P180 Training Course SGSI HSE CONSULTANCY
Shell Global Solutions
Page 1
P180drf. P180drf.PPT PPT - 1
OBJECTIVES: By the end of this session you will be able to: – explain the function and and purpose of drain systems, – explain explain some of their their general general design considerations, – explain the function and and purpose of flares and vents, – discuss the key key issues in the design of flares and and vents, – know where where to seek seek guidance on drain and and flare design. Shell Global Solutions
OBJECTIVES
Page 2
P180drf. P180drf.PPT PPT - 2
OBJECTIVES: By the end of this session you will be able to: – explain the function and and purpose of drain systems, – explain explain some of their their general general design considerations, – explain the function and and purpose of flares and vents, – discuss the key key issues in the design of flares and and vents, – know where where to seek seek guidance on drain and and flare design. Shell Global Solutions
OBJECTIVES
Page 2
P180drf. P180drf.PPT PPT - 2
WHAT STREAMS DO YOU WANT TO HANDLE ?
Shell Global Solutions
P180drf. P180drf.PPT PPT - 3
WHAT STREAMS DO YOU WANT TO HANDLE? At first site the facility drainage problem may seem like a simple one, but if you take some time to think about about it you will find find a large number number of different different system. system. A desire for convenien convenience ce has led in the past to complex systems with many interconnections. In many cases there was a lack of thought to the way that systems should, could or would be operated and there have been some notable and quite serious incidents because of the mal-functioning or mal-operation of systems. Drain systems designed as an afterthought can be more hazardous than the main process. process. Therefore defining clearly what has to be drained and then providing appropriate well designed systems and operating procedures is essential. If given some thought it will be realised that the facilities drainage problem is a complex one. There are many different stream to be considered each needing a specific solution. Onshore and offshore need different solutions and offshore usually means a more complex disposal problem. It is essential that streams are kept segregated as far as possible and that interconnection between systems is minimised.
Page 3
STREAMS TO BE HANDLED Rainwater
Storm Water
Chemicals
Fire Water Drilling Mud
Wash Water
Process Fluids Aviation Fuel Grey Water
Spills Lube Oil
Black Water (sewage)
Shell Global Solutions
P180drf.PPT - 4
STREAMS TO BE HANDLED. At first site the facility drainage problem may seem like a simple one, but if you take some time to think about it you will find a large number of different system. A desire for convenience has led in the past to complex systems with many interconnections. In many cases there was a lack of thought to the way that systems should, could or would be operated and there have been some notable and quite serious incidents because of the mal-functioning or mal-operation of systems. Drain systems designed as an afterthought can be more hazardous than the main process. Therefore defining clearly what has to be drained and then providing appropriate well designed systems and operating procedures is essential. If given some thought it will be realised that the facilities drainage problem is a complex one. There are many different stream to be considered each needing a specific solution. Onshore and offshore need different solutions and offshore usually means a more complex disposal problem. It is essential that streams are kept segregated as far as possible and that interconnection between systems is minimised.
Page 4
DRAINAGE SYSTEMS What are three most important things about Drains Systems • Segregation, • Segregation, and • Segregation
Shell Global Solutions
DRAINAGE SYSTEMS
Page 5
P180drf.PPT - 5
WHY HAVE A DRAINAGE SYSTEMS ? • cater for accidentally spilled flammable liquids • handle surface water such as rain • provide a route for the safe and environmentally • acceptable disposal of liquid inventory • provide segregation
Shell Global Solutions
P180drf.PPT - 6
WHY HAVE A DRAINAGE SYSTEMS ?
The purpose of the drain systems is to collect and convey drainage streams to an appropriate disposal system in such a way as to protect personnel, plant and equipment, and to avoid environmental pollution. Note that the release of pollutants to the sea and hence the design features required of offshore drain systems are generally subject to the MARPOL convention, to which most countries are now signatories. Onshore disposal will be subject to local regulations. Drain systems provide the means of safely removing residual process and wash-down fluids from vessels, pipes, flooring and instruments, resulting either from operational activities or from preparation prior to carrying out maintenance work. The fluids are collected and transported to a recovery system or are disposed of in a safe and environmentally acceptable fashion. A fundamental safety consideration is that a drain system must not provide a route for migration of flammable liquids or vapours from one hazardous area to another, or to non-hazardous areas. Other factors affecting the safety and environmental acceptability of drain systems include: • interconnections between drain systems; • effect of blockages; • accidental or deliberate misuse; • preventing the spread of fires or flammable fluids; • pollution of the sea; • release of toxic materials to the atmosphere; • incorrect material specifications; • inability to be cleaned and maintained.
Page 6
Drains System Classification a) hydrocarbon drains b) non hydrocarbon drains subdivided into: i) open drainage systems ii) closed systems
Shell Global Solutions
Drains System Classification 1.
Page 7
P180drf.PPT - 7
Drains System Classification Classify your drains into each group
Shell Global Solutions
Drains System Classification 2.
Page 8
P180drf.PPT - 8
GUIDELINES • interconnection between different drain systems • Capacity – worst case • effect of blockages • accidental or deliberate misuse • possibility to spread fire or flammable liquids • provisions to clean and maintain the system
Shell Global Solutions
P180drf.PPT - 9
GUIDELINES. Drain systems have been involved in a large proportion of accidents within oil and gas processing facilities. There design demands careful consideration. The factors listed above affect the safety and environmental acceptability of drain systems. Careful design can avoid problems in operation and prevent the occurrence of accidents. In addition to considering the above factors the drains system design should be optimised based on an analysis of the following: • the nature of the product (flammable, toxic) • the pressure of the disposal stream • the degree of contamination (continuous or accidental) • the hazardous area of the disposal point. Where necessary segregated disposal streams should be provided. Kerbs or drip pans should be provided around vessels, pumps and other sources of leakage to limit the spread of small spills. Codes and Standards
For onshore facilities DEP 34.14.20.31: Drainage and Primary Treatment Systems; gives guidance on the design of onshore treatment systems. For offshore drains systems reference can be made to DEP 37.14.10.10-Gen.: Drain Systems for Offshore Installations. For storage tanks the worst case credible spill is associated with tank rupture. In this case suitable bunding provisions should be made in accordance with the IP Code Part 3 - Refinery Safety Code. Also provision for bund evacuation needs to be addressed. The release of pollutants, and hence the design features required for offshore drainage systems, is subject to the MARPOL convention, to which most countries are now signatory. As yet no specific codes or standards exist within the Shell Group for offshore drainage systems apart from those developed by individual operating companies. Page 9
GENERAL DESIGN CONSIDERATIONS Slope 1:100 to 1:75
• • • • • •
liquid seals and dip pipes floor drains drip pans tundishes and funnels vents disposal to sea
FPSOs & floating facilities
?
Avoid this it won’t work
Tank inerted and under pressure Dip leg arrangement for floating storage drains/slops tanks Shell Global Solutions
P180drf.PPT - 10
GENERAL DESIGN CONSIDERATIONS.
Drain lines from open drains shall enter drains collection vessels via a liquid seal, typically a U-bend, to prevent possible backflow of vapour. The liquid seal requires regular checking to ensure its integrity and accessibility aspects shall therefore be considered during detailed piping design. Dip pipes shall be provided if a caisson is used for the CD or OHD systems even though it might appear that they are not strictly required where non-hazardous and hazardous area drainage systems, including collection caissons, are totally segregated from one another. However, they are useful in minimising vapour release into
the modules in the event of backflow or other system upset conditions by creating an extra water seal between the process and the drainage systems. FLOOR DRAINS: Where the risk of hydrocarbon spillage can reasonably be expected to be negligible, grating should be used instead of solid plate wherever possible. Rain and deluge water will then be discharged directly overboard, thereby reducing the volumes of uncontaminated water which would otherwise be collected through the drains system. Drip pans shall be installed under equipment, such as wellheads and pig traps, where spillage of hydrocarbons direct to the sea is possible. However, since drip pans are likely to form a hazardous zone, they
should preferably be avoided as far as possible by designing out potential sources of leaks. The atmospheric vents associated with the drainage systems, e.g. from the collection vessels or the drains caissons, shall not be interconnected with each other and should preferably be dedicated vents. They shall be designed and positioned so that ignition by static electricity (or other ignition source) is precluded. The top of the vent pipe shall be sharp-edged to prevent brush discharges. Consideration should be given to placing the vent within the protective "umbrella" of the facility’s lightning conductor system or inside the Faraday cage formed by part of a structure, such as the flare boom. When sizing the vents, abnormal vapour flow rates shall be taken into account, such as those resulting from an incompletely depressurised vessel. The vents shall be sited away from HVAC inlets and shall not be fitted with flame arrestors.
Page 10
Drawn on P&ID
Piping elevation and as built
Gas out
HP Separator MAOP 3500 psi Liquid out
Drain Valve
ANSI 1500#
ANSI 150#
Drains Caisson (atmospheric) Maintenance Procedure: Drain vessel liquids through process, blow down, vent open drain valve for atmospheric draining.
Practice: Open drain valve to drain vessel whilst under pressure or drain vessel liquids through process, blow down and vent then break drain piping and collect final liquids in a bucket. Shell Global Solutions
P180drf.PPT - 11
Drawn vs. as built
On the left a simplified P&ID of the closed drain system for a high pressure knock out vessel on an offshore gas platform. The well stream enters the vessel operating at 3500 psi, gas and liquids are separated and flow out to the gas and liquids processes respectively. The drain detail shown is described as a maintenance drain for the disposal of residual liquids and washout water when the process is shutdown and the vessel is under maintenance. Operating procedures stipulate that vessel process liquids are drained through the process. The process is then shutdown, blown down and vented before the drain valve can be opened and the residual liquids (and any subsequently added wash water) drained. An inspection at site revealed the as built plant to be as shown on the right. With a drain valve positioned above the bottom of the vessel it was impossible to comply with the draining procedure. This is a real case and it was reported that the only variation to the written procedure was that after blow down and venting the drain piping at the base of the vessel was disconnected and any residual liquids drained to the drip pan. It is easy to imagine though that even with properly laid out piping the temptation exists to open the valve whilst the vessel is under pressure and use the available force to clear the liquids. This is a dangerous and unacceptable practice which risks overpressuring the drains caisson which (although not shown) has connections to open hazardous and non hazardous drains. The best solution is to avoid the closed drain altogether (unless dealing with particularly hazardous or toxic materials e.g. H 2S) and drain to the inlet of a open hazardous drain.
Page 11
Shell Global Solutions
Open Drains
Page 12
P180drf.PPT - 12
Schematic for a drain system with closed drains. The above drawing shows the arrangement of an offshore drain system with closed drains. Again the open hazardous and open non-hazardous drain systems are completely segregated. In this case discharge to the closed drains is by hard-piped connections that shall be positively isolated from the process during normal operation. The drain points should be fitted with double block valves with an intervening spade or spectacle blind rated for the upstream connection pressure. This ensures isolation from both the vessel and drain system when removing the spade or swinging the spectacle blind. An alternative isolation system for sight-glass drainage is a double-block-and bleed arrangement. The main drainage header should be fabricated from 150# rated piping class and terminate at a closed drains drum. The branch connections from the vessels to the main header or up to the first pipe diameter increase shall be rated for the same pressure as the vessel itself. This is because it is in the smaller branch pipes that hydrates are likely to form, should the vessel be inadvertently drained under pressure. Branches shall be connected to the top of the main header(s). There shall be no block valves in the drain system except for those at the individual drainage points. The need for hydrotesting the CD system means that a flange must be installed at the specification break in the piping so that the two pipe classes can be isolated from one another. It is intended that the CD system shall be used only to empty residual liquids from equipment prior to maintenance. No process shall be drained via the CD system unless that process has been fully depressurised. The closed drains drum shall be designed with sufficient volume to receive the drained fluids and to permit vapour disengagement.. The contents of the vessel should be pumped out under level control to a suitable low pressure location in the process to minimise the potential for back flow.
Page 13
Typical Seal Trap Arrangement
Shell Global Solutions
Typical Seal Trap Arrangement
Page 14
P180drf.PPT - 14
Design a simple drains System
Shell Global Solutions
Design a simple drains System
Page 15
P180drf.PPT - 15
What are the 3 most important things about drains. What are the Drain system classifications
Shell Global Solutions
DRAINS
Page 16
P180drf.PPT - 16
FLARES AND VENTS WHY have them WHAT makes a flare system HOW to design them What is NEW in flares
Shell Global Solutions
FLARES AND VENTS 1. There are
Page 17
P180drf.PPT - 17
FLARES AND VENTS
WHY BLOW DOWN • Emergencies • Maintenance
Shell Global Solutions
FLARES AND VENTS 2. There are
Page 18
P180drf.PPT - 18
Typical Flare/Relief System Flare boom
Flare Header Flare knock-out drum
Liquids capacity for worst blowdown
Manual blowdown valve Relief valve
To process Automatic blowdown valve
Liquids recovery pump Shell Global Solutions
Typical Flare/Relief System
Page 19
P180drf.PPT - 19
Considerations on whether to vent or flare: • DO NOT VENT • the impact on the environment • the safety and integrity of the disposal system • local regulations • economic evaluations
Shell Global Solutions
P180drf.PPT - 20
Flaring versus venting Wherever possible disposal streams shall be collected in a closed system and directed to a flare or vent, except when they can be sent back to the process or stored. In this context, the use of a gas recover system can be considered. In principle flaring is the preferred solution but this my not be possible where disposal streams contain products that are not combustible. Local regulations have largely been responsible for the control of flaring
Page 20
WHAT GOES WHERE
HP Relief System • • •
LP Relief System • • •
Venting • • • Shell Global Solutions
WHAT GOES WHERE
Page 21
P180drf.PPT - 21
HP Relief System • high pressure vessels • heat exchangers • pumps • compression systems
LP Relief System • low pressure vessels • low pressure equipment • atmosphere tanks • blanketing systems
Venting • drains tanks • purge posts • inerting systems • ??? Shell Global Solutions
WHAT GOES WHERE
Page 22
P180drf.PPT - 22
MOST IMPORTANT DESIGN IMPACTS
•Liquid carry over •Back pressure •Radiation •Purging
Shell Global Solutions
MOST IMPORTANT DESIGN IMPACTS
Page 23
P180drf.PPT - 23
LIQUID CARRY OVER HORIZONTAL KNOCK-OUT DRUM
LIQUID CARRY OVER HORIZONTAL KNOCK-OUT DRUM
Page 24
HYDROCARBON FLARE SYSTEM AND H 2S FLARE SYSTEM
HYDROCARBON FLARE SYSTEM AND H2S FLARE SYSTEM. The above flare system is typical of a refinery or chemical plant and is a more complex system than we would normally encounter in E&P, but there are examples that come close. Below are the notes applicable to the drawing. 1. The need for steam tracing depends on climatic conditions. 2. The pump capacity shall be such that the liquid hold-up of the knock-out drum can be disposed of within two hours. 3. For LNG plants no water seal vessel and no steam injection in the flare tip is applied. 4. Water seal column height, "H" shall be greater than P/J, where P = maximum pressure in the water seal vessel (in metres water column) and J = specific density of liquid. H shall be at least 2 metres. 5. Steam flow depicted for electronic transmission of signals. 6. Operator set maximum steam flow. 7. Range of required steam flow may necessitate more than one transmitter (auto range selection). 8. TIC is optional but shall be applied when liquid which is too hot or too cold (e.g. LPG) is pumped to slops. 9. Ultrasonic flow meter.
Page 25 10. A level alarm shall be provided if large quantities of liquid are expected.
Flare Radiation Calculation
Flare Radiation Calculation
Page 26
Shell FRED
Shell Global Solutions
Shell FRED
Page 27
To request a free evaluation CD-Rom containing full software products, please fill in an enquiry form or e-mail us at
[email protected] . www.shellshepherd.com Alternatively you may contact HSE Consultancy at: Shell Global Solutions (UK) Cheshire Innovation Park PO Box 1 Chester CH1 3SH. UK Tel. +44 151 373 5010 Fax. +44 151 373 5058 Shell Global Solutions
Information
Page 28
P180drf.PPT - 28
Shell FRED The following are currently used by Shell to reduce emissions from purging: • Purging with nitrogen instead of hydrocarbon gases • Provision of low purge flare tips • Installation of fluidic/molecular seals
Proven techniques not currently used by Shell: • Purging with combustion gases • Eliminate purge gas requirement by designing vent system/degasser for flashback
Shell Global Solutions
P180drf.PPT - 29
Shell FRED
A number of low impact purge operations are available. These are identified above and should be reviewed on a case by case basis as applicable. In addition, purge rates can be minimised by accurate rather than conservative methods for calculating purge gas rates.
Page 29
STRUCTURES FOR FLARES AND VENT STACKS AND LIQUID BURNERS • free standing stack • guyed stack • derrick structure • angled boom structure (especially on offshore platforms • Also Ground flares and Burner pits
Shell Global Solutions
P180drf.PPT - 30
STRUCTURES FOR FLARES AND VENT STACKS AND LIQUID BURNERS
Guidance on the design of structures can be found in DEP 34.00.00.30-Gen., DEP 34.24.26.31-Gen. And DEP 34.28.00.31-Gen. The type selected is based on economic and operational grounds. If only one stack is required, any of the four types noted above may be selected.
Page 30
What is NEW in flares
Shell Global Solutions
What is NEW in flares There are
Page 31
P180drf.PPT - 31
For intermittent flaring resulting from process upsets, the following are currently considered by to reduce the impact of flare emissions and effects:
use of leaner flare gas
steam/water injection or air assisted flares
high velocity tips
enclosed ground flares, box flares or low intensive flare tips for reduced light effect
flaring window
Low noise burners
Shell Global Solutions
P180drf.PPT - 32
FLARE EMISSIONS
Proven technology, but new to Shell are in-ground enclosed flares and low profile enclosed ground flares for smoke reduction, marketed by NAO Inc For continuous flaring, the following should be considered :
Use of energy from continuous flares for WHR
Use of vent gas for power generation rather than flaring
Optimised combustion technology - including efficient burner design, low purge flare tips etc - is provided by:
Elmac
Birwelco
Kaldair
NAO Inc
To reduce emissions, low consumption pilot ignition packages (Birwelco) or pilots on demand should be considered. Alternatives for non continuous pilots are: • Electrical ignition • Projectile ignition Both methods are well established, although there is some concern regarding the efficiency of projectile ignition with vertical stacks. Existing flare systems can be readily modified to accommodate non continuous pilots.
Page 32
Flare Recovery System Recovery Equipment
Flare Valve
To Process
To Flare Tip
Rupture Disc Flare Header
Flare Gas Knock-out Drum
Shell Global Solutions
P180drf.PPT - 33
FLARE GAS RECOVERY Flare gas recovery is a proven process and is currently used by Shell. The flare gas recovery system is designed for normal leakage rates, vent gases normally flared and minor process upsets. During recovery, the flare line is closed by the valve installed downstream of the KO drum. For safety, a bursting disc is installed in parallel. The flare gas is compressed and recycled to the process or used as fuel gas. For larger releases, the valve will open and the recovering equipment will be isolated. During this operation, the gas will be ignited. Each flare system requires evaluation on a case by case basis as there is the potential for high compression duty, depending on the recycle pressure required. Installation needs to be weighed against the “cost” of CO2 (tax in Norway or environmental targets) Vendors supplying flare gas recovery systems are:
Kaldair
Umoe
Elmac
Page 33
THE UMOE SAFE FLARE The new and patented UMOE SAFE FLARE gas recovery system eliminates the need for continuous flaring of gas on Offshore Platforms and Petrochemical Plants. The gas is safely and effectively recovered to be utilised for other purposes. The system claims a cost effective recovery of flare gas and a substantial reduction of CO2 emissions. The concept comprises flare closing components, a gas recovery system and a separate system for igniting the flare. Reference is made to the illustration of the basic flaring technology. Basic components are a flare valve in the flare line fitted with a rupture disc in parallel. When pressure in the flare system reaches a predetermined level, the flare valve opens. In normal operation, the flare gas recovery system should capture the underlying flare gas that continuously leaks into the flare collection header and direct it back into the gas processing for compression, dehydration and export. If a problem occurs the flare valve will open promptly and the gas will be diverted to the flare. The flare is an essential safety system, used for safe disposal of flows from pressure safety valves and depressurisation of processing equipment. The flare gas recovery system must not compromise this capability: 1. The system must be able to open quickly, before the pressure rises and reaches a predetermined level. 2. The reliability must comply with all security standards of the project. 3. The gas recovery system must be simple and reliable. You can find details about the UMOE flare at the following web site:
http://www.umoetech.no./
Page 34
UMOE SAFE IGNITION
UMOE SAFE IGNITION consists of a compressed nitrogen driven launcher contained in a stainless steel cabinet at the deck level. In addition, a striker plate is located below the flare tips to ignite the specially designed ignition pellet being automatically launched from the launching unit. When hitting the striker plate, the pellet will explode and generate a shower of sparks, each igniting along its entire path. Guaranteed ignition in all weather conditions. Umoe Safe Ignition has been designed by Umoe Process Technology AS, Techno Consult AS and Raufoss Technology AS and is protected by several Norwegian and international patents
Page 35
Shell Global Solutions
Example
Page 36
P180drf.PPT - 36
Shell Global Solutions
Example
Page 37
P180drf.PPT - 37