JOB SAFETY ANALYSIS FOR demobilization works
1.
Description of Task Step
Removal/demolition of existing chain link fence and supports.
CLIENT
RLIC
LOCATION : TRAGS SUPPORTS SERVICES AREA
CONTRACTOR
TRAGS DATE: 06/12/10
TEAM COMPOSITION
TASK NAME Step No.
Ref. No:
Hazard
• • • • • •
Slip, trip and falls. Sharp edges and sharp objects. Cuts, nips, due to unsafe and incorrect handling of hand tools. Tripping hazard due to cables. Dust (Inhalation ) Particles penetrating into the eye. .
Who Or What Might Be Harmed
• •
Personnel injury. Equipment.
Control Measures/ Recovery Measures
• • • • • •
.
• • •
•
JOB SAFETY ANALYSIS FOR DEMOBILIZATION WORKS
Follow method statement. Follow CPW. Adequate supervision. Tool box talk prior to start the task. Avoid unauthorised entry to the area. Provide signage for restrict unauthorised personnel to enter area. Awareness shall be provided to the personnel who ever involved in the activities. JSA briefing shall be done prior to the job along with the toolbox talks. Use appropriate personal protective equipment (Hand gloves, eye protection, and hard hat). Inform Client for approval before start the job.
Action/ Responsible Party
TRAGS
1
JOB SAFETY ANALYSIS FOR demobilization works
2.
Description of Task Step
Housekeeping and site clearance.
CLIENT
RLIC
LOCATION : TRAGS SUPPORTS SERVICES AREA
CONTRACTOR
TRAGS DATE: 06/12/10
TEAM COMPOSITION
TASK NAME Step No.
Ref. No:
Hazard
Trip, slip and fall/struck by.
Who Or What Might Be Harmed
Personnel injury.
Control Measures/ Recovery Measures
• • •
JOB SAFETY ANALYSIS FOR DEMOBILIZATION WORKS
Housekeeping will be maintained in a good and orderly manner. Keep the tools and equipments in appropriate place. Remove all tools and equipment as soon as reasonably practicable after usage