DOCUMENT
UMBER
Project
Package
Originator
Discipline
Doc. Type
Unit n
0
Serial n
0
Rev
Page
RAPID
P20 1
WCTB
HSE
PRC
7410
0007
0
1/12
PETRONAS RAPID PRO ECT PACKAGE 20C1: COMMON CONSTRUCTIO ACCESS AN PERMANENT ROADS WITHIN THE RAPID SITE AT PENGE ANG JOHOR
JOB H ZARD ANALYSIS ________ __________ ___________ ___________ ___________ __________ __________ __________
HEALTH SAFET AND EN IRONME T J B HAZA D ANALY IS (JHA) RIVEN PILES / SPU PILES
OWNER pproval: Name: Date (DD MMM‐YY): Signature: Document class:
Z
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
JOB HAZARD ANALYSIS Task/ Job Description :
DRIVEN PILES / SPUN PILES
Date :
Task Duration :
Specific Area :
Development Team No.
Name
Position
Signature
Date
1 2 3 4 5 6 7 8 Prepared by;
Checked by; Mohamad Rasydi 2014.09.16 00:41:11 +08'00'
Approved by; Ihsan 2014.09.16 00:42:02 +08'00'
Ng Mun Wai 2014.09.16 00:41:37 +08'00'
_________________________ ( Mr. Mohamad Rasydi )
_________________________ ( Mr. Ng Mun Wai )
_________________________ ( Mr. Ihsan Idris )
CONSTRUCTION MANAGER
PROJECT MANAGER WCT BERHAD
PROJECT DIRECTOR
WCT BERHAD
WCT BERHAD
work supervisor : I certified that I have explain this JHA to all workers
No. 1 2 3
Name
IC No.
Signature
Date
Page
2
/ 12
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Page
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
3
/ 12
JOB HAZARD ANALYSIS Task/ Job Description :
DRIVEN PILES / SPUN PILES
Potential Hazard Examples for Specific Categories : Worker slip/trip/fall struck/against
back injury hazardous chemical
overhead work burn (heat/chemical) eye injury radiation hazard sharp object
contact by/with caught/in/on/between strains electrical hazard
Equipment
gas release (HC/ H2s)
damage (physical) loss of production
spill or loss of containment dusty
explosion
off‐site impact
BASIC JOB STEP 1 Land surveyor set out piling points in the site
Specific Area :
risk rating Likelihood:
Severity : extreme high medium low
Environment
fire
Task Duration :
Date :
multiple facilities, extensive damage or prolong loss of production > RM 2000 Single Fatality, major injury, > 1 lost Time Injury (LTI) major and loss of Major & minor injury /loss of No injury, slight damage to equipment and no loss to production
Likelihood Medium L
High M
Medium High
M H
H EX
1.1 Land surveyor or his assistant hit by moving machine/vehicle.
1.2 Trip and fall.
Possible could occur (0.5‐4 year) remote, unlikely to occur (4‐30 year)
medium low
Mitigation
severity Low
POTENTIAL HAZARDS
Probable, likely to occur (0‐0.5 year)
high
Low
Medium High
Safe working Practices SWP, PTW, HSEMS SWP, PTW, HSEMS, HSE awareness
Extreme Special procedure, HSE awareness, OSH program
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
CONTROLS
ACTION BY;
personal injury
M
1.1 Land surveyor and his assistant must attend induction before entering the site.
WCT HSSE Supervisor
1.2 Traffic diversion will be implemented in the event survey points are located on access roads.
WCT's HSSE Personnel / Site Supervisor
personal injury
L
1.3 Plastic barriers and flagmen will be WCT's Site provided when survey points are located Supervisor / HSSE at the road side. Personnel
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
4
/ 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS 1.3 Hand injury when installing survey pegs
1.4 Struck by lightning
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Personal injury
L
Fatality / personal injury
H
Specific Area :
CONTROLS 1.4 Passage / pathways for workers are inspected daily to ensure materials / equipment / tools are NOT kept along the passage / pathways.
WCT's Site Supervisor
1.5 To maintain good housekeeping in each work site.
WCT's Site Supervisor / HSSE
1.6 Proper ladder with handrail will be provided for ingress/egress of an excavation.
WCT's HSSE Personnel / Site Supervisor
1.7 Any self ‐made tool will be confiscated and removed from the site.
WCT's HSSE Personnel
1.8 Land surveyor and his assistant must wear cotton glove and PPE while
WCT's HSSE Personnel
1.9 Land surveyor is NOT allowed to work in an open field during rain.
WCT's HSSE Personnel
1.10 Pre‐start briefing and tool box talk will be performed to raise awareness and reinforce 2
Delivery and unloading of piles using a mobile crane
2.1 Trailer collide with ongoing/moving traffic
Personnal injury/property damage
L
ACTION BY;
2.1 Escort by WCT personnel or site supervisor.
WCT's Project Manager / Site Supervisor WCT's site supervisor
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
5
/ 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
2.2 Trailer skid and out of control on slippery road
Personnal injury/property damage
M
2.2 Supervisor only allows the trailer to enter the site after he has assess condition of the access roads in the site are safe for vehicle movement
2.3 Piles hit people during lifting and unloading
Personnal injury/property damage
M
2.3 Pre‐plan and identify safe access route to the unloading site
ACTION BY; WCT's Site Supervisor and HSSE Personnel WCT's Site Supervisor
2.4 No vehicle movement in the site during heavy rain and immediately after the rain.
WCT's Site Supervisor and HSSE Personnel
2.5 Driver of the trailer to observe speed limit in the site (25 km/hr) and follow the escort
WCT's HSSE Personnel
WCT's Site Supervisor and HSSE Personnel
2.4 Worker fall from the trailer
Personal injury
L
2.6 Delivery trailer must be inspected and its brake, tyres, windscreen and etc. are in an acceptable condition before it is allowed to enter the site.
2.5 Lifting cable snapped or lifting gears failed
Fatality / Personal injury
H
2.7 To obtain PTW prior to any lifting and unloading.
WCT's HSSE Personnel
2.6 Fingers of the workers caught in between the piles
Personal Injury
L
2.8 Crane must be inspected and must have must valid PMA.
WCT's HSSE Personnel
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
6
/ 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
ACTION BY;
2.9 The crane must have a permit‐to‐ operate sticker.
WCT's HSSE Personnel
2.10 Crane operator must attend induction before entering the site.
WCT's HSSE Personnel
2.11 Lifting gears must be inspected and have all the necessary certificates before being used.
WCT's HSSE Personnel
2.12 Only lifting gears (sling, chain, shackles, hooks) with proper color coding are allowed to be used.
WCT's HSSE Personnel
2.13 Radius of the lifting must be barricaded with plastic barriers to prevent people walking into the lifting zone.
WCT's Site Supervisor and HSSE Personnel
2.14 Signalman / watchman to guide the WCT's Site crane operator and coordinate lifting Supervisor and process. HSSE Personnel 2.15 Tag line to be used to control the spun pile when it is being lifted
WCT Site Supervisor
2.16 Signs will be placed around the lifting zone.
WCT's Site Supervisor
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
7
/ 12
JOB HAZARD ANALYSIS Task/ Job Description :
DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS 2.17 Full‐time supervisor and safety personnel throughout the unloading process. 2.18 Pre‐start briefing and tool box talks. 2.19 Crane operator and workers must wear proper PPE.
3
Moving and positioning a piling rig
ACTION BY; WCT's Site Supervisor and HSSE Personnel WCT's Site Supervisor WCT's Site Supervisor and HSSE Personnel WCT's HSSE Personnel
3.1 Operator or mechanic falls Property damage from the piling rig / Personel Injury
L
3.1 Operator of the piling rig and mechanic must attend induction.
3.2 The piling rig accidentally hit people working nearby.
Property damage / Personel Injury
M
3.2 The piling rig must be inspected before entering the project site.
3.3 The piling rig tilted due to uneven ground.
Property damage
L
3.3 Operator or mechanic has to use WCT's Site body harness when he is performing Supervisor and routine maintenance and checking HSSE Personnel where he is exposed to falling from high. 3.4 Flagmen / watchmen will be deployed when the piling rig is moving.
WCT's Site Supervisor and HSSE Personnel
WCT's Site Supervisor and HSSE Personnel
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
8
/ 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS 3.5 Workers must be kept at least 5m from the piling rig when it is moving.
WCT's HSSE Personnel
3.6 Windscreen and windows are free of obstruction or shed.
WCT's Site Supervisor
3.7 Full‐time supervisor.
4
Hoisting a spun pile to the piling frame
4.1 Falling pile due to snapped Fatality / lifting cable or lifting gears Personal injury / failure Property damage
H
ACTION BY;
WCT
3.8 Working platform for the piling rig must be leveled / flattened by an excavator or a motorgrader.
WCT's Site Supervisor
3.9 Soft ground will be removed and replaced with suitable earth and compacted.
WCT's Site Supervisor
4.1 Only lifting ropes and lifting gears (sling, chain, shackles, hooks) with proper color coding are allowed to be
WCT's HSSE Personnel
4.2 All lifting ropes and gears must be visually inspected for any abnormally before put to use.
WCT's Site Supervisor
4.3 PTW must be obtained before commencing the works.
WCT's Site Supervisor and HSSE Personnel
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Rev
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
0
Page
9
/ 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
ACTION BY;
4.4 Lifting zone must be barricaded.
WCT's Site Supervisor
4.5 Signalman / watchman must be full time at the site.
WCT's Site Supervisor
4.6 Tool box talk or pre‐start briefing will be conducted by supervisor
WCT's HSSE Personnel & Site Supervisor 4.7 Full‐time supervisor throughout the WCT's Site lifting process. Supervisor
5
Driving of spun pile into the ground
5.1 Hearing impairment
5.2 Falling object from the piling frame
4.8 Operator will be given interval short break to avoid fatigue.
WCT's HSSE Personnel & Site Supervisor WCT's Site Supervisor & HSSE personnel
People working close to the piling rig
L
5.1 Supervisor, operators and workers exposed to the noise for a long duration must wear ear muffs.
Personal injury
L
5.2 To obtain PTW before commencing the works.
WCT's HSSE Personnel & Site Supervisor 5.3 Warning signs will be put up to WCT's HSSE ensure NO worker is standing below the Personnel & Site piling frame. Supervisor
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
Rev
Page
0
10 / 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
ACTION BY;
5.4 Supervisor and workers must wear safety helmet.
WCT's HSSE Personnel & Site Supervisor 5.5 Tool box talk or pre‐start briefing will WCT's Site be conducted by supervisor. Supervisor 6
Welding when joining of spun piles
6.1 Sparks from the welding cause fire to flammable material nearby 6.2 Burns due to accidental contact with hot surface
Personal injury / property damaged Personal injury
M
6.1 Hot Work Permit must be secured before commencing with the welding.
L
6.2 Fire extinguiher must be in place during the hot work.
6.3 Burns caused by welding sparks
Personal injury
L
6.3 Flammable substances such as fuel, paint, lubricant, cleaning agent and etc. must be kept away from the hot work.
WCT's Site Supervisor
6.4 Proper housekeeping and proper storage for flammable material.
WCT's Site Supervisor
6.5 Welder must use leather glove and welding shield. 6.6 Warning signs will be displayed when hot work is being carried out.
WCT's HSSE Personnel WCT's HSSE Personnel & Site Supervisor
WCT's HSSE Personnel & Site Supervisor WCT's Site Supervisor
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
Rev
Page
0
11 / 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP 7
Cutting of spun piles using handheld circular saw and removal of the cut piles
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
7.1 Accidental cuts by the rotating blade
L
7.1 The handheld circular saw must be inspected and approved before use.
7.2 Pre‐cut pile falls / collapses on the worker
M
7.2 Permit to work must be secured prior to commencement of the work.
7.3 Cut pile hit worker while it is being lifted.
L
7.3 Only trained worker is allow to operate the circular saw. 7.4 Warning signs will be displayed to ward off any unauthorized entry to the work area
ACTION BY; WCT's HSSE Personnel WCT's HSSE Personnel & Site Supervisor WCT's HSSE Personnel & Site Supervisor WCT's HSSE Personnel & Site Supervisor
7.5 Free‐standing pile more than 3m in height will be secured and hoisted by a rope hooked to an excavator's bucket
WCT's Site Supervisor
7.6 Only ONE (1) worker is allowed in cutting of piles at one time in the same place.
WCT's HSSE Personnel & Site Supervisor
7.7 Lifting zone will be barricaded.
WCT's HSSE Personnel & Site Supervisor
Document Number
PETRONAS RAPID PROJECT PACKAGE 20C1: COMMON CONSTRUCTION ACCESS AND PERMANENT ROADS WITHIN THE RAPID SITE AT PENGERANG JOHOR
Project
Package
Originator
Discipline
Doc. Type
Unit n°
Serial no
RAPID
P20C1
WCTB
HSE
PRC
7410
0007
Rev
Page
0
12 / 12
JOB HAZARD ANALYSIS Task/ Job Description : DRIVEN PILES / SPUN PILES
BASIC JOB STEP
Task Duration :
Date :
POTENTIAL HAZARDS
Who or What might be harmed (person/ Equipment/ Environment)
risk rating
Specific Area :
CONTROLS
ACTION BY;
7.8 Flagmen / signalmen will be provided throughout the lifting works
WCT's HSSE Personnel & Site Supervisor
7.9 Worker must use polka dot gloves and goggles.
WCT's HSSE Personnel & Site Supervisor
7.10 Tool box talk or pre‐start briefing will be conducted by supervisor.
WCT's Site Supervisor