Electrical Thumb Rules (Part 3)
Home
Electrical Thumb Rules (Part 3)
Electrical BasicsFull description...
Author:
Manish Tiwari
10 downloads
131 Views
148KB Size
Report
DOWNLOAD .PDF
Recommend Documents
Electrical Thumb Rules-(Part 1)
Rules ElectricalFull description
Electrical Thumb Rules
Electrical Thumb Rules You MUST Follow (Part 1) _ EEP.pdf
Full description
B737 Rules of Thumb
B737 Essential Data
Aviation Rules of Thumb
aviation rulesFull description
Rules of Thumb
Rules of thumb
Beams Thumb Rules
Full description
Aviation Rules of Thumb
Rules of thumb for pilotsDescrição completa
Foundation Thumb Rules
Foundation Thumb Rules
253083742-Rules-of-Thumb
Document
47643027 Foundation Thumb Rules
FootingFull description
Tower Thumb Rules
Tower Rules
Rules of Thumb
Structural Engineering Rules of Thumb for designDescripción completa
Rules of Thumb
Structural Engineering Rules of Thumb for designFull description
Hvac Rules of Thumb
HVAC rule of ThumbFull description
Hvac Design Thumb Rules
Useful collection of handy thumb rules for quick assessment of HVAC systems.Full description
Electrical Thumb Rule
Thumb rules electrical calculationsFull description
Electrical Thumb Rule
Electrical Thumb RuleFull description
Thumb Rules in Civil Engineering
civil engineering rules
Rules of Thumb Steel Design
Rules of Thumb Steel Design
Rules of Thumb (3rd Edition)
rules of thumb-mechanical
Mechanical Seals, Rules of Thumb
Best Guidelines to select mechanical seals
Aquaponic Gardening Rules of Thumb
aquaponics
Thumb Rules for Structural Design
Thumb rule designFull description
Electrical Thumb Rules-(Part-3) Size of Capacitor for P.F Correction: For Motor
Size Size of Capa citor = 1/3 Hp o f Motor Motor ( 0 .12x KW KW of Motor)
For Transformer
< 315 KVA KVA
5% of KVA KVA Rati ng
315 KVA to 1 000 00 0 KVA KVA
6% of KVA KVA Rati ng
>1000 KVA KVA
8% of KVA KVA Rati ng
Earthing Resistance value: Earthing Resistance Value
Power Station
0.5 Ω
Sub Station Majo Major r
1.0 Ω
Sub Station Mino Minor r
2.0 Ω
Distribution Trans former former
5.0 Ω
Transmission Line
10 Ω
Single Isol ate Earth Earth Pit
5.0 Ω
Earthing Grid
0.5 Ω
As As per p er NEC Earthin g Res is tance s hould be <5.0 Ω
Voltage Limit (As per CPWD & Kerala Elect.Board): Voltage Limit (As Per CPW D)
240V
< 5 KW
415V
<100 KVA KVA
11KV
<3 MVA
22KV
<6 MVA
33KV
<12 MVA
66KV
<20 MVA
110KV
<40 MVA
220KV
>40 MVA
Voltage Variation > 33 KV
(-) 12.5% to (+) 10%
< 33 KV
(-) 9% to (+) 6%
Low Voltage
(-) 6% to (+) 6%
Insulation Class: Insulation
Temperature
Class A
105°C
Class E
120°C
Class B
130°C
Class F
155°C
Class H
180°C
Class N
200°C
Standard Voltage Limit: Voltage
IEC (60038)
ELV
< 50 V
LV
50 V to 1 KV
MV
HV
> 1KV
IEC (6100:3.6)
Indian Elect. Rule
<=1 KV
< 250 V
<= 35 KV
250 V to 650 V
<= 230 KV
650 V to 33 KV
EHV
> 230 KV
> 33 KV
Standard Electrical Connection (As per GERC): As per Type of Connection Connection
Voltage
LT Connection
<=440V
HT connection
440V to 66KV
EHT connection
>= 66KV
As per Electrical Load Demand
Up 6W Load demand
1 Phase 23 0V Supply
6W to 100KVA(100KW)
3 Phase 44 0V Supply
100KVA to 2500KVA
11KV,22KV,33KV
Above 250 0KVA
66KV HT Connection Earthing
H.T Connection’s Earthing Strip
20mm X4mm Cu. Strip
CT & PT bodies
2Nos
PT Secondary
1Nos
CT Secondary
1Nos
I/C and O/G Cable+ Cubicle Body
2Nos
Standard Meter Room Size (As per GERC): Meter Box Height
Upper level does no t beyond 1.7 m eter and Lower level shou ld not below 1.2 m eter from ground.
Facing of Meter Box
Meter Box sh ould be at front area of Building at Ground Floor.
Meter Roo m / Closed Shade
4 meter squa re Size
Approximate Load as per Sq.ft Area (As per DHBVN): Sq.ft Area
Required Load (Connected)
< 900 Sq.ft
8 KW
901 Sq.ft to 1 600 Sq.ft
16 KW
1601 Sq.ft to 250 0 Sq.ft
20 KW
> 2500 Sq.ft
24 KW
For Flats :100 Sq.ft / 1 KW
For Flats USS /TC: 100 Sq.ft / 23 KVA
Contracted Load in case of High-rise Building: For Domestic Load
500 watt per 100 Sq. foot of the constructed area.
For Commercial
1500 watt per 100 Sq. foot of the constructed area
Other Common Load
Staircase Light
For lift, water lifting pump, streetlight if any, corridor/campus lighting and other common facilities, actual load shall be calculated
11KW/Flat Ex: 200Flat=200×11=2.2KW
Sanctioned Load for Building Up to 50 kW
The L.T. existing mains shall be strengthened.
50 kW to 450 kW (500 kVA)
11 kV existing feeders s hall be extended if s pare capacity is available o therwise, new 11 kV feeders s hall be cons tructed.
450 kW to 2550 kW (3000 kVA)
11 kV feeder shall be constructed from the nea rest 33 kV or 110 kV substation
2550 kW to 8 500 kW (10,000 kVA)
33kV feeder from 33 kV or 110 kV sub station
8500 kW (10,000 kVA)
110 kV feeder from nearest 110 kV or 220 kV sub -station
×
Report "Electrical Thumb Rules (Part 3)"
Your name
Email
Reason
-Select Reason-
Pornographic
Defamatory
Illegal/Unlawful
Spam
Other Terms Of Service Violation
File a copyright complaint
Description
×
Sign In
Email
Password
Remember me
Forgot password?
Sign In
Our partners will collect data and use cookies for ad personalization and measurement.
Learn how we and our ad partner Google, collect and use data
.
Agree & close