00 83,400.00 4,580.00 3,750.00 10,000,000.00 9,184,140.00 54,000.00 97,399.35 19,577,269.35 195,772.69
1 M3 1.00 121.0 2.00 6.00
Beton Bertulang K225, Pilar Jembatan 50/50. m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 1,871,890.57 292,323.72 293,659.04 3,238,083.33
1 M3 1.00 113.0 2.00 6.00
Beton Bertulang K225, Support pipa 30/30. m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (10% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 1,748,129.21 292,323.72 117,463.62 2,938,126.54
1 M3 1.00 140.0 2.00 6.00
Beton Bertulang K225, Kepala Pilar Jembatan 50/130. m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 2,165,823.80 292,323.72 293,659.04 3,532,016.56
1 M3 1.00 2.00
Beton Tidak Bertulang K125 (Lantai Kerja tebal 5 cm) m3 Adukan Beton K125, Analisa C-30. M2 Cetakan beton non eksposed Analisa C4. Jumlah
594,330.00 = Rp. 63,403.59 = Rp. = Rp.
594,330.00 126,807.18 721,137.18
1 M3 1.00 1.00
Beton Thrushblock tidak bertulang K125 rata2 8 bh/ m3. m3 Adukan Beton K125, Analisa C-30. M2 Cetakan beton non eksposed Analisa C4. Jumlah
594,330.00 = Rp. 63,403.59 = Rp. = Rp.
594,330.00 63,403.59 657,733.59
No 40
41
42
43
44
45
46
47
48
49
Uraian Pekerjaan
Harga Satuan
Jumlah
1 M3 1.00 103.0 0.25
Plat lantai beton bertulang, K225 baja U24 (103 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. Jumlah
780,210.00 = Rp. 15,470.17 = Rp. 146,161.86 = Rp. = Rp.
780,210.00 1,593,427.51 36,540.46 2,410,177.97
1 M3 1.00 129.0 0.25
Plat lantai beton bertulang, K225 baja U24 (129 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. Jumlah
780,210.00 = Rp. 15,470.17 = Rp. 146,161.86 = Rp. = Rp.
780,210.00 1,995,651.93 36,540.46 2,812,402.39
1 M3 1.00 168.0 0.25
Plat lantai beton bertulang, K225 baja U24 (168 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. Jumlah
780,210.00 = Rp. 15,470.17 = Rp. 146,161.86 = Rp. = Rp.
780,210.00 2,598,988.56 36,540.46 3,415,739.02
1 M3 1.00 183.0 0.25
Plat lantai beton bertulang, K225 baja U24 (183 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. Jumlah
780,210.00 = Rp. 15,470.17 = Rp. 146,161.86 = Rp. = Rp.
780,210.00 2,831,041.11 36,540.46 3,647,791.57
1 M3 1.00 98.0 13.20 2.00
Plat Dinding beton bertulang, K225 baja U24 (98 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 1,516,076.66 1,929,336.54 97,886.35 4,323,509.54
1 M3 1.00 129.0 10.00 2.00
Plat Dinding beton bertulang, K225 baja U24 (129 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 1,995,651.93 1,461,618.59 97,886.35 4,335,366.86
1 M3 1.00 136.0 10.00 2.00
Plat Dinding beton bertulang, K225 baja U24 (136 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 2,103,943.12 1,461,618.59 97,886.35 4,443,658.05
1 M3 1.00 210.0 10.00 2.00
Plat Dinding beton bertulang, K225 baja U24 (210 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 3,248,735.70 1,461,618.59 97,886.35 5,588,450.63
1 M3 1.00 152.0 13.33 1.00
Kolom beton bertulang, K225 baja U24 (152 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (25% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 2,351,465.84 1,948,337.58 48,943.17 5,128,956.59
1 M3 1.00 165.0 12.00 4.00
Balok beton bertulang, K225 baja U24 (165 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (50% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 2,552,578.05 1,753,942.31 391,545.39 5,478,275.74
No 50
Uraian Pekerjaan 1 M3
= Rp. = Rp. = Rp. = Rp.
780,210.00 760,843.05 2,691,809.58 4,232,862.63
Sloof beton bertulang, K175 baja U24 (148 kg/m3) tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata. m3 Adukan Beton K225, Analisa C-29. 648,570.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 Jumlah
= Rp. = Rp. = Rp. = Rp.
648,570.00 2,028,914.80 2,289,585.16 4,967,069.96
Kolom/balok ringbalk, K175 baja U24 (148 kg/m3) tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata. m3 Adukan Beton K175, Analisa C-29. 648,570.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 Jumlah
= Rp. = Rp. = Rp. = Rp.
648,570.00 735,481.62 2,289,585.16 3,673,636.78
1 M3 1.00 90.0 6.66 6.66
Plat Atap beton bertulang, K225 baja U24 (90 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (75% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 1,392,315.30 973,437.98 977,884.60 4,123,847.88
1 M3 1.00 189.0 6.66 6.66
Plat Atap beton bertulang, K225 baja U24 (189 kg/m3) m3 Adukan Beton K225, Analisa C-28. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (75% Analisa C5) Jumlah
780,210.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
780,210.00 2,923,862.13 973,437.98 977,884.60 5,655,394.71
1 M3 1.00 90.0 25.62 1.00
Lisplank beton bertulang, K175 baja U24 (90 kg/m3) m3 Adukan Beton K225, Analisa C-29. Kg Pembesian tulangan beton, Analisa C27. M2 Cetakan beton eksposed Analisa C29. M2 Perancah tinggi 3 m (50% Analisa C5) Jumlah
648,570.00 15,470.17 146,161.86 195,772.69
= Rp. = Rp. = Rp. = Rp. = Rp.
648,570.00 1,392,315.30 3,744,666.82 97,886.35 5,883,438.00
1 M3 0.06 6.4 0.58 0.03 1.00
Pembuatan dan pemasangan Patok PDAM beton 20x20x145 cm (sesuai gbr. Standart) m3 Adukan Beton K175, Analisa C-29. 648,570.00 = Rp. 37,617.06 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 = Rp. 99,525.62 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 = Rp. 36,774.08 m3 Cor dengan adukan Beton K125, Analisa C1. 594,330.00 = Rp. 19,018.56 ls Biaya pengangkutan, pemasangan dan tulisan cekung di cat = Rp. 7,500.00 Jumlah = Rp. 200,435.00
1 M3 1.00 32.00 148.0
52
1 M3 1.00 11.60 148.0
53
54
55
56
Jumlah
Sloof beton bertulang, K225 baja U24 (174 kg/m3) tidak termasuk bekisting, karena dicetak dengan bekisting pasangan bata. m3 Adukan Beton K225, Analisa C-29. 780,210.00 M2 Cetakan beton non eksposed Analisa C4. 63,403.59 Kg Pembesian tulangan beton, Analisa C27. 15,470.17 Jumlah
1.00 12.00 174.0
51
Harga Satuan
No D 57
58
59
60
61
62
63
Uraian Pekerjaan
Harga Satuan
Jumlah
PEKERJAAN KONSTRUKSI BAJA 1 M' Pekerjaan pengelasan rangka baja dengan Las Listrik (dibawah). 1.500 kg Kawat Las Listrik 11,100.00 2.000 jam Welding Mechine 500A 16,700.00 0.500 oh Pekerja 25,000.00 0.250 oh Tukang las 50,000.00 0.250 oh Operator semi terampil 45,800.00 0.250 oh Tukang besi profil 45,800.00 1.000 ls Alat bantu Jumlah
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,650.00 33,400.00 12,500.00 12,500.00 11,450.00 11,450.00 4,897.50 102,847.50
1 M' Pekerjaan pengelasan rangka baja dengan Las Listrik (diketinggian). 1.500 kg Kawat Las Listrik 11,100.00 3.000 jam Welding Mechine 500A 16,700.00 0.750 oh Pekerja 25,000.00 0.300 oh Tukang las 50,000.00 0.500 oh Operator semi terampil 45,800.00 0.300 oh Tukang besi profil 45,800.00 1.000 ls Alat bantu Jumlah
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,650.00 50,100.00 18,750.00 15,000.00 22,900.00 13,740.00 6,857.00 143,997.00
1 M' Pekerjaan pemotongan plat baja tebal 5 mm 3.000 kg Karbit 0.500 oh Pekerja 0.250 oh Tukang las tidak bersertifikat 0.025 oh Mandor 1.000 ls Alat bantu Jumlah
6,100.00 25,000.00 41,700.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
18,300.00 12,500.00 10,425.00 937.50 4,216.25 46,378.75
40,800.00 12,900.00 3,200.00 5,400.00 11,200.00 25,000.00 42,500.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,280.00 2,193.00 480.00 2,700.00 1,120.00 3,750.00 9,562.50 10,305.00 937.50 906.56 46,234.56
6,000.00 46,378.75 102,847.50 25,000.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,376,000.00 751,335.75 416,532.38 50,000.00 45,800.00 375.00 72,800.86 3,712,843.99 9,375.87
6,000.00 = Rp. 46,378.75 = Rp. 102,847.50 = Rp. = Rp. = Rp. = Rp.
660,000.00 55,654.50 246,834.00 19,437.29 981,930.00 8,926.64
6,200.00 = Rp. 6,000.00 = Rp. 29,200.00 = Rp. = Rp. 25,000.00 = Rp. = Rp. = Rp.
111,600.00 9,000.00 58,400.00 5,000.00 22,500.00 206,500.00 206,500.00
1 M2 Pengecatan besi/pipa anti karat (exterior painting). 0.350 kg Cat besi 0.170 ltr Meni besi 0.150 ltr Minyak cat 0.500 lbr Kertas ampelas besi 0.100 lbr Kuas 0.150 oh Pekerja 0.225 oh Tukang cat/pelitur 0.225 oh Kepala tukang cat/pelitur 0.025 oh Mandor 1.000 ls Alat bantu Jumlah 1 kg Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m 396.0 Pembuatan Profil Baja Honney Comb (HC) 340, L = 9 m 396.0 kg Besi profil Ex DN (SII) 16.20 m Pemotongan plat baja 4.050 m Pengelasan as badan HC 2.000 oh Pekerja 1.000 oh Tukang besi profil 0.010 oh Mandor 1.000 ls Alat bantu Jumlah Harga Satuan 1 kg Pembuatan Gelagar HC 1 kg Pekerjaan konstruksi rangka baja 110.00 kg Besi siku 1.20 kg Pemotongan besi 2.40 bh Pengelasan rangka baja 1.00 ls Alat bantu Jumlah 1 kg Pekerjaan konstruksi rangka baja 1 unit Bar Matahari Pipa Dia. 300 mm (sesuai gambar). 18.00 kg Besi tulangan polos 1.50 kg Besi strip 3 mm 2.00 bh Baut mur M12 1.00 bh Karet packing 1.00 ls Biaya pabrikasi Jumlah Dibulatkan
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No 64
65
66
67
E 68
69
70
71
Uraian Pekerjaan
Harga Satuan
Jumlah
1 unit Plat landasan 40x40 cm, tebal 9 mm + angkur baut mur. 11.30 kg Besi plat 4.00 bh Angkur baut M16 1.00 ls Biaya pabrikasi Jumlah Dibulatkan
11,500.00 = Rp. 29,200.00 = Rp. 15,000.00 = Rp. = Rp. = Rp.
129,996.00 116,800.00 15,000.00 261,796.00 261,800.00
1 unit Klem pipa Dia. 300 mm, plat baja 3 x 50 mm + maut mur. 1.25 kg Besi plat 2.00 bh Baut mur M12 1.00 bh Karet packing 1/2 diameter. 1.00 ls Biaya pabrikasi Jumlah Dibulatkan
11,500.00 = Rp. 29,200.00 = Rp. = Rp. 10,000.00 = Rp. = Rp. = Rp.
14,380.81 58,400.00 5,000.00 10,000.00 87,780.81 87,780.00
1 unit Tutup Manhole 105x105 cm, plat baja 5 mm, rangka L.50x50x5 39.11 m Besi siku (Rangka tutup & rangka lubang) 3,000.00 = Rp. 39.25 kg Besi plat 11,500.00 = Rp. 2.00 bh Engsel baja 12,500.00 = Rp. 2.00 bh Handle, besi dia. 16 mm di las pada tutup 2,500.00 = Rp. 1.00 bh Kunci gembok 17,500.00 = Rp. 8.00 bh Angkur dia. 12 mm 2,500.00 = Rp. 1.00 bh Kait gembok dilas pada rangka 2,500.00 = Rp. 1.00 ls Biaya pengelasan/pabrikasi & pasang 150,000.00 = Rp. Jumlah = Rp. Dibulatkan = Rp.
117,342.00 451,375.00 25,000.00 5,000.00 17,500.00 20,000.00 2,500.00 150,000.00 788,717.00 788,720.00
1 m' Pemasangan waterstop, plat baja tebal 3 mm lebar 20 cm. 4.71 kg Besi plat 1.20 m 60% pekerjaan pemotong plat dengan las 1.00 ls Biaya pemasangan dan alat bantu Jumlah Dibulatkan PEKERJAAN KAYU 1 M3 Kayu kuda-kuda, nok, skor dan gording, kayu borneo 8/15. 1.100 kg Kayu borneo 6.000 oh Pekerja 12.000 oh Tukang Kayu 4.000 oh Tukang kayu semi terampil 1.200 oh Kepala tukang kayu 0.300 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan 1 M3 Rangka kusen pintu dan jendela, Kayu Kamper medan 1.100 kg Kayu kamper medan 12.000 oh Pekerja 20.000 oh Tukang Kayu 6.000 oh Tukang kayu semi terampil 2.400 oh Kepala tukang kayu 0.300 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan
11,500.00 = Rp. 27,827.25 = Rp. = Rp. = Rp. = Rp.
54,165.00 33,392.70 8,755.77 96,313.47 96,310.00
2,633,900.00 25,000.00 42,500.00 41,700.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,897,290.00 150,000.00 510,000.00 166,800.00 54,960.00 11,250.00 189,515.00 3,979,815.00 3,979,820.00
3,956,800.00 25,000.00 42,500.00 41,700.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,352,480.00 300,000.00 850,000.00 250,200.00 109,920.00 11,250.00 293,692.50 6,167,542.50 6,167,540.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
97,500.00 34,240.70 2,700.00 10,000.00 25,500.00 4,580.00 375.00 3,869.79 178,765.49 178,770.00
5,700.00 = Rp.
28,500.00
1 M2
Penutup atap Genting pres dan rangka kaso 5/7 dan reng 2/3 25 bh Genteng pres 3,900.00 0.013 m3 Kayu borneo 2,633,900.00 0.25 kg Paku biasa 10,800.00 0.400 oh Pekerja 25,000.00 0.600 oh Tukang Kayu 42,500.00 0.100 oh Kepala tukang kayu 45,800.00 0.010 oh Mandor 37,500.00 1.000 ls Alat bantu Jumlah Dibulatkan
1 M2 Penutup bubungan 5.000 bh Genteng bubungan
No
Uraian Pekerjaan 0.270 0.032 0.300 0.150 0.020 1.000
zak m3 oh oh oh ls
Portland cement Pasir pasang Pekerja Tukang batu semi terampil Mandor Alat bantu Jumlah Dibulatkan
Harga Satuan 48,300.00 116,600.00 25,000.00 38,300.00 37,500.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,041.00 3,731.20 7,500.00 5,745.00 750.00 2,963.36 62,230.56 62,230.00
No 72
73
74
75
Uraian Pekerjaan 1 m1 Lisplank, kayu borne 2x3/20 0.009 m3 Kayu borneo 0.1 kg Paku biasa 0.200 oh Pekerja 0.500 oh Tukang Kayu 0.100 oh Kepala tukang kayu 0.010 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan 1 bh Daun Pintu double triplek, rangka borneo 3/6 0.025 m3 Kayu kamper medan 0.711 lbr Kayu Multiplek 4 mm (122 x 242 cm) 0.250 kg Lem kayu 0.020 kg Paku biasa 2.250 oh Pekerja 6.750 oh Tukang Kayu 0.675 oh Kepala tukang kayu 0.050 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan 1 M3 Pasang Plafond dan Rangka Pafond, kayu Borneo 5/7 0.023 m3 Kayu borneo 0.023 m2 Asbes eternit 100 x 100 cm 0.280 oh Pekerja 0.800 oh Tukang Kayu 0.080 oh Kepala tukang kayu 0.015 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan 1 M2 Daun jendala kaca, kayu 3/10 dan profil 2/3. 0.014 kg Kayu Kamper medan 2.400 m profil 2/3 0.500 oh Pekerja 1.000 oh Tukang Kayu 0.150 oh Kepala tukang kayu 0.015 oh Mandor 1.000 ls Alat bantu Jumlah Dibulatkan
Harga Satuan
Jumlah
2,633,900.00 10,800.00 25,000.00 42,500.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
23,178.32 1,080.00 5,000.00 21,250.00 4,580.00 375.00 2,773.17 58,236.49 58,240.00
3,956,800.00 45,600.00 25,000.00 10,800.00 25,000.00 42,500.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
96,941.60 32,434.63 6,250.00 216.00 56,250.00 286,875.00 30,915.00 1,875.00 25,587.86 537,345.09 537,350.00
2,633,900.00 10,000.00 25,000.00 42,500.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
60,579.70 230.00 7,000.00 34,000.00 3,664.00 562.50 5,301.81 111,338.01 111,340.00
3,956,800.00 6,500.00 25,000.00 42,500.00 45,800.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
55,395.20 15,600.00 12,500.00 42,500.00 6,870.00 562.50 6,671.39 140,099.09 140,100.00
ANALISA PEKERJAAN No
Uraian Pekerjaan
Harga Satuan
Jumlah
F
PEKERJAAN PEMASANGAN PIPA BAJA
76
1 kg Pengangkutan pipa baja ke lokasi galian. 3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian. 2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km 4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp. 8.000 oh Pekerja 25,000.00 = Rp. 1.000 oh Sopir 50,000.00 = Rp. 1.000 oh Pembantu sopir 33,300.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp.
200,000.00 200,000.00 50,000.00 33,300.00 48,330.00 531,600.00 170.00
8 btg Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda. 15.000 kg Kawat Las Listrik 11,100.00 6.000 jam Welding Mechine 500A 16,700.00 1.000 unit Bahan cairan spay uji las (2 tube) 149,900.00 1.200 kg Coltar primer anti karat 12,900.00 96.00 bh Baut baja , Mur , Ring 4,000.00 8.00 bh Packing Loose Flange 7,500.00 6.000 oh Pekerja 25,000.00 1.000 oh Tukang pipa 37,500.00 6.000 oh Operator semi terampil 45,800.00 2.000 oh Tukang las 50,000.00 0.020 oh Mandor 37,500.00 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 Meter Penyambungan pipa GI dengan flange
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
166,500.00 100,200.00 149,900.00 15,480.00 384,000.00 60,000.00 150,000.00 37,500.00 274,800.00 100,000.00 750.00 143,913.00 1,583,000.00 32,900.00
77 78
1 M' 1 M'
= Rp. = Rp.
49,468.75 56,535.71
79
1 M' Pemasangan Pipa GI ND. 250 mm, diatas tumpuan 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 49,468.75 = Rp. = Rp. = Rp.
5,270.00 49,468.75 5,473.88 60,200.00
1 M' Pemasangan Pipa GI ND. 300 mm, diatas tumpuan 36.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 56,535.71 = Rp. = Rp. = Rp.
6,120.00 56,535.71 6,265.57 68,900.00
80
81
82
Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg )
1 M' Pemasangan GI Dia. 250 mm, Galian tanah biasa. 0.720 m3 Galian tanah biasa 0.203 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.518 m3 Urugan tanah kembali 0.518 m3 Pemadatan tanah perlapis 25 cm 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. 0.720 m3 Galian tanah berbatu 0.203 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,169.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 9,694.91 106,600.00
39,370.00 = Rp. 7,875.00 = Rp. 101,830.00 = Rp.
28,346.40 1,594.69 15,619.99
No 0.518 0.518 31.00 1.000 1.000
m3 m3 kg m1 ls
Uraian Pekerjaan Urugan tanah kembali Pemadatan tanah perlapis 25 cm Pengangkutan pipa baja ke lokasi galian. Penyambungan dan pengelasan pipa. Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Harga Satuan 8,620.00 12,300.00 170.00 49,468.75
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,460.85 6,365.25 5,270.00 49,468.75 13,001.73 124,100.00
No 83
84
85
86
87
88
Uraian Pekerjaan Harga Satuan 1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. 0.720 m2 Bongkaran perkerasan jalan kelas III (40 cm) 22,640.00 0.480 m3 Galian tanah berbatu 39,370.00 0.203 m3 Buangan tanah disekitar lokasi 7,875.00 0.153 m3 Urugan Pasir dipadatkan 101,830.00 0.518 m3 Urugan tanah kembali 8,620.00 0.518 m3 Pemadatan tanah perlapis 25 cm 12,300.00 31.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 1.000 m1 Penyambungan dan pengelasan pipa. 49,468.75 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,300.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 15,337.13 133,300.00
1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. 0.720 m2 Bongkaran perkerasan jalan kelas I (15 cm) 0.480 m3 Galian tanah berbatu 0.203 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.518 m3 Urugan tanah kembali 0.518 m3 Pemadatan tanah perlapis 25 cm 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,884.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 11,956.19 131,500.00
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
3,103.20 23,622.00 1,594.69 15,619.99 3,943.65 5,627.25 5,270.00 49,468.75 10,824.95 119,000.00
71,250.00 28,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
55,575.00 19,810.00 6,290.00 56,535.71 27,642.14 165,800.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,350.40 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71 10,948.91 120,400.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
30,708.60 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71
1 M' Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block. 0.720 m2 Bongkaran Paving Block tebal 8 cm 0.600 m3 Galian tanah berbatu 0.203 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.458 m3 Urugan kembali 0.458 m3 Pemadatan tanah dengan alat 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. 0.780 m3 Galian dasar sungai berbatu 0.70 m3 Pasangan batu kosong (bahan setempat) 37.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. 0.780 m3 Galian tanah biasa 0.250 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.530 m3 Urugan kembali 0.530 m3 Pemadatan tanah dengan alat 37.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. 0.780 m3 Galian tanah berbatu 0.250 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.530 m3 Urugan kembali 0.530 m3 Pemadatan tanah dengan alat 37.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa.
Jumlah
No 1.000
ls
Uraian Pekerjaan Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Harga Satuan
Jumlah = Rp. = Rp.
12,484.73 137,300.00
No 89
90
91
92
93
Uraian Pekerjaan Harga Satuan 1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. 0.600 m2 Bongkaran jalan Kelas III 22,640.00 0.455 m3 Galian tanah berbatu 39,370.00 0.250 m3 Buangan tanah disekitar lokasi 7,875.00 0.179 m3 Urugan Pasir dipadatkan 101,830.00 0.465 m3 Urugan kembali 8,620.00 0.465 m3 Pemadatan tanah dengan alat 12,300.00 37.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 1.000 m1 Penyambungan dan pengelasan pipa. 56,535.71 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,584.00 17,913.35 1,968.75 18,256.66 4,008.30 5,719.50 6,290.00 56,535.71 12,427.63 136,700.00
1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. 0.600 m2 Bongkaran jalan Kelas I tebal 15 cm 0.618 m3 Galian tanah berbatu 0.250 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.465 m3 Urugan kembali 0.465 m3 Pemadatan tanah dengan alat 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,904.00 24,310.98 1,968.75 18,256.66 4,008.30 5,719.50 5,270.00 56,535.71 13,097.39 144,000.00
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 24,803.10 1,968.75 18,256.66 4,051.40 5,781.00 5,270.00 56,535.71 12,097.66 133,000.00
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 3.000 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 10.000 jam Water Pump (Dia. 5 cm) 10,400.00 6.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
44,156.25 45,000.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 62,400.00 117,945.63 1,297,401.88 2,590.00
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 4.500 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
63,585.00 67,500.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00
1 M' Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. 1.000 m2 Bongkaran Paving Block tebal 8 cm 0.630 m3 Galian tanah berbatu 0.250 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.470 m3 Urugan kembali 0.470 m3 Pemadatan tanah dengan alat 31.00 kg Pengangkutan pipa baja ke lokasi galian. 1.000 m1 Penyambungan dan pengelasan pipa. 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah
No 2.000 2.000 2.000 12.000 10.000 1.000
oh oh oh jam jam ls
Uraian Pekerjaan Operator semi terampil Pembantu operator Pembantu sopir Water Pump (Dia. 5 cm) Pressure Pump 20 Bar Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
Harga Satuan 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
91,600.00 100,000.00 66,600.00 124,800.00 104,000.00 128,378.50 1,412,163.50 2,820.00
No G
Uraian Pekerjaan PEKERJAAN PEMASANGAN PIPA PVC
94
1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm 200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian. 1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m) 4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00 4.000 oh Pekerja 25,000.00 = Rp. 100,000.00 1.000 oh Sopir 50,000.00 = Rp. 50,000.00 1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00 1.000 ls Alat bantu = Rp. 18,745.00 Jumlah ( Dibulatkan dalam ratusan) = Rp. 393,645.00 Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp. 330.00
95 96 97 98 99 100 101
102
103 104 105 106 107 108 109
110
1 M' 110 1 M' 120 1 M' 140 1 M' 170 1 M' 210 1 M' 260 1 M' 310
Harga Satuan
Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm % Analisa F.48
Jumlah
330.00 = Rp.
363.00
330.00 = Rp.
396.00
330.00 = Rp.
462.00
330.00 = Rp.
561.00
330.00 = Rp.
693.00
330.00 = Rp.
858.00
330.00 = Rp.
1,023.00
1 M' Penyambungan pipa PVC Dia. 50 mm didalam galian 360 m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung. 4.000 oh Pekerja 25,000.00 = Rp. 1.000 oh Tukang batu semi terampil 38,300.00 = Rp. 2.000 oh Tukang pipa 37,500.00 = Rp. 1.000 oh Mandor 37,500.00 = Rp. 0.100 An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya Penyambungan per 1 m panjang Pipa. = Rp.
100,000.00 38,300.00 75,000.00 37,500.00 5,067.00 12,540.00 268,407.00 750.00
1 M' 105 1 M' 125 1 M' 175 1 M' 200 1 M' 240 1 M' 275 1 M' 300
Penyambungan pipa PVC Dia. 75 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 100 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 150 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 200 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 250 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 300 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 400 mm didalam galian % Analisa F.50
1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. 0.385 m3 Galian tanah biasa 0.090 m3 Buangan tanah disekitar lokasi 0.088 m3 Urugan Pasir dipadatkan 0.295 m3 Urugan kembali 0.295 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian
750.00 = Rp.
787.50
750.00 = Rp.
937.50
750.00 = Rp.
1,312.50
750.00 = Rp.
1,500.00
750.00 = Rp.
1,800.00
750.00 = Rp.
2,062.50
750.00 = Rp.
2,250.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,576.80 708.75 8,924.67 2,542.90 3,628.50 330.00 750.00
No 1.00
111
ls
Uraian Pekerjaan Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Harga Satuan
1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. 0.399 m3 Galian tanah biasa 0.106 m3 Buangan tanah disekitar lokasi 0.100 m3 Urugan Pasir dipadatkan 0.307 m3 Urugan kembali 0.307 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
Jumlah = Rp. = Rp.
2,446.16 26,900.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,847.40 831.80 10,170.73 2,645.26 3,774.56 363.00 787.50 2,642.02 29,000.00
No 112
113
114
115
Uraian Pekerjaan
Harga Satuan
1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. 0.509 m3 Galian tanah biasa 0.123 m3 Buangan tanah disekitar lokasi 0.115 m3 Urugan Pasir dipadatkan 0.345 m3 Urugan kembali 0.345 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. 0.536 m3 Galian tanah biasa 0.141 m3 Buangan tanah disekitar lokasi 0.152 m3 Urugan Pasir dipadatkan 0.371 m3 Urugan kembali 0.371 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. 0.542 m3 Galian tanah biasa 0.148 m3 Buangan tanah disekitar lokasi 0.152 m3 Urugan Pasir dipadatkan 0.380 m3 Urugan kembali 0.380 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. 0.550 m3 Galian tanah biasa 0.160 m3 Buangan tanah disekitar lokasi 0.177 m3 Urugan Pasir dipadatkan 0.390 m3 Urugan kembali 0.390 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. 0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 0.420 m3 Galian tanah berbatu 0.136 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.524 m3 Urugan kembali 0.524 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. 0.688 m3 Galian tanah biasa 0.250 m3 Buangan tanah disekitar lokasi 0.219 m3 Urugan Pasir dipadatkan 0.424 m3 Urugan kembali
Jumlah
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,012.20 964.69 11,674.08 2,973.90 4,243.50 396.00 937.50 3,120.19 34,300.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,553.40 1,107.42 15,492.71 3,196.94 4,561.76 462.00 1,312.50 3,668.67 40,300.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,661.64 1,167.27 15,492.71 3,273.66 4,671.23 561.00 1,500.00 3,732.75 41,000.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,824.00 1,260.00 18,028.27 3,361.80 4,797.00 693.00 1,800.00 4,076.41 44,800.00
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,388.00 16,535.40 1,074.38 15,619.99 4,513.19 6,439.93 693.00 1,800.00 5,300.00 69,300.00
19,680.00 7,875.00 101,830.00 8,620.00
= Rp. = Rp. = Rp. = Rp.
13,530.00 1,968.75 22,272.14 3,652.73
No 0.424 1.00 1.000 1.000
m3 m1 m1 ls
Uraian Pekerjaan Harga Satuan Pemadatan tanah dengan alat 12,300.00 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp.
5,212.13 858.00 2,062.50 5,500.00 55,000.00
No
1
2
3
4
Uraian Pekerjaan
Harga Satuan
Jumlah
1 M' Pemasangan Pipa STEEL Dia. 300 mm, Galian tanah berbatu. 0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 8,000.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
27,992.07 1,968.75 18,256.66 4,051.40 5,781.00 858.00 8,000.00 8,000.00 74,900.00
1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. 0.715 m3 Galian tanah biasa 0.270 m3 Buangan tanah disekitar lokasi 0.232 m3 Urugan Pasir dipadatkan 0.434 m3 Urugan kembali 0.434 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa. 0.840 m3 Galian tanah biasa 0.360 m3 Buangan tanah disekitar lokasi 0.234 m3 Urugan Pasir dipadatkan 0.480 m3 Urugan kembali 0.480 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras 0.399 m3 Galian tanah keras 0.123 m3 Buangan tanah disekitar lokasi 0.120 m3 Urugan Pasir dipadatkan 0.263 m3 Urugan tanah kembali 0.263 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras 0.413 m3 Galian tanah keras 0.123 m3 Buangan tanah disekitar lokasi 0.127 m3 Urugan Pasir dipadatkan 0.290 m3 Urugan tanah kembali 0.290 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,071.20 2,129.40 23,649.29 3,737.63 5,333.28 858.00 2,062.50 5,184.13 57,000.00
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,531.20 2,835.00 23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 5,653.81 62,100.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,714.41 964.69 12,234.15 2,262.75 3,228.75 330.00 750.00 5,300.00 35,700.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
11,083.88 964.69 12,957.14 2,499.80 3,567.00 363.00 787.50 4,800.00 37,000.00
No 5
6
7
8
9
10
Uraian Pekerjaan
Harga Satuan
1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. 0.495 m3 Galian tanah keras 0.160 m3 Buangan tanah disekitar lokasi 0.158 m3 Urugan Pasir dipadatkan 0.308 m3 Urugan tanah kembali 0.308 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. 0.550 m3 Galian tanah keras 0.181 m3 Buangan tanah disekitar lokasi 0.200 m3 Urugan Pasir dipadatkan 0.314 m3 Urugan tanah kembali 0.314 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. 0.561 m3 Galian tanah keras 0.185 m3 Buangan tanah disekitar lokasi 0.201 m3 Urugan Pasir dipadatkan 0.327 m3 Urugan tanah kembali 0.327 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. 0.605 m3 Galian tanah keras 0.250 m3 Buangan tanah disekitar lokasi 0.228 m3 Urugan Pasir dipadatkan 0.355 m3 Urugan tanah kembali 0.355 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. 0.660 m3 Galian tanah keras 0.281 m3 Buangan tanah disekitar lokasi 0.328 m3 Urugan Pasir dipadatkan 0.352 m3 Urugan tanah kembali 0.352 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. 0.688 m3 Galian tanah keras 0.303 m3 Buangan tanah disekitar lokasi 0.332 m3 Urugan Pasir dipadatkan 0.413 m3 Urugan tanah kembali 0.413 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm
Jumlah
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,300.65 1,260.00 16,052.77 2,650.65 3,782.25 396.00 937.50 5,100.00 43,400.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 1,062.00 1,812.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,778.50 1,422.42 20,380.55 2,709.91 3,866.81 1,062.00 1,812.50 7,100.00 53,100.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,074.07 1,456.09 20,472.30 2,815.29 4,017.18 462.00 1,312.50 7,400.00 53,000.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,256.35 1,968.75 23,221.60 3,060.10 4,366.50 693.00 1,800.00 8,100.00 59,400.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,734.20 2,212.09 33,427.52 3,030.79 4,324.68 858.00 2,062.50 9,100.00 72,700.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
18,473.13 2,382.19 33,779.75 3,555.75 5,073.75 858.00
No 1.000 1.000
Uraian Pekerjaan Harga Satuan m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
Jumlah 2,062.50 10,100.00 76,200.00
No 11
12
13
14
15
16
Uraian Pekerjaan
Harga Satuan
1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras 0.715 m3 Galian tanah keras 0.360 m3 Buangan tanah disekitar lokasi 0.407 m3 Urugan Pasir dipadatkan 0.465 m3 Urugan tanah kembali 0.465 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 1.000 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 1.000 ls Alat bantu Jumlah 1 M' Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu 0.373 m3 Galian tanah berbatu 0.063 m3 Buangan tanah disekitar lokasi 0.061 m3 Urugan Pasir dipadatkan 0.295 m3 Urugan tanah kembali 0.295 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 1.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu 0.381 m3 Galian tanah berbatu 0.063 m3 Buangan tanah disekitar lokasi 0.071 m3 Urugan Pasir dipadatkan 0.309 m3 Urugan tanah kembali 0.309 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm 1.00 m1 Penyambungan pipa PVC Dia. 75 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. 0.455 m3 Galian tanah berbatu 0.090 m3 Buangan tanah disekitar lokasi 0.082 m3 Urugan Pasir dipadatkan 0.350 m3 Urugan tanah kembali 0.350 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. 0.500 m3 Galian tanah berbatu 0.123 m3 Buangan tanah disekitar lokasi 0.105 m3 Urugan Pasir dipadatkan 0.373 m3 Urugan tanah kembali 0.373 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. 0.550 m3 Galian tanah berbatu 0.090 m3 Buangan tanah disekitar lokasi 0.105 m3 Urugan Pasir dipadatkan 0.389 m3 Urugan tanah kembali 0.389 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm
Jumlah
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,212.05 2,835.00 41,469.54 4,008.30 5,719.50 330.00 750.00 11,400.00 85,700.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,665.33 492.19 6,164.35 2,542.90 3,628.50 330.00 750.00 5,500.00 34,000.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,009.81 492.19 7,250.84 2,661.43 3,797.63 363.00 787.50 5,900.00 36,200.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,913.35 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 6,700.00 42,300.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,685.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 7,500.00 48,300.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,653.50 708.75 10,740.16 3,348.87 4,778.55 561.00
No 1.00 1.00
Uraian Pekerjaan Harga Satuan m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
Jumlah 1,500.00 7,800.00 51,000.00
No 17
18
19
19
Uraian Pekerjaan Harga Satuan 1 M' Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. 0.558 m3 Galian tanah berbatu 39,370.00 0.203 m3 Buangan tanah disekitar lokasi 7,875.00 0.153 m3 Urugan Pasir dipadatkan 101,830.00 0.403 m3 Urugan tanah kembali 8,620.00 0.403 m3 Pemadatan tanah perlapis 25 cm 12,300.00 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,968.46 1,594.69 15,619.99 3,469.55 4,950.75 693.00 1,800.00 8,200.00 58,200.00
1 M' Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. 0.711 m3 Galian tanah berbatu 0.250 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.470 m3 Urugan tanah kembali 0.470 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
27,992.07 1,968.75 18,256.66 4,051.40 5,781.00 858.00 2,062.50 8,500.00 69,400.00
1 M' Pemasangan Pipa STEEL Dia. 300 mm, Galian tanah berbatu. 0.711 m3 Galian tanah berbatu 39,370.00 = Rp. 0.250 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 0.470 m3 Urugan tanah kembali 8,620.00 = Rp. 0.470 m3 Pemadatan tanah perlapis 25 cm 12,300.00 = Rp. 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
27,992.07 1,968.75 18,256.66 4,051.40 5,781.00 858.00 2,062.50 14,800.00 75,700.00
1 M' Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu. 0.730 m3 Galian tanah berbatu 0.260 m3 Buangan tanah disekitar lokasi 0.189 m3 Urugan Pasir dipadatkan 0.490 m3 Urugan tanah kembali 0.490 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu 0.805 m3 Galian tanah berbatu 0.360 m3 Buangan tanah disekitar lokasi 0.234 m3 Urugan Pasir dipadatkan 0.480 m3 Urugan tanah kembali 0.480 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1.000 m1 Penyambungan pipa PVC Dia. 400 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu. 0.500 m3 Galian tanah berbatu 0.123 m3 Buangan tanah disekitar lokasi 0.105 m3 Urugan Pasir dipadatkan 0.373 m3 Urugan tanah kembali 0.373 m3 Pemadatan tanah perlapis 25 cm
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
Jumlah
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
28,740.10 2,048.29 19,285.15 4,222.94 6,025.77 858.00 2,062.50 16,759.33 80,000.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
31,692.85 2,835.00 23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 17,207.94 88,900.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00
= Rp. = Rp. = Rp. = Rp. = Rp.
19,685.00 964.69 10,673.97 3,210.95 4,581.75
No 1.00 1.00 1.00
Uraian Pekerjaan kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Harga Satuan 170.00 = Rp. 23,000.00 = Rp. = Rp. = Rp.
1 M' Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu. 0.550 m3 Galian tanah berbatu 0.090 m3 Buangan tanah disekitar lokasi 0.105 m3 Urugan Pasir dipadatkan 0.389 m3 Urugan tanah kembali 0.389 m3 Pemadatan tanah perlapis 25 cm 1.00 kg Pengangkutan pipa baja ke lokasi galian. 1.00 m1 Penyambungan dan pengelasan pipa. 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 24,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
Jumlah 170.00 23,000.00 40,000.00 102,200.00
21,653.50 708.75 10,740.16 3,348.87 4,778.55 170.00 24,000.00 57,500.00 122,800.00
No 20
21
22
23
24
25
Uraian Pekerjaan Harga Satuan 1 M' Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. 0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 0.400 m3 Galian tanah berbatu 39,370.00 0.090 m3 Buangan tanah disekitar lokasi 7,875.00 0.082 m3 Urugan Pasir dipadatkan 101,830.00 0.350 m3 Urugan tanah kembali 8,620.00 0.350 m3 Pemadatan tanah perlapis 25 cm 12,300.00 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 1.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,586.00 15,748.00 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 3,347.69 36,800.00
1 M' Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. 0.600 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 0.400 m3 Galian tanah berbatu 0.123 m3 Buangan tanah disekitar lokasi 0.105 m3 Urugan Pasir dipadatkan 0.373 m3 Urugan tanah kembali 0.373 m3 Pemadatan tanah perlapis 25 cm 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm 1.00 m1 Penyambungan pipa PVC Dia. 150 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,586.00 15,748.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 3,695.39 40,600.00
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 19,685.00 1,035.00 13,092.43 3,608.09 5,148.43 561.00 1,500.00 4,893.99 53,800.00
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 23,622.00 1,174.22 15,619.99 4,403.90 6,283.98 693.00 1,800.00 5,790.71 63,600.00
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 25,984.20 1,344.38 18,256.66 4,217.64 6,018.21 858.00 2,062.50 6,305.16 69,300.00
4,310.00 = Rp. 39,370.00 = Rp.
5,172.00 28,346.40
1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. 1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 0.500 m3 Galian tanah berbatu 0.131 m3 Buangan tanah disekitar lokasi 0.129 m3 Urugan Pasir dipadatkan 0.419 m3 Urugan kembali 0.419 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. 1.000 m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 0.600 m3 Galian tanah berbatu 0.149 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.511 m3 Urugan kembali 0.511 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. 1.000 m2 Bongkaran Paving Block tebal 8 cm 0.660 m3 Galian tanah berbatu 0.171 m3 Buangan tanah disekitar lokasi 0.179 m3 Urugan Pasir dipadatkan 0.489 m3 Urugan kembali 0.489 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. 1.200 m2 Bongkaran Paving Block tebal 8 cm 0.720 m3 Galian tanah berbatu
Jumlah
No 0.246 0.234 0.414 0.414 1.00 1.000 1.000
m3 m3 m3 m3 m1 m1 ls
Uraian Pekerjaan Harga Satuan Buangan tanah disekitar lokasi 7,875.00 Urugan Pasir dipadatkan 101,830.00 Urugan kembali 8,620.00 Pemadatan tanah dengan alat 12,300.00 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm 1,023.00 Penyambungan pipa PVC Dia. 400 mm didalam galian 2,250.00 Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,935.00 23,857.31 3,571.14 5,095.71 1,023.00 2,250.00 7,125.06 78,300.00
No 26
27
28
29
30
31
Uraian Pekerjaan Harga Satuan 1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. 0.700 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 0.420 m3 Galian tanah berbatu 39,370.00 0.311 m3 Buangan tanah disekitar lokasi 7,875.00 0.129 m3 Urugan Pasir dipadatkan 101,830.00 0.349 m3 Urugan kembali 8,620.00 0.349 m3 Pemadatan tanah dengan alat 12,300.00 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,848.00 16,535.40 2,452.50 13,092.43 3,004.69 4,287.43 561.00 1,500.00 5,728.14 63,000.00
1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. 0.750 m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. 0.420 m3 Galian tanah berbatu 39,370.00 = Rp. 0.349 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 0.153 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 0.311 m3 Urugan kembali 8,620.00 = Rp. 0.311 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. 1.00 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
16,980.00 16,535.40 2,749.22 15,619.99 2,679.90 3,823.98 693.00 1,800.00 6,088.15 66,900.00
1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. 0.800 m2 Bongkaran jalan Kelas III 22,640.00 = Rp. 0.585 m3 Galian tanah berbatu 39,370.00 = Rp. 0.236 m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. 0.179 m3 Urugan Pasir dipadatkan 101,830.00 = Rp. 0.564 m3 Urugan kembali 8,620.00 = Rp. 0.564 m3 Pemadatan tanah dengan alat 12,300.00 = Rp. 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. 1.000 m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
18,112.00 23,031.45 1,856.25 18,256.66 4,864.14 6,940.71 858.00 2,062.50 7,598.17 83,500.00
1 M' Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. 0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 0.368 m3 Galian tanah berbatu 0.136 m3 Buangan tanah disekitar lokasi 0.129 m3 Urugan Pasir dipadatkan 0.524 m3 Urugan kembali 0.524 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 1.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. 0.700 m2 Bongkaran jalan Kelas I tebal 15 cm 0.420 m3 Galian tanah berbatu 0.136 m3 Buangan tanah disekitar lokasi 0.153 m3 Urugan Pasir dipadatkan 0.524 m3 Urugan kembali 0.524 m3 Pemadatan tanah dengan alat 1.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 1.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 M' Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. 0.800 m2 Bongkaran jalan Kelas I tebal 15 cm 0.585 m3 Galian tanah berbatu
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,388.00 14,468.48 1,074.38 13,092.43 4,513.19 6,439.93 561.00 1,500.00 5,903.74 64,900.00
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,388.00 16,535.40 1,074.38 15,619.99 4,513.19 6,439.93 693.00 1,800.00 8,328.30 72,300.00
24,840.00 = Rp. 39,370.00 = Rp.
19,872.00 23,031.45
No 0.169 0.179 0.491 0.491 1.00 1.000 1.000
m3 m3 m3 m3 m1 m1 ls
Uraian Pekerjaan Harga Satuan Buangan tanah disekitar lokasi 7,875.00 Urugan Pasir dipadatkan 101,830.00 Urugan kembali 8,620.00 Pemadatan tanah dengan alat 12,300.00 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,331.72 18,256.66 4,231.50 6,037.98 858.00 2,062.50 7,568.18 83,200.00
No 32
33
34
35
Uraian Pekerjaan Harga Satuan 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 0.118 kg Kaporit 15,000.00 4.000 oh Pekerja 25,000.00 4.000 jam Pickup Truck 47,900.00 1.000 oh Tukang pipa 37,500.00 0.100 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 6.000 jam Water Pump (Dia. 5 cm) 10,400.00 4.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,766.25 1,766.25 100,000.00 191,600.00 37,500.00 3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 74,858.25 823,440.75 1,640.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.265 kg Kaporit 4.000 oh Pekerja 4.000 jam Pickup Truck 1.000 oh Tukang pipa 0.100 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 6.000 jam Water Pump (Dia. 5 cm) 4.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
3,974.06 3,974.06 100,000.00 191,600.00 37,500.00 3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 75,299.81 828,297.94 1,650.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,065.00 7,065.00 150,000.00 239,500.00 56,250.00 5,625.00 50,000.00 91,600.00 100,000.00 66,600.00 83,200.00 62,400.00 91,930.50 1,011,235.50 2,020.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,896.25 15,896.25 150,000.00 239,500.00 56,250.00 5,625.00 50,000.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.471 kg Kaporit 6.000 oh Pekerja 5.000 jam Pickup Truck 1.500 oh Tukang pipa 0.150 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 8.000 jam Water Pump (Dia. 5 cm) 6.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 1.060 kg Kaporit 6.000 oh Pekerja 5.000 jam Pickup Truck 1.500 oh Tukang pipa 0.150 oh Mandor 1.000 oh Sopir
Jumlah
No 2.000 2.000 2.000 9.000 7.000 1.000
oh oh oh jam jam ls
Uraian Pekerjaan Operator semi terampil Pembantu operator Pembantu sopir Water Pump (Dia. 5 cm) Pressure Pump 20 Bar Alat bantu Jumlah Biaya Pengetesan per 1m panjang
Harga Satuan 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
91,600.00 100,000.00 66,600.00 93,600.00 72,800.00 95,776.75 1,053,544.25 2,100.00
No 36
37
38
39
Uraian Pekerjaan Harga Satuan 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 1.884 kg Kaporit 15,000.00 7.000 oh Pekerja 25,000.00 6.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 10.000 jam Water Pump (Dia. 5 cm) 10,400.00 8.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
28,260.00 28,260.00 175,000.00 287,400.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 83,200.00 109,682.00 1,206,502.00 2,410.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 2.944 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 11.000 jam Water Pump (Dia. 5 cm) 8.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
44,156.25 44,156.25 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 114,400.00 83,200.00 120,981.25 1,330,793.75 2,660.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
63,585.00 63,585.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 124,800.00 93,600.00 126,947.00 1,396,417.00 2,790.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
113,040.00 113,040.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 4.239 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 12.000 jam Water Pump (Dia. 5 cm) 9.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 7.536 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir
Jumlah
No 2.000 2.000 2.000 18.000 12.000 1.000
oh oh oh jam jam ls
Uraian Pekerjaan Operator semi terampil Pembantu operator Pembantu sopir Water Pump (Dia. 5 cm) Pressure Pump 20 Bar Alat bantu Jumlah Biaya Pengetesan per 1m panjang
Harga Satuan 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
91,600.00 100,000.00 66,600.00 187,200.00 124,800.00 146,198.00 1,608,178.00 3,210.00
ANALISA PEKERJAAN No
Uraian Pekerjaan
Harga Satuan
Jumlah
F
PEKERJAAN PEMASANGAN PIPA BAJA
76
1 kg Pengangkutan pipa baja ke lokasi galian. 3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian. 2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km 4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp. 8.000 oh Pekerja 25,000.00 = Rp. 1.000 oh Sopir 50,000.00 = Rp. 1.000 oh Pembantu sopir 33,300.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp. 8 btg 15.000 6.000 1.000 1.200 96.00 8.00 6.000 1.000 6.000 2.000 0.020 1.000
Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda. kg Kawat Las Listrik 11,100.00 jam Welding Mechine 500A 16,700.00 unit Bahan cairan spay uji las (2 tube) 149,900.00 kg Coltar primer anti karat 12,900.00 bh Baut baja , Mur , Ring 4,000.00 bh Packing Loose Flange 7,500.00 oh Pekerja 25,000.00 oh Tukang pipa 37,500.00 oh Operator semi terampil 45,800.00 oh Tukang las 50,000.00 oh Mandor 37,500.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 Meter Penyambungan pipa GI dengan flange
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
77 78
1 M' 1 M'
Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg )
= Rp. = Rp.
79
1 M' 31.00 1.000 1.000
Pemasangan Pipa GI ND. 250 mm, diatas tumpuan kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 49,468.75 = Rp. = Rp. = Rp.
1 M' 36.00 1.000 1.000
Pemasangan Pipa GI ND. 300 mm, diatas tumpuan kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 56,535.71 = Rp. = Rp. = Rp.
1 M'
Pemasangan GI Dia. 250 mm, Galian tanah biasa.
80
81
0.720 0.203 0.153 0.518 0.518 31.00 1.000 1.000
82
83
84
85
m3 m3 m3 m3 m3 kg m1 ls
Galian tanah biasa Buangan tanah disekitar lokasi Urugan Pasir dipadatkan Urugan tanah kembali Pemadatan tanah perlapis 25 cm Pengangkutan pipa baja ke lokasi galian. Penyambungan dan pengelasan pipa. Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.720 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.720 0.480 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. m2 Bongkaran perkerasan jalan kelas III (40 cm) m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.720 0.480 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. m2 Bongkaran perkerasan jalan kelas I (15 cm) m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.720 0.600 0.203 0.153 0.458
Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
22,640.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00
= Rp. = Rp. = Rp. = Rp. = Rp.
0.458 31.00 1.000 1.000
86
87
88
89
90
m3 kg m1 ls
Pemadatan tanah dengan alat Pengangkutan pipa baja ke lokasi galian. Penyambungan dan pengelasan pipa. Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.780 0.70 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. m3 Galian dasar sungai berbatu m3 Pasangan batu kosong (bahan setempat) kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.780 0.250 0.179 0.530 0.530 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.780 0.250 0.179 0.530 0.530 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.600 0.455 0.250 0.179 0.465 0.465 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.600 0.618
Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu
12,300.00 = Rp. 170.00 = Rp. 49,468.75 = Rp. = Rp. = Rp.
71,250.00 28,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
22,640.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
24,840.00 = Rp. 39,370.00 = Rp.
0.250 0.179 0.465 0.465 31.00 1.000 1.000
91
92
93
1 M' 1.000 0.630 0.250 0.179 0.470 0.470 31.00 1.000 1.000
m3 m3 m3 m3 kg m1 ls
Buangan tanah disekitar lokasi Urugan Pasir dipadatkan Urugan kembali Pemadatan tanah dengan alat Pengangkutan pipa baja ke lokasi galian. Penyambungan dan pengelasan pipa. Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 3.000 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 10.000 jam Water Pump (Dia. 5 cm) 10,400.00 6.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 4.500 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
12.000 10.000 1.000
jam Water Pump (Dia. 5 cm) jam Pressure Pump 20 Bar ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
10,400.00 = Rp. 10,400.00 = Rp. = Rp. = Rp. = Rp.
G
PEKERJAAN PEMASANGAN PIPA PVC
94
1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm 200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian. 1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m) 4.000 jam Pickup Truck 47,900.00 = Rp. 4.000 oh Pekerja 25,000.00 = Rp. 1.000 oh Sopir 50,000.00 = Rp. 1.000 oh Pembantu sopir 33,300.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp.
95
1 M' 110 1 M' 120 1 M' 140 1 M' 170 1 M' 210 1 M' 260 1 M' 310
Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm % Analisa F.48
102
1 M' 360 4.000 1.000 2.000 1.000 0.100 1.000
Penyambungan pipa PVC Dia. 50 mm didalam galian m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung. oh Pekerja 25,000.00 = Rp. oh Tukang batu semi terampil 38,300.00 = Rp. oh Tukang pipa 37,500.00 = Rp. oh Mandor 37,500.00 = Rp. An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya Penyambungan per 1 m panjang Pipa. = Rp.
103
1 M' 105 1 M' 125
Penyambungan pipa PVC Dia. 75 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 100 mm didalam galian % Analisa F.50
96 97 98 99 100 101
104
330.00 = Rp. 330.00 = Rp. 330.00 = Rp. 330.00 = Rp. 330.00 = Rp. 330.00 = Rp. 330.00 = Rp.
750.00 = Rp. 750.00 = Rp.
105 106 107 108 109
110
111
112
113
1 M' 175 1 M' 200 1 M' 240 1 M' 275 1 M' 300
Penyambungan pipa PVC Dia. 150 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 200 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 250 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 300 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 400 mm didalam galian % Analisa F.50
1 M' 0.385 0.090 0.088 0.295 0.295 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm m1 Penyambungan pipa PVC Dia. 50 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.399 0.106 0.100 0.307 0.307 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.509 0.123 0.115 0.345 0.345 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.536 0.141 0.152 0.371 0.371 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm
750.00 = Rp. 750.00 = Rp. 750.00 = Rp. 750.00 = Rp. 750.00 = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
114
115
116
117
118
1.00 1.00
m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.542 0.148 0.152 0.380 0.380 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.550 0.160 0.177 0.390 0.390 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.688 0.250 0.219 0.424 0.424 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.715 0.270 0.232 0.434 0.434 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.840 0.360
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi
1,312.50 = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,680.00 = Rp. 7,875.00 = Rp.
0.234 0.480 0.480 1.00 1.000 1.000
119
120
121
122
m3 m3 m3 m1 m1 ls
Urugan Pasir dipadatkan Urugan kembali Pemadatan tanah dengan alat Pengangkutan dan penjajaran pipa PVC Dia. 400 mm Penyambungan pipa PVC Dia. 400 mm didalam galian Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.399 0.123 0.120 0.263 0.263 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm m1 Penyambungan pipa PVC Dia. 50 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.413 0.123 0.127 0.290 0.290 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.495 0.160 0.158 0.308 0.308 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.550 0.181 0.200 0.314 0.314 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
123
124
125
126
127
1 M' 0.561 0.185 0.201 0.327 0.327 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.605 0.250 0.228 0.355 0.355 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.660 0.281 0.328 0.352 0.352 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.688 0.303 0.332 0.413 0.413 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.715 0.360 0.407 0.465 0.465
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00
= Rp. = Rp. = Rp. = Rp. = Rp.
128
129
130
131
132
1.00 1.000 1.000
m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm m1 Penyambungan pipa PVC Dia. 50 mm didalam galian ls Alat bantu Jumlah
1 M' 0.373 0.063 0.061 0.295 0.295 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm m1 Penyambungan pipa PVC Dia. 50 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.381 0.063 0.071 0.309 0.309 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.455 0.090 0.082 0.350 0.350 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.500 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.550
Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. m3 Galian tanah berbatu
330.00 = Rp. 750.00 = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 330.00 750.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 = Rp.
0.090 0.105 0.389 0.389 1.00 1.00 1.00
133
134
135
135
m3 m3 m3 m3 m1 m1 ls
Buangan tanah disekitar lokasi Urugan Pasir dipadatkan Urugan tanah kembali Pemadatan tanah perlapis 25 cm Pengangkutan dan penjajaran pipa PVC Dia. 200 mm Penyambungan pipa PVC Dia. 200 mm didalam galian Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.558 0.203 0.153 0.403 0.403 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.711 0.250 0.179 0.470 0.470 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.730 0.260 0.189 0.490 0.490 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.805 0.360 0.234 0.480 0.480 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm m1 Penyambungan pipa PVC Dia. 400 mm didalam galian ls Alat bantu
7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
Jumlah ( Dibulatkan dalam ratusan)
= Rp.
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
1 M' 0.500 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.550 0.090 0.105 0.389 0.389 1.00 1.00 1.00
Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 23,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 24,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
136
137
138
139
140
1 M' 0.600 0.400 0.090 0.082 0.350 0.350 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.600 0.400 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 1.000 0.500 0.131 0.129 0.419 0.419 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 1.000 0.600 0.149 0.153 0.511 0.511 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M'
Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1.000 0.660 0.171 0.179 0.489 0.489 1.00 1.000 1.000
141
m2 m3 m3 m3 m3 m3 m1 m1 ls
Bongkaran Paving Block tebal 8 cm Galian tanah berbatu Buangan tanah disekitar lokasi Urugan Pasir dipadatkan Urugan kembali Pemadatan tanah dengan alat Pengangkutan dan penjajaran pipa PVC Dia. 300 mm Penyambungan pipa PVC Dia. 300 mm didalam galian Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1 M' 1.200 0.720 0.246 0.234 0.414 0.414 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm m1 Penyambungan pipa PVC Dia. 400 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
142
1 M' 0.700 0.420 0.311 0.129 0.349 0.349 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. m3 Galian tanah berbatu 39,370.00 = Rp. m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. m3 Urugan Pasir dipadatkan 101,830.00 = Rp. m3 Urugan kembali 8,620.00 = Rp. m3 Pemadatan tanah dengan alat 12,300.00 = Rp. m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 = Rp. m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
143
1 M' 0.750 0.420 0.349 0.153 0.311 0.311 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. m3 Galian tanah berbatu 39,370.00 = Rp. m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. m3 Urugan Pasir dipadatkan 101,830.00 = Rp. m3 Urugan kembali 8,620.00 = Rp. m3 Pemadatan tanah dengan alat 12,300.00 = Rp. m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
144
1 M' 0.800 0.585 0.236
Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi
22,640.00 = Rp. 39,370.00 = Rp. 7,875.00 = Rp.
0.179 0.564 0.564 1.00 1.000 1.000
145
146
147
148
m3 m3 m3 m1 m1 ls
Urugan Pasir dipadatkan Urugan kembali Pemadatan tanah dengan alat Pengangkutan dan penjajaran pipa PVC Dia. 300 mm Penyambungan pipa PVC Dia. 300 mm didalam galian Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.700 0.368 0.136 0.129 0.524 0.524 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.700 0.420 0.136 0.153 0.524 0.524 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.800 0.585 0.169 0.179 0.491 0.491 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.118 kg Kaporit 4.000 oh Pekerja 4.000 jam Pickup Truck 1.000 oh Tukang pipa
101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp.
0.100 1.000 2.000 2.000 2.000 6.000 4.000 1.000
149
150
151
oh oh oh oh oh jam jam ls
Mandor Sopir Operator semi terampil Pembantu operator Pembantu sopir Water Pump (Dia. 5 cm) Pressure Pump 20 Bar Alat bantu Jumlah Biaya Pengetesan per 1m panjang
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.265 kg Kaporit 4.000 oh Pekerja 4.000 jam Pickup Truck 1.000 oh Tukang pipa 0.100 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 6.000 jam Water Pump (Dia. 5 cm) 4.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.471 kg Kaporit 6.000 oh Pekerja 5.000 jam Pickup Truck 1.500 oh Tukang pipa 0.150 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 8.000 jam Water Pump (Dia. 5 cm) 6.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 1.060 kg Kaporit
37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 = Rp. 15,000.00 = Rp.
6.000 5.000 1.500 0.150 1.000 2.000 2.000 2.000 9.000 7.000 1.000
152
153
154
oh jam oh oh oh oh oh oh jam jam ls
Pekerja Pickup Truck Tukang pipa Mandor Sopir Operator semi terampil Pembantu operator Pembantu sopir Water Pump (Dia. 5 cm) Pressure Pump 20 Bar Alat bantu Jumlah Biaya Pengetesan per 1m panjang
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 1.884 kg Kaporit 7.000 oh Pekerja 6.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 10.000 jam Water Pump (Dia. 5 cm) 8.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 2.944 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 11.000 jam Water Pump (Dia. 5 cm) 8.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M'
Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm.
25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 4.239 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 12.000 jam Water Pump (Dia. 5 cm) 9.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 155
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 7.536 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 18.000 jam Water Pump (Dia. 5 cm) 12.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
Jumlah
170.00
didekat galian. 200,000.00 200,000.00 50,000.00 33,300.00 48,330.00 531,600.00 170.00
166,500.00 100,200.00 149,900.00 15,480.00 384,000.00 60,000.00 150,000.00 37,500.00 274,800.00 100,000.00 750.00 143,913.00 1,583,000.00 32,900.00 49,468.75 56,535.71
s
0.79 125,920
49,468.75 56,535.71 60,200.00
5,270.00 49,468.75 5,473.88 60,200.00 68,900.00 6,120.00 56,535.71 6,265.57 68,900.00 106,600.00
14,169.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 9,694.91 106,600.00 124,100.00 28,346.40 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 13,001.73 124,100.00 133,300.00 16,300.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 15,337.13 133,300.00 131,500.00 17,884.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 11,956.19 131,500.00 119,000.00 3,103.20 23,622.00 1,594.69 15,619.99 3,943.65
5,627.25 5,270.00 49,468.75 10,824.95 119,000.00
(11,100.00) 165,800.00
55,575.00 19,810.00 6,290.00 56,535.71 27,642.14 165,800.00 120,400.00 15,350.40 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71 10,948.91 120,400.00 137,300.00 30,708.60 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71 12,484.73 137,300.00 136,700.00 13,584.00 17,913.35 1,968.75 18,256.66 4,008.30 5,719.50 6,290.00 56,535.71 12,427.63 136,700.00 144,000.00 14,904.00 24,310.98
1,968.75 18,256.66 4,008.30 5,719.50 5,270.00 56,535.71 13,097.39 144,000.00 133,000.00 4,310.00 24,803.10 1,968.75 18,256.66 4,051.40 5,781.00 5,270.00 56,535.71 12,097.66 133,000.00 2,590.00 44,156.25 45,000.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 62,400.00 117,945.63 1,297,401.88 2,590.00 2,820.00 63,585.00 67,500.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00
124,800.00 104,000.00 128,378.50 1,412,163.50 2,820.00
330.00
aran pipa didekat galian. 191,600.00 100,000.00 50,000.00 33,300.00 18,745.00 393,645.00 330.00 363.00 363.00 396.00 396.00 462.00 462.00 561.00 561.00 693.00 693.00 858.00 858.00 1,023.00 1,023.00
750.00 100,000.00 38,300.00 75,000.00 37,500.00 5,067.00 12,540.00 268,407.00 750.00 787.50 787.50 937.50 937.50
1,312.50 1,312.50 1,500.00 1,500.00 1,800.00 1,800.00 2,062.50 2,062.50 2,250.00 2,250.00 26,900.00 7,576.80 708.75 8,924.67 2,542.90 3,628.50 330.00 750.00 2,446.16 26,900.00
26,800.00 29,000.00
7,847.40 831.80 10,170.73 2,645.26 3,774.56 363.00 787.50 2,642.02 29,000.00 34,300.00 10,012.20 964.69 11,674.08 2,973.90 4,243.50 396.00 937.50 3,120.19 34,300.00 40,300.00 10,553.40 1,107.42 15,492.71 3,196.94 4,561.76 462.00
1,312.50 3,668.67 40,300.00 41,000.00 10,661.64 1,167.27 15,492.71 3,273.66 4,671.23 561.00 1,500.00 3,732.75 41,000.00 44,800.00 10,824.00 1,260.00 18,028.27 3,361.80 4,797.00 693.00 1,800.00 4,076.41 44,800.00 54,500.00 13,530.00 1,968.75 22,272.14 3,652.73 5,212.13 858.00 2,062.50 4,955.62 54,500.00 57,000.00 14,071.20 2,129.40 23,649.29 3,737.63 5,333.28 858.00 2,062.50 5,184.13 57,000.00 62,100.00 16,531.20 2,835.00
23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 5,653.81 62,100.00 35,700.00 10,714.41 964.69 12,234.15 2,262.75 3,228.75 330.00 750.00 5,300.00 35,700.00 37,900.00 11,083.88 964.69 12,957.14 2,499.80 3,567.00 363.00 787.50 5,700.00 37,900.00 44,800.00 13,300.65 1,260.00 16,052.77 2,650.65 3,782.25 396.00 937.50 6,500.00 44,800.00 52,000.00 14,778.50 1,422.42 20,380.55 2,709.91 3,866.81 462.00 1,312.50 7,100.00 52,000.00
(13,800.00)
53,000.00 15,074.07 1,456.09 20,472.30 2,815.29 4,017.18 462.00 1,312.50 7,400.00 53,000.00 59,400.00 16,256.35 1,968.75 23,221.60 3,060.10 4,366.50 693.00 1,800.00 8,100.00 59,400.00 72,700.00 17,734.20 2,212.09 33,427.52 3,030.79 4,324.68 858.00 2,062.50 9,100.00 72,700.00
(20,700.00) 76,200.00
18,473.13 2,382.19 33,779.75 3,555.75 5,073.75 858.00 2,062.50 10,100.00 76,200.00
55,000.00 85,700.00
19,212.05 2,835.00 41,469.54 4,008.30 5,719.50
330.00 750.00 11,400.00 85,700.00
60,900.00 ok
34,000.00
14,665.33 492.19 6,164.35 2,542.90 3,628.50 330.00 750.00 5,500.00 34,000.00 36,300.00 15,009.81 492.19 7,250.84 2,661.43 3,797.63 363.00 787.50 6,000.00 36,300.00 42,300.00 17,913.35 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 6,700.00 42,300.00 48,300.00 19,685.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 7,500.00 48,300.00 51,000.00 21,653.50
708.75 10,740.16 3,348.87 4,778.55 561.00 1,500.00 7,800.00 51,000.00 58,200.00 21,968.46 1,594.69 15,619.99 3,469.55 4,950.75 693.00 1,800.00 8,200.00 58,200.00 69,200.00 27,992.07 1,968.75 18,256.66 4,051.40 5,781.00 858.00 2,062.50 8,250.00 69,200.00
28,740.10 2,048.29 19,285.15 4,222.94 6,025.77 858.00 2,062.50 16,759.33 80,000.00 88,900.00 31,692.85 2,835.00 23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 17,207.94
88,900.00
sisten Perencanaan engembangan Sarana dan na Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
19,685.00 964.69 10,673.97 3,210.95 4,581.75 170.00 23,000.00 40,000.00 102,200.00
21,653.50 708.75 10,740.16 3,348.87 4,778.55 170.00 24,000.00 57,500.00 122,800.00
an Prasarana Permukiman
ok
36,800.00 2,586.00 15,748.00 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 3,347.69 36,800.00 40,600.00 2,586.00 15,748.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 3,695.39 40,600.00 53,800.00 4,310.00 19,685.00 1,035.00 13,092.43 3,608.09 5,148.43 561.00 1,500.00 4,893.99 53,800.00 63,600.00 4,310.00 23,622.00 1,174.22 15,619.99 4,403.90 6,283.98 693.00 1,800.00 5,790.71 63,600.00 69,300.00
4,310.00 25,984.20 1,344.38 18,256.66 4,217.64 6,018.21 858.00 2,062.50 6,305.16 69,300.00 78,300.00 5,172.00 28,346.40 1,935.00 23,857.31 3,571.14 5,095.71 1,023.00 2,250.00 7,125.06 78,300.00 63,000.00 15,848.00 16,535.40 2,452.50 13,092.43 3,004.69 4,287.43 561.00 1,500.00 5,728.14 63,000.00 66,900.00 16,980.00 16,535.40 2,749.22 15,619.99 2,679.90 3,823.98 693.00 1,800.00 6,088.15 66,900.00 83,500.00 18,112.00 23,031.45 1,856.25
18,256.66 4,864.14 6,940.71 858.00 2,062.50 7,598.17 83,500.00 64,900.00 17,388.00 14,468.48 1,074.38 13,092.43 4,513.19 6,439.93 561.00 1,500.00 5,903.74 64,900.00 72,300.00 17,388.00 16,535.40 1,074.38 15,619.99 4,513.19 6,439.93 693.00 1,800.00 8,328.30 72,300.00 83,200.00 19,872.00 23,031.45 1,331.72 18,256.66 4,231.50 6,037.98 858.00 2,062.50 7,568.18 83,200.00 1,640.00 1,766.25 1,766.25 100,000.00 191,600.00 37,500.00
3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 74,858.25 823,440.75 1,640.00 1,650.00 3,974.06 3,974.06 100,000.00 191,600.00 37,500.00 3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 75,299.81 828,297.94 1,650.00 2,020.00 7,065.00 7,065.00 150,000.00 239,500.00 56,250.00 5,625.00 50,000.00 91,600.00 100,000.00 66,600.00 83,200.00 62,400.00 91,930.50 1,011,235.50 2,020.00 2,100.00 15,896.25 15,896.25
150,000.00 239,500.00 56,250.00 5,625.00 50,000.00 91,600.00 100,000.00 66,600.00 93,600.00 72,800.00 95,776.75 1,053,544.25 2,100.00 2,410.00 28,260.00 28,260.00 175,000.00 287,400.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 83,200.00 109,682.00 1,206,502.00 2,410.00 2,660.00 44,156.25 44,156.25 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 114,400.00 83,200.00 120,981.25 1,330,793.75 2,660.00 2,790.00
63,585.00 63,585.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 124,800.00 93,600.00 126,947.00 1,396,417.00 2,790.00 3,210.00 113,040.00 113,040.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 187,200.00 124,800.00 146,198.00 1,608,178.00 3,210.00
ANALISA PEKERJAAN No
Uraian Pekerjaan
Harga Satuan
Jumlah
F
PEKERJAAN PEMASANGAN PIPA BAJA
76
1 kg Pengangkutan pipa baja ke lokasi galian. 3000 kg Pekerjaan Pengangkutan GI ke lokasi pemasangan dan penjajaran pipa didekat galian. 2,976 kg = 6 btg (4m) Pipa GI diangkut Truk Jarak L < 10 Km 4.000 jam Plat Bed Truck 4 Ton 50,000.00 = Rp. 8.000 oh Pekerja 25,000.00 = Rp. 1.000 oh Sopir 50,000.00 = Rp. 1.000 oh Pembantu sopir 33,300.00 = Rp. 1.000 ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya angkut dan meletakkan 1 kg Pipa GI di dekat lobang galian. = Rp.
200,000.00 200,000.00 50,000.00 33,300.00 48,330.00 531,600.00 170.00
8 btg 15.000 6.000 1.000 1.200 96.00 8.00 6.000 1.000 6.000 2.000 0.020 1.000
Penyambungan Flange Pipa GI (4m), dengan Las Listrik 2 katoda. kg Kawat Las Listrik 11,100.00 jam Welding Mechine 500A 16,700.00 unit Bahan cairan spay uji las (2 tube) 149,900.00 kg Coltar primer anti karat 12,900.00 bh Baut baja , Mur , Ring 4,000.00 bh Packing Loose Flange 7,500.00 oh Pekerja 25,000.00 oh Tukang pipa 37,500.00 oh Operator semi terampil 45,800.00 oh Tukang las 50,000.00 oh Mandor 37,500.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) 1 Meter Penyambungan pipa GI dengan flange
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
166,500.00 100,200.00 149,900.00 15,480.00 384,000.00 60,000.00 150,000.00 37,500.00 274,800.00 100,000.00 750.00 143,913.00 1,583,000.00 32,900.00
77 78
1 M' 1 M'
Penyambungan Pipa Las Flange Pipa Dia. 250 mm ( prestasi 8 btg ) Penyambungan Pipa Las Flange Pipa Dia. 300 mm ( prestasi 7 btg )
= Rp. = Rp.
49,468.75 56,535.71
79
1 M' 31.00 1.000 1.000
Pemasangan Pipa GI ND. 250 mm, diatas tumpuan kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 49,468.75 = Rp. = Rp. = Rp.
5,270.00 49,468.75 5,473.88 60,200.00
1 M' 36.00 1.000 1.000
Pemasangan Pipa GI ND. 300 mm, diatas tumpuan kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
170.00 = Rp. 56,535.71 = Rp. = Rp. = Rp.
6,120.00 56,535.71 6,265.57 68,900.00
1 M' 0.720 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan GI Dia. 250 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.720 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
80
81
82
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,169.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 9,694.91 106,600.00
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
28,346.40 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 13,001.73 124,100.00
No 83
84
85
86
87
88
Uraian Pekerjaan Harga Satuan Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas III. m2 Bongkaran perkerasan jalan kelas III (40 cm) 22,640.00 m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 m1 Penyambungan dan pengelasan pipa. 49,468.75 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,300.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 15,337.13 133,300.00
1 M' 0.720 0.480 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, dibawah jalan Kelas I. m2 Bongkaran perkerasan jalan kelas I (15 cm) m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,884.80 18,897.60 1,594.69 15,619.99 4,460.85 6,365.25 5,270.00 49,468.75 11,956.19 131,500.00
1 M' 0.720 0.600 0.203 0.153 0.458 0.458 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 250 mm, dibawah Paving Block. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 49,468.75
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
3,103.20 23,622.00 1,594.69 15,619.99 3,943.65 5,627.25 5,270.00 49,468.75 10,824.95 119,000.00
1 M' 0.780 0.70 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, didasar sungai berbatu. m3 Galian dasar sungai berbatu m3 Pasangan batu kosong (bahan setempat) kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
71,250.00 28,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
55,575.00 19,810.00 6,290.00 56,535.71 27,642.14 165,800.00
1 M' 0.780 0.250 0.179 0.530 0.530 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,350.40 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71 10,948.91 120,400.00
1 M' 0.780 0.250 0.179 0.530 0.530 37.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
30,708.60 1,968.75 18,256.66 4,568.60 6,519.00 6,290.00 56,535.71 12,484.73 137,300.00
1 M' 0.720 0.480 0.203 0.153 0.518 0.518 31.00 1.000 1.000
Jumlah
No 89
90
91
92
93
Uraian Pekerjaan Harga Satuan Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III 22,640.00 m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan kembali 8,620.00 m3 Pemadatan tanah dengan alat 12,300.00 kg Pengangkutan pipa baja ke lokasi galian. 170.00 m1 Penyambungan dan pengelasan pipa. 56,535.71 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,584.00 17,913.35 1,968.75 18,256.66 4,008.30 5,719.50 6,290.00 56,535.71 12,427.63 136,700.00
1 M' 0.600 0.618 0.250 0.179 0.465 0.465 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,904.00 24,310.98 1,968.75 18,256.66 4,008.30 5,719.50 5,270.00 56,535.71 13,097.39 144,000.00
1 M' 1.000 0.630 0.250 0.179 0.470 0.470 31.00 1.000 1.000
Pemasangan Pipa GI Dia. 300 mm, dibawah Paving Block. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 56,535.71
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 24,803.10 1,968.75 18,256.66 4,051.40 5,781.00 5,270.00 56,535.71 12,097.66 133,000.00
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 250 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 3.000 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 10.000 jam Water Pump (Dia. 5 cm) 10,400.00 6.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
44,156.25 45,000.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 62,400.00 117,945.63 1,297,401.88 2,590.00
1 M' Pengetesan Tekanan dan Kebocoran, Pipa Steel Dia. 300 mm. 500 m Pekerjaan Pengetesan dan Desinfektan Pipa Pipa Steel Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 4.500 kg Kaporit 15,000.00 6.000 oh Pekerja 25,000.00 8.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 12.000 jam Water Pump (Dia. 5 cm) 10,400.00 10.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan) Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
63,585.00 67,500.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 124,800.00 104,000.00 128,378.50 1,412,163.50 2,820.00
1 M' 0.600 0.455 0.250 0.179 0.465 0.465 37.00 1.000 1.000
Jumlah
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No G
Uraian Pekerjaan PEKERJAAN PEMASANGAN PIPA PVC
94
1 M' Pengangkutan dan penjajaran Pipa PVC Dia. 50 mm 200 btg Pengangkutan Pipa PVC Dia. 300 mm ke lokasi pemasangan dan penjajaran pipa didekat galian. 1,200 m (dianggap 1 batang pipa PVC, panjang = 6 m) 4.000 jam Pickup Truck 47,900.00 = Rp. 191,600.00 4.000 oh Pekerja 25,000.00 = Rp. 100,000.00 1.000 oh Sopir 50,000.00 = Rp. 50,000.00 1.000 oh Pembantu sopir 33,300.00 = Rp. 33,300.00 1.000 ls Alat bantu = Rp. 18,745.00 Jumlah ( Dibulatkan dalam ratusan) = Rp. 393,645.00 Biaya angkut dan meletakkan 1 kg Pipa PVC di dekat lobang galian. = Rp. 330.00
95 96 97 98 99 100 101
102
103 104 105 106 107 108 109
1 M' 110 1 M' 120 1 M' 140 1 M' 170 1 M' 210 1 M' 260 1 M' 310
Pengangkutan dan penjajaran Pipa PVC Dia. 75 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 100 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 150 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 200 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 250 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 300 mm % Analisa F.48 Pengangkutan dan penjajaran Pipa PVC Dia. 400 mm % Analisa F.48
Harga Satuan
Jumlah
330.00 = Rp.
363.00
330.00 = Rp.
396.00
330.00 = Rp.
462.00
330.00 = Rp.
561.00
330.00 = Rp.
693.00
330.00 = Rp.
858.00
330.00 = Rp.
1,023.00
1 M' 360 4.000 1.000 2.000 1.000 0.100 1.000
Penyambungan pipa PVC Dia. 50 mm didalam galian m Prestasi penyambungan dalam 1 hari, tidak termasuk bahan penyambung. oh Pekerja 25,000.00 = Rp. oh Tukang batu semi terampil 38,300.00 = Rp. oh Tukang pipa 37,500.00 = Rp. oh Mandor 37,500.00 = Rp. An Pemasangan turap kayu pengaman galian 1.5 m 50,670.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp. Biaya Penyambungan per 1 m panjang Pipa. = Rp.
100,000.00 38,300.00 75,000.00 37,500.00 5,067.00 12,540.00 268,407.00 750.00
1 M' 105 1 M' 125 1 M' 175 1 M' 200 1 M' 240 1 M' 275 1 M' 300
Penyambungan pipa PVC Dia. 75 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 100 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 150 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 200 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 250 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 300 mm didalam galian % Analisa F.50 Penyambungan pipa PVC Dia. 400 mm didalam galian % Analisa F.50
750.00 = Rp.
787.50
750.00 = Rp.
937.50
750.00 = Rp.
1,312.50
750.00 = Rp.
1,500.00
750.00 = Rp.
1,800.00
750.00 = Rp.
2,062.50
750.00 = Rp.
2,250.00
No 110
111
112
113
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 50 mm, Galian tanah biasa. m3 Galian tanah biasa 19,680.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan kembali 8,620.00 m3 Pemadatan tanah dengan alat 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,576.80 708.75 8,924.67 2,542.90 3,628.50 330.00 750.00 2,446.16 26,900.00
1 M' 0.399 0.106 0.100 0.307 0.307 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,847.40 831.80 10,170.73 2,645.26 3,774.56 363.00 787.50 2,642.02 29,000.00
1 M' 0.509 0.123 0.115 0.345 0.345 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,012.20 964.69 11,674.08 2,973.90 4,243.50 396.00 937.50 3,120.19 34,300.00
1 M' 0.536 0.141 0.152 0.371 0.371 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,553.40 1,107.42 15,492.71 3,196.94 4,561.76 462.00 1,312.50 3,668.67 40,300.00
1 M' 0.385 0.090 0.088 0.295 0.295 1.00 1.00 1.00
Jumlah
No 114
115
116
117
118
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 200 mm, Galian tanah biasa. m3 Galian tanah biasa 19,680.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan kembali 8,620.00 m3 Pemadatan tanah dengan alat 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,661.64 1,167.27 15,492.71 3,273.66 4,671.23 561.00 1,500.00 3,732.75 41,000.00
1 M' 0.550 0.160 0.177 0.390 0.390 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,824.00 1,260.00 18,028.27 3,361.80 4,797.00 693.00 1,800.00 4,076.41 44,800.00
1 M' 0.688 0.250 0.219 0.424 0.424 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,530.00 1,968.75 22,272.14 3,652.73 5,212.13 858.00 2,062.50 4,955.62 54,500.00
1 M' 0.715 0.270 0.232 0.434 0.434 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,071.20 2,129.40 23,649.29 3,737.63 5,333.28 858.00 2,062.50 5,184.13 57,000.00
1 M' 0.840 0.360 0.234 0.480 0.480 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah biasa. m3 Galian tanah biasa m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm m1 Penyambungan pipa PVC Dia. 400 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
19,680.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,531.20 2,835.00 23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 5,653.81 62,100.00
1 M' 0.542 0.148 0.152 0.380 0.380 1.00 1.00 1.00
Jumlah
No 119
120
1 M' 0.399 0.123 0.120 0.263 0.263 1.00 1.00 1.00
1 M' 0.413 0.123 0.127 0.290 0.290 1.00 1.00 1.00
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 50 mm, Galian tanah keras m3 Galian tanah keras 26,870.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
10,714.41 964.69 12,234.15 2,262.75 3,228.75 330.00 750.00 5,300.00 35,700.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah keras m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
11,083.88 964.69 12,957.14 2,499.80 3,567.00 363.00 787.50 5,700.00 37,900.00
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
Jumlah
No 121
122
123
124
125
126
127
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 100 mm, Galian tanah keras. m3 Galian tanah keras 26,870.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
13,300.65 1,260.00 16,052.77 2,650.65 3,782.25 396.00 937.50 6,500.00 44,800.00
1 M' 0.550 0.181 0.200 0.314 0.314 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,778.50 1,422.42 20,380.55 2,709.91 3,866.81 462.00 1,312.50 7,100.00 52,000.00
1 M' 0.561 0.185 0.201 0.327 0.327 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,074.07 1,456.09 20,472.30 2,815.29 4,017.18 462.00 1,312.50 7,400.00 53,000.00
1 M' 0.605 0.250 0.228 0.355 0.355 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
16,256.35 1,968.75 23,221.60 3,060.10 4,366.50 693.00 1,800.00 8,100.00 59,400.00
1 M' 0.660 0.281 0.328 0.352 0.352 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,734.20 2,212.09 33,427.52 3,030.79 4,324.68 858.00 2,062.50 9,100.00 72,700.00
1 M' 0.688 0.303 0.332 0.413 0.413 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah keras. m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
26,870.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
18,473.13 2,382.19 33,779.75 3,555.75 5,073.75 858.00 2,062.50 10,100.00 76,200.00
1 M' 0.715 0.360 0.407 0.465
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah keras m3 Galian tanah keras m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali
26,870.00 7,875.00 101,830.00 8,620.00
= Rp. = Rp. = Rp. = Rp.
19,212.05 2,835.00 41,469.54 4,008.30
1 M' 0.495 0.160 0.158 0.308 0.308 1.00 1.00 1.00
Jumlah
No 0.465 1.00 1.000 1.000
m3 m1 m1 ls
Uraian Pekerjaan Harga Satuan Pemadatan tanah perlapis 25 cm 12,300.00 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 Alat bantu Jumlah
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp.
5,719.50 330.00 750.00 11,400.00 85,700.00
No 128
129
130
131
132
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 50 mm, Galian tanah berbatu m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 50 mm 330.00 m1 Penyambungan pipa PVC Dia. 50 mm didalam galian 750.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
14,665.33 492.19 6,164.35 2,542.90 3,628.50 330.00 750.00 5,500.00 34,000.00
1 M' 0.381 0.063 0.071 0.309 0.309 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 75 mm, Galian tanah berbatu m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 75 mm m1 Penyambungan pipa PVC Dia. 75 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 363.00 787.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,009.81 492.19 7,250.84 2,661.43 3,797.63 363.00 787.50 6,000.00 36,300.00
1 M' 0.455 0.090 0.082 0.350 0.350 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 100 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm m1 Penyambungan pipa PVC Dia. 100 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 396.00 937.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,913.35 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 6,700.00 42,300.00
1 M' 0.500 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,685.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 7,500.00 48,300.00
1 M' 0.550 0.090 0.105 0.389 0.389 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,653.50 708.75 10,740.16 3,348.87 4,778.55 561.00 1,500.00 7,800.00 51,000.00
1 M' 0.373 0.063 0.061 0.295 0.295 1.00 1.00 1.00
Jumlah ok
No 133
134
135
135
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 250 mm, Galian tanah berbatu. m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,968.46 1,594.69 15,619.99 3,469.55 4,950.75 693.00 1,800.00 8,200.00 58,200.00
1 M' 0.711 0.250 0.179 0.470 0.470 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
27,992.07 1,968.75 18,256.66 4,051.40 5,781.00 858.00 2,062.50 8,250.00 69,200.00
1 M' 0.730 0.260 0.189 0.490 0.490 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 350 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
28,740.10 2,048.29 19,285.15 4,222.94 6,025.77 858.00 2,062.50 16,759.33 80,000.00
1 M' 0.805 0.360 0.234 0.480 0.480 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 400 mm, Galian tanah berbatu m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm m1 Penyambungan pipa PVC Dia. 400 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
31,692.85 2,835.00 23,857.31 4,137.60 5,904.00 1,023.00 2,250.00 17,207.94 88,900.00
1 M' 0.558 0.203 0.153 0.403 0.403 1.00 1.00 1.00
Jumlah
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
1 M' 0.500 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa GI Dia. 150 mm, Galian tanah berbatu. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm kg Pengangkutan pipa baja ke lokasi galian. m1 Penyambungan dan pengelasan pipa. ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M'
Pemasangan Pipa GI Dia. 200 mm, Galian tanah berbatu.
39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 23,000.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,685.00 964.69 10,673.97 3,210.95 4,581.75 170.00 23,000.00 40,000.00 102,200.00
No 0.550 0.090 0.105 0.389 0.389 1.00 1.00 1.00
m3 m3 m3 m3 m3 kg m1 ls
Uraian Pekerjaan Galian tanah berbatu Buangan tanah disekitar lokasi Urugan Pasir dipadatkan Urugan tanah kembali Pemadatan tanah perlapis 25 cm Pengangkutan pipa baja ke lokasi galian. Penyambungan dan pengelasan pipa. Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Harga Satuan 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 170.00 24,000.00
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
21,653.50 708.75 10,740.16 3,348.87 4,778.55 170.00 24,000.00 57,500.00 122,800.00
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
No 136
137
138
139
140
141
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 100 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. 4,310.00 m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan tanah kembali 8,620.00 m3 Pemadatan tanah perlapis 25 cm 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 100 mm 396.00 m1 Penyambungan pipa PVC Dia. 100 mm didalam galian 937.50 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,586.00 15,748.00 708.75 8,364.61 3,017.00 4,305.00 396.00 937.50 3,347.69 36,800.00
1 M' 0.600 0.400 0.123 0.105 0.373 0.373 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 150 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan tanah kembali m3 Pemadatan tanah perlapis 25 cm m1 Pengangkutan dan penjajaran pipa PVC Dia. 150 mm m1 Penyambungan pipa PVC Dia. 150 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 462.00 1,312.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,586.00 15,748.00 964.69 10,673.97 3,210.95 4,581.75 462.00 1,312.50 3,695.39 40,600.00
1 M' 1.000 0.500 0.131 0.129 0.419 0.419 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 19,685.00 1,035.00 13,092.43 3,608.09 5,148.43 561.00 1,500.00 4,893.99 53,800.00
1 M' 1.000 0.600 0.149 0.153 0.511 0.511 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah Trotoar. m2 Bongkaran Perkerasan Paving Block tebal 8 cm. m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 23,622.00 1,174.22 15,619.99 4,403.90 6,283.98 693.00 1,800.00 5,790.71 63,600.00
1 M' 1.000 0.660 0.171 0.179 0.489 0.489 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, dibawah Trotoar. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
4,310.00 25,984.20 1,344.38 18,256.66 4,217.64 6,018.21 858.00 2,062.50 6,305.16 69,300.00
1 M' 1.200 0.720 0.246 0.234 0.414 0.414 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 400 mm, dibawah Trotoar. m2 Bongkaran Paving Block tebal 8 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 400 mm m1 Penyambungan pipa PVC Dia. 400 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
4,310.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 1,023.00 2,250.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
5,172.00 28,346.40 1,935.00 23,857.31 3,571.14 5,095.71 1,023.00 2,250.00 7,125.06 78,300.00
1 M' 0.600 0.400 0.090 0.082 0.350 0.350 1.00 1.00 1.00
Jumlah
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No 142
143
144
145
146
147
1 M' 0.700 0.420 0.311 0.129 0.349 0.349 1.00 1.00 1.00
Uraian Pekerjaan Harga Satuan Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 m3 Galian tanah berbatu 39,370.00 m3 Buangan tanah disekitar lokasi 7,875.00 m3 Urugan Pasir dipadatkan 101,830.00 m3 Urugan kembali 8,620.00 m3 Pemadatan tanah dengan alat 12,300.00 m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm 561.00 m1 Penyambungan pipa PVC Dia. 200 mm didalam galian 1,500.00 ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
Jumlah = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,848.00 16,535.40 2,452.50 13,092.43 3,004.69 4,287.43 561.00 1,500.00 5,728.14 63,000.00
1 M' 0.750 0.420 0.349 0.153 0.311 0.311 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III tebal 40 cm 22,640.00 = Rp. m3 Galian tanah berbatu 39,370.00 = Rp. m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. m3 Urugan Pasir dipadatkan 101,830.00 = Rp. m3 Urugan kembali 8,620.00 = Rp. m3 Pemadatan tanah dengan alat 12,300.00 = Rp. m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm 693.00 = Rp. m1 Penyambungan pipa PVC Dia. 250 mm didalam galian 1,800.00 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
16,980.00 16,535.40 2,749.22 15,619.99 2,679.90 3,823.98 693.00 1,800.00 6,088.15 66,900.00
1 M' 0.800 0.585 0.236 0.179 0.564 0.564 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas III. m2 Bongkaran jalan Kelas III 22,640.00 = Rp. m3 Galian tanah berbatu 39,370.00 = Rp. m3 Buangan tanah disekitar lokasi 7,875.00 = Rp. m3 Urugan Pasir dipadatkan 101,830.00 = Rp. m3 Urugan kembali 8,620.00 = Rp. m3 Pemadatan tanah dengan alat 12,300.00 = Rp. m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm 858.00 = Rp. m1 Penyambungan pipa PVC Dia. 300 mm didalam galian 2,062.50 = Rp. ls Alat bantu = Rp. Jumlah ( Dibulatkan dalam ratusan) = Rp.
18,112.00 23,031.45 1,856.25 18,256.66 4,864.14 6,940.71 858.00 2,062.50 7,598.17 83,500.00
1 M' 0.700 0.368 0.136 0.129 0.524 0.524 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 200 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 200 mm m1 Penyambungan pipa PVC Dia. 200 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.700 0.420 0.136 0.153 0.524 0.524 1.00 1.00 1.00
Pemasangan Pipa PVC Dia. 250 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 250 mm m1 Penyambungan pipa PVC Dia. 250 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
1 M' 0.800 0.585 0.169 0.179 0.491 0.491 1.00 1.000 1.000
Pemasangan Pipa PVC Dia. 300 mm, dibawah jalan Kelas I. m2 Bongkaran jalan Kelas I tebal 15 cm m3 Galian tanah berbatu m3 Buangan tanah disekitar lokasi m3 Urugan Pasir dipadatkan m3 Urugan kembali m3 Pemadatan tanah dengan alat m1 Pengangkutan dan penjajaran pipa PVC Dia. 300 mm m1 Penyambungan pipa PVC Dia. 300 mm didalam galian ls Alat bantu Jumlah ( Dibulatkan dalam ratusan)
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 561.00 1,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,388.00 14,468.48 1,074.38 13,092.43 4,513.19 6,439.93 561.00 1,500.00 5,903.74 64,900.00
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 693.00 1,800.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
17,388.00 16,535.40 1,074.38 15,619.99 4,513.19 6,439.93 693.00 1,800.00 8,328.30 72,300.00
24,840.00 39,370.00 7,875.00 101,830.00 8,620.00 12,300.00 858.00 2,062.50
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,872.00 23,031.45 1,331.72 18,256.66 4,231.50 6,037.98 858.00 2,062.50 7,568.18 83,200.00
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No 148
149
150
151
Uraian Pekerjaan Harga Satuan 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 50 mm. 2.94 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 0.118 kg Kaporit 15,000.00 4.000 oh Pekerja 25,000.00 4.000 jam Pickup Truck 47,900.00 1.000 oh Tukang pipa 37,500.00 0.100 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 6.000 jam Water Pump (Dia. 5 cm) 10,400.00 4.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,766.25 1,766.25 100,000.00 191,600.00 37,500.00 3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 74,858.25 823,440.75 1,640.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 75 mm. 6.62 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.265 kg Kaporit 4.000 oh Pekerja 4.000 jam Pickup Truck 1.000 oh Tukang pipa 0.100 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 6.000 jam Water Pump (Dia. 5 cm) 4.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
3,974.06 3,974.06 100,000.00 191,600.00 37,500.00 3,750.00 50,000.00 91,600.00 100,000.00 66,600.00 62,400.00 41,600.00 75,299.81 828,297.94 1,650.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
7,065.00 7,065.00 150,000.00 239,500.00 56,250.00 5,625.00 50,000.00 91,600.00 100,000.00 66,600.00 83,200.00 62,400.00 91,930.50 1,011,235.50 2,020.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
15,896.25 15,896.25 150,000.00 239,500.00 56,250.00 5,625.00 50,000.00 91,600.00 100,000.00 66,600.00 93,600.00 72,800.00 95,776.75 1,053,544.25 2,100.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 100 mm. 11.78 m3 Pengadaan air pengujian dan pembersihan/flushing. 0.471 kg Kaporit 6.000 oh Pekerja 5.000 jam Pickup Truck 1.500 oh Tukang pipa 0.150 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 8.000 jam Water Pump (Dia. 5 cm) 6.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 150 mm. 26.49 m3 Pengadaan air pengujian dan pembersihan/flushing. 1.060 kg Kaporit 6.000 oh Pekerja 5.000 jam Pickup Truck 1.500 oh Tukang pipa 0.150 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 9.000 jam Water Pump (Dia. 5 cm) 7.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
Jumlah
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No 152
153
154
155
Uraian Pekerjaan Harga Satuan 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 200 mm. 47.10 m3 Pengadaan air pengujian dan pembersihan/flushing. 600.00 1.884 kg Kaporit 15,000.00 7.000 oh Pekerja 25,000.00 6.000 jam Pickup Truck 47,900.00 2.000 oh Tukang pipa 37,500.00 0.200 oh Mandor 37,500.00 1.000 oh Sopir 50,000.00 2.000 oh Operator semi terampil 45,800.00 2.000 oh Pembantu operator 50,000.00 2.000 oh Pembantu sopir 33,300.00 10.000 jam Water Pump (Dia. 5 cm) 10,400.00 8.000 jam Pressure Pump 20 Bar 10,400.00 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
28,260.00 28,260.00 175,000.00 287,400.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 104,000.00 83,200.00 109,682.00 1,206,502.00 2,410.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 250 mm. 73.59 m3 Pengadaan air pengujian dan pembersihan/flushing. 2.944 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 11.000 jam Water Pump (Dia. 5 cm) 8.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
44,156.25 44,156.25 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 114,400.00 83,200.00 120,981.25 1,330,793.75 2,660.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
63,585.00 63,585.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 124,800.00 93,600.00 126,947.00 1,396,417.00 2,790.00
600.00 15,000.00 25,000.00 47,900.00 37,500.00 37,500.00 50,000.00 45,800.00 50,000.00 33,300.00 10,400.00 10,400.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
113,040.00 113,040.00 150,000.00 383,200.00 75,000.00 7,500.00 50,000.00 91,600.00 100,000.00 66,600.00 187,200.00 124,800.00 146,198.00 1,608,178.00 3,210.00
1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 300 mm. 105.98 m3 Pengadaan air pengujian dan pembersihan/flushing. 4.239 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 12.000 jam Water Pump (Dia. 5 cm) 9.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang 1 M' Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 500 m Pengetesan Tekanan dan kebocoran Pipa PVC Dia. 400 mm. 188.40 m3 Pengadaan air pengujian dan pembersihan/flushing. 7.536 kg Kaporit 6.000 oh Pekerja 8.000 jam Pickup Truck 2.000 oh Tukang pipa 0.200 oh Mandor 1.000 oh Sopir 2.000 oh Operator semi terampil 2.000 oh Pembantu operator 2.000 oh Pembantu sopir 18.000 jam Water Pump (Dia. 5 cm) 12.000 jam Pressure Pump 20 Bar 1.000 ls Alat bantu Jumlah Biaya Pengetesan per 1m panjang
Jumlah
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No
Uraian Pekerjaan
H
PEKERJAAN PERKERASAN JALAN Pemadatan 1M2 Pemadatan tanah dasar menggunakan Stamper 0.100 jam Plate Vibrator Tamper 0.100 oh Operator semi terampil 0.010 oh Mandor 1.000 m2 Penyiraman Jumlah
156
157
158
159
160
Harga Satuan
1M2 Pemadatan standart Bina Marga menggunakan alat berat 0.012 jam Tree Wheel Roller 51 HP 0.012 oh Operator terampil 0.001 oh Mandor 1.000 m2 Penyiraman Jumlah 1 M2 Lapis Resap Pengikat (Prime Coat), 0,8 lt/m2. 200.00 m2 Prime Coat dihampar manual : 129 kg Aspal 37 ltr Minyak tanah 6.00 oh Pekerja 0.20 oh Mandor 0.50 m3 Kayu bakar 5.00 ltr Minyak bakar ah Alat bantu Jumlah Konstruksi Jalan 1 M2 Lapis Pondasi bawah Onderlaght, tebal 15 cm. 150.00 m2 Lapisan LPB dengan tebal 15 cm, dihampar manual. 29.70 m3 Kerikil sungai tidak disaring 1.00 oh Mandor 22.00 oh Pekerja 2.00 oh Operator semi terampil 2.00 oh Pembantu operator 6.00 jam Vibro Roller 600 Kg 1.000 ls Alat bantu Jumlah 1 M2 Lapis Pondasi bawah steinslaght Kelas C, tebal 15 cm.
1 M2 Lapis Pondasi bawah onderlaght, tebal 30 cm. 150.00 m2 Lapisan LPB dengan tebal 15 cm, dihampar manual. 59.40 m3 Kerikil sungai tidak disaring 1.00 oh Mandor
4,200.00 45,800.00 37,500.00
21,900.00 50,000.00 37,500.00
5,800.00 1,700.00 25,000.00 37,500.00 82,500.00 2,400.00
75,000.00 37,500.00 25,000.00 45,800.00 50,000.00 15,600.00
75,000.00 37,500.00
22.00 oh Pekerja 2.00 oh Operator semi terampil 2.00 oh Pembantu operator 6.00 jam Tree Wheel Roller 51 HP 1.000 ls Alat bantu Jumlah 1 M2 Lapis Pondasi bawah steinslaght Kelas C, tebal 30 cm.
161
1 M2 150.00 15.84 3.96 1.00 20.00 2.00 2.00 7.00 1.000 1 M2
Lapis Pondasi Atas Steinslaght , tebal 7 cm. m2 Lapisan LPA dengan tebal 10 cm, dihampar manual. m3 Batu pecah 2 - 3 m3 Batu pecah 1 - 2 oh Mandor oh Pekerja oh Operator semi terampil oh Pembantu operator jam Vibro Roller 600 Kg ls Alat bantu Jumlah Lapis Pondasi Atas steinslaght Kelas A, tebal 7 cm.
25,000.00 45,800.00 50,000.00 21,900.00
136,600.00 136,600.00 37,500.00 25,000.00 45,800.00 50,000.00 15,600.00
162
1 M2 Lapis Perkerasan Macadam, tebal 5 cm. 180.00 m2 Lapisan Perkerasan Macadam tebal 5 cm, dihampar manual. 7.58 m3 Batu pecah 2 - 3 136,600.00 2.39 m3 Batu pecah 1 - 2 136,600.00 1.36 m3 Batu pecah 0,5 - 1 108,300.00 0.38 m3 Pasir beton 133,300.00 600 m2 Prime Coat (3 x tabur) 5,193.02 2.00 m3 Kayu bakar 82,500.00 5.00 ltr Minyak bakar 2,400.00 24.00 oh Pekerja 25,000.00 1.00 oh Mandor 37,500.00 1.00 oh Sopir 50,000.00 1.00 oh Operator terampil 50,000.00 1.00 oh Pembantu operator 50,000.00 6.00 jam Tree Wheel Roller 51 HP 21,900.00 5.00 jam Pickup Truck 47,900.00 1.00 ls Alat bantu Jumlah 1 M2 Lapis Perkerasan Macadam, tebal 5 cm.
163
1 M2 Lapis PENETRASI , tebal 3 cm. 250.00 m2 Lapisan latasir tebal 3 cm padat, dihampar manual. 6.38 m3 Pasir beton 1.69 m3 Abu batu/Filler 563 kg Aspal 5.00 m3 Kayu bakar 10.00 ltr Minyak bakar 28.00 oh Pekerja 1.00 oh Mandor
133,300.00 139,900.00 5,800.00 82,500.00 2,400.00 25,000.00 37,500.00
1.00 1.00 1.00 6.00 4.00 1.00 1 M2
oh oh oh jam jam ls
Sopir Operator terampil Pembantu operator Tree Wheel Roller 51 HP Pickup Truck Alat bantu Jumlah Lapis LATASIR, tebal 3 cm.
50,000.00 50,000.00 50,000.00 21,900.00 47,900.00
Assisten Perencanaa Proyek Pengembangan Sarana dan Pra Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
164
165
1 M2 Perbaikan Perkerasan jalan kelas III 1.00 m2 Lapir LPB, steinslaght kelas C, Analisa 76 1.00 m2 Lapis Penetrasi Macadam tebal 5 cm
20,970.00 33,558.13
1 M2 Perbaikan Perkerasan jalan kelas I 1.00 m2 Lapir LPB, steinslaght kelas C, Analisa 76 1.00 m2 Lapir LPA, steinslaght kelas A, Analisa 76 1.00 m2 LATASIR tebal 3 cm
20,970.00 23,985.49 24,101.38
166
1 M2 Pemasangan kembali Paving Block (30% rusak diganti baru) 0.30 m2 Paving Block natural 8 cm 65,800.00 0.05 m3 Pasir pasang 116,600.00 0.10 oh Pekerja 25,000.00 0.05 oh Tukang batu 38,300.00 0.00 oh Mandor 37,500.00 0.01 oh Operator terampil 50,000.00 1.00 ls Alat bantu Jumlah
167 168 169 170
1 M2 1 M2 1 M2 1 M2
171
1 M2 Jalan inspeksi, beton rabat tebal 10 cm 1.20 m2 Pemadatan tanah dasar 0.12 m3 Pasir urug dipadatkan
Perbaikan paving blok, pemasangan pipa dia. 400 mm Perbaikan paving blok, pemasangan pipa dia. 300 mm Perbaikan paving blok, pemasangan pipa dia. 250 mm Perbaikan paving blok, pemasangan pipa dia. 200 mm
(1,0 m/m1) (0.90 m/m1) (0.80 m/m1) (0.70 m/m1)
5,643.75 101,830.00
0.11 0.20 0.05 0.01 0.01 1.00
m3 m3 oh oh oh ls
Beton K125 Pekerja Tukang batu Mandor Operator terampil Alat bantu Jumlah
594,330.00 25,000.00 38,300.00 37,500.00 50,000.00
172
1 M2 Perbaikan Perkerasan jalan kelas III, pemasangan pipa dia. 200 mm 0.60 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00 0.60 m2 Lapis Penetrasi Macadam tebal 5 cm 33,558.13
173
1 M2 Perbaikan Perkerasan jalan kelas I, pemasangan pipa dia. 200 mm 0.60 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00 0.60 m2 Lapir LPA, Sub Base kelas A, Analisa 76 23,985.49 0.60 m2 LATASIR tebal 3 cm 24,101.38
174
1 M2 Perbaikan Perkerasan jalan kelas I, pemasangan pipa dia. 250 mm 0.65 m2 Lapir LPB, steinslaght kelas C, Analisa 76 20,970.00 0.65 m2 Lapir LPA, Sub Base kelas A, Analisa 76 23,985.49 0.65 m2 LATASIR tebal 3 cm 24,101.38
Assisten Perencanaa Proyek Pengembangan Sarana dan Pra Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
1 M'
Pekerjaan Saluran 0.210 m3 Galian tanah
19,680.00
0.210 m3 Buang tanah galian
7,875.00
0.190 m3 Pasangan batu kali 1:4 0.551 m2 Siaran 1:4 0.600 m2 Plesteran 1:4 1 ls Perapihan
480,990.00 27,380.00 27,200.00 500.00
Jumlah Dibulatkan No
Uraian Pekerjaan 1 M' 3.00 3.00 3.00 1.00
Harga Satuan
Pekerjaan Jalan Penetrasi Lebar Perkerasan 3.00 meter meter meter meter ls
Lapisan pondasi atas Stenslagh t =7 cm Lapisan resap pengikat ( Prime Coate ) Lapisan Penetrasi t=3 cm Perapihan
= Rp. = Rp. = Rp. = Rp.
23,985.49 5,193.02 24,101.38 1,000.00
Jumlah Dibulatkan No
Uraian Pekerjaan 1 M' 3.50 3.50 3.50 3.50 1.00
Harga Satuan
Pekerjaan Jalan Penetrasi Lebar Perkerasan 3.50 meter meter meter meter meter ls
Pecing Onderlagh 80 % Lapisan pondasi atas Stenslagh t =7 cm Lapisan resap pengikat ( Prime Coate ) Lapisan Penetrasi t=3 cm Perapihan
= Rp. = Rp. = Rp. = Rp. = Rp.
30,549.96 23,985.49 5,193.02 24,101.38 3,300.00
Jumlah Dibulatkan No
Uraian Pekerjaan 1 M' 4.00 4.00 4.00 4.00 1.00
Harga Satuan
Pekerjaan Jalan Penetrasi Lebar Perkerasan 4.00 meter meter meter meter meter ls
Lapisan Pondasi Bawah Onderlagh 15 Cm Lapisan pondasi atas Stenslagh t =7 cm Lapisan resap pengikat ( Prime Coate ) Lapisan Penetrasi t=3 cm Perapihan
= Rp. = Rp. = Rp. = Rp. = Rp.
20,970.00 23,985.49 5,193.02 24,101.38 6,800.00
Jumlah Dibulatkan
1 M'
Pekerjaan Saluran 0.210 m3 Galian tanah
19,680.00
0.210 m3 Buang tanah galian
7,875.00
0.190 m3 Pasangan batu kali 1:4 0.551 m2 Siaran 1:4 0.600 m2 Plesteran 1:4 1 ls Perapihan
480,990.00 27,380.00 27,200.00 5,225.00
Jumlah Dibulatkan
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Pe Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
Jumlah
5,643.75 = Rp. = Rp. = Rp. = Rp. = Rp.
420.00 4,580.00 375.00 268.75 5,643.75
= Rp. = Rp. = Rp. = Rp. = Rp.
262.80 600.00 37.50 150.00 1,050.30
1,050.30
5,193.02 = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
750,288.00 62,560.00 150,000.00 7,500.00 41,250.00 12,000.00 15,005.76 1,038,603.76 5,193.02 20,970.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,227,500.00 37,500.00 550,000.00 91,600.00 100,000.00 93,600.00 45,300.00 3,145,500.00 20,970.00
36,369.00 = Rp. = Rp.
4,455,000.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
550,000.00 91,600.00 100,000.00 131,400.00 89,850.00 5,455,350.00 36,369.00
23,985.49 = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
2,163,744.00 540,936.00 37,500.00 500,000.00 91,600.00 100,000.00 109,200.00 54,843.60 3,597,823.60 23,985.49 33,558.13
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
1,035,646.56 326,036.88 146,984.76 50,531.36 3,115,811.28 165,000.00 12,000.00 600,000.00 37,500.00 50,000.00 50,000.00 50,000.00 131,400.00 239,500.00 30,052.05 6,040,462.90 33,558.13 24,101.38
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
849,787.50 236,081.25 3,262,500.00 412,500.00 24,000.00 700,000.00 37,500.00
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
50,000.00 50,000.00 50,000.00 131,400.00 191,600.00 29,976.84 6,025,345.59 24,101.38
Assisten Perencanaan mbangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
54,528.13 = Rp. = Rp. = Rp.
20,970.00 33,558.13 54,528.13 69,056.87
= Rp. = Rp. = Rp. = Rp.
20,970.00 23,985.49 24,101.38 69,056.87 30,675.11
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
19,740.00 5,830.00 2,500.00 1,915.00 37.50 500.00 152.61 30,675.11
= Rp. = Rp. = Rp. = Rp.
30,675.11 27,607.60 24,540.09 21,472.58
30,675.11 27,607.60 24,540.09 21,472.58 101,374.24
= Rp. = Rp.
6,772.50 12,219.60
= Rp. = Rp. = Rp. = Rp. = Rp. = Rp. = Rp.
65,376.30 5,000.00 1,915.00 375.00 500.00 9,215.84 101,374.24
= Rp. = Rp. = Rp.
12,582.00 20,134.88 32,716.88
= Rp. = Rp. = Rp. = Rp.
12,582.00 14,391.29 14,460.83 41,434.12
= Rp. = Rp. = Rp. = Rp.
13,630.50 15,590.57 15,665.90 44,886.97
32,716.88
41,434.12
44,886.97
Assisten Perencanaan mbangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568
= Rp.
4,132.80
= Rp.
1,653.75
= Rp.
91,388.10 15,086.38 16,320.00 500.00
= Rp. = Rp. = Rp.
129,081.03 129,080.00 Jumlah
71,956.47 15,579.06 72,304.15 1,001.00
= Rp. = Rp. = Rp. = Rp.
160,840.68 160,840.00 Jumlah
= Rp. = Rp. = Rp. = Rp. = Rp.
106,924.86 83,949.22 18,175.57 84,354.84 3,300.00
296,704.48 296,700.00 Jumlah
= Rp. = Rp. = Rp. = Rp. = Rp.
83,880.00 95,941.96 20,772.08 96,405.53 6,800.00
303,799.57 303,790.00
= Rp.
4,132.80
= Rp.
1,653.75
= Rp.
91,388.10 15,086.38 16,320.00 5,225.00
= Rp. = Rp. = Rp.
133,806.03 133,800.00
Perencanaan rana dan Prasarana Permukiman
No
Uraian Pekerjaan
Harga Satuan
Jumlah
No
Uraian Pekerjaan
Harga Satuan
Jumlah
Pekerjaan Jalan Penetrasi Lebar Perkerasan 4.00 meter
1 M' 4.00 4.00 4.00 4.00 1.00
meter meter meter meter ls
Lapisan Pondasi Bawah Onderlagh 15 Cm Lapisan pondasi atas Stenslagh t =7 cm Lapisan resap pengikat ( Prime Coate ) Lapisan Penetrasi t=3 cm Perapihan
= Rp. = Rp. = Rp. = Rp. = Rp.
20,970.00 23,985.49 5,193.02 24,101.38 6,800.00
= Rp. = Rp. = Rp. = Rp. = Rp.
Jumlah Dibulatkan
1 M'
83,880.00 95,941.96 20,772.08 96,405.53 6,800.00
303,799.57 303,790.00
Pekerjaan Saluran 0.210 m3 Galian tanah
19,680.00 = Rp.
0.210 m3 Buang tanah galian 0.190 m3 Pasangan batu kali 1:4 0.551 m2 Siaran 1:4 0.600 m2 Plesteran 1:4 1 ls Perapihan
4,132.80
7,875.00 = Rp.
1,653.75
480,990.00 = Rp.
91,388.10
27,380.00 = Rp. 27,200.00 = Rp. 5,225.00 = Rp.
15,086.38 16,320.00 5,225.00
Jumlah Dibulatkan
133,806.03 133,800.00
Assisten Perencanaan Proyek Pengembangan Sarana dan Prasarana Permukiman Jawa Barat
Ir. Ady Rachmat Nip 110 054 568