Tips Tricks with Version Six (Client) Don Louser PMP, PMA Consultants LLC
Give Us Your Card
• There are more items in this presentation than we will have time to demonstrate • Give us your business card and we will send you the entire presentation complete with notes • Or, contact me @
[email protected]
2
What we have for you today...
• What’s New in Client v. 6.0 (Slides 1-20) • Use of Indicators (Slide 21) • Global Changes – De-status the Schedule (Slides 22-26) • Global Changes – Change WBS from Filters (Slide 27) • Export and Importing Projects (Slides 28-39) • Project details that are often forgotten (Slides 40-42) • Renumbering Activities (Slides 43-45) • Building your Schedule – Making a List (Slides 46-47) • Building your Schedule - Linking Shortcuts (Slide 48) • The Schedule Report (Slides 49-52) • Lag Calendars (Slides 53-54) 3
What we have for you today (cont.)... • Fragnets
(Slides 55-58) • Coding and WBS Shortcuts (Slides 59-63) • Finding and Filtering Activities (Slides 64-65) • Roles and Resource Loading (Slides 66) • Schedule Crashing Basics (Slides 67-68) • Advanced Layouts For Communication (Slides 69-71) • Advanced Gantt Chart Formatting (Slides 72-76) • Exporting and Importing Layouts/Reports (Slide 77) • Add Bar-charts & Graphics to Reports (Slides 78-83) • Working with Baselines (Slides 84-91) 4
What’s New – Reflection Projects •
Power with Simplicity !!!
•
A Reflection is a Copy of a Project that enhances Your Ability to “What If” or Update Your Project
•
Same Name – What If – Internal Link to Source – Baseline – Timesheet Data – Activity Owner
•
“Activity Owner” make changes via .xer or Web
•
Review & Change or Merge As Is (Check Boxes)
•
Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection DEMO 5
What’s New - Create Reflection Project
6
Making Changes to Reflection Projects
• Use to test Scenarios or Update Project • Send w/Project Specific Layout to Others to Update • Import/Export just like any other Project file • Activity Owner – designate Owner w/Required Web License & Privileges to Update/Change • Admin or Project Superuser gets last shot to Review/Correct before merging back into Source Project •
Merge Will Not remove Activities, Resource Assignments, WBS Elements, Work Products & Docs, Expenses, Issues or Risks if deleted from Reflection
7
Merging Reflection into Source Project •
Close all Projects
•
Go to Projects Table – Select Reflection Project
•
Right Click – Merge Reflection into Source Project
8
Merging Reflection into Source Project
9
Merging Reflection into Source Project
10
Merging Reflection into Source Project
11
What’s New – Future Bucket Planning
• Redistribute Even Distribution of Budgeted Units • Editable Security Privilege • Duration Type Must be Fixed Duration & Units, or Fixed Duration & Units/Time • Use Resource Spreadsheet or Resource Assignment • In Future Bucket Period type or change Values as Needed 12
What’s New – Future Bucket Planning Day 1 Even Spread Future Bucket
Day 2
Day 3
Day 4
Day 5
TOTAL
8
8
8
8
8
40
8A
8A
4A
10R
10R
40
•Assuming Daily TS – P5 spread evenly •Actual levels of work may vary •Example shows 20 A units in 3 days •Remaining needs to be adjusted •Two remaining buckets reflect adjustment •Activity Adjusted must have Fixed Duration & Units, orFixed Duration & Units/Time •Use Resource Spreadsheet to adjust future bucket period
13
Edit Future Bucket Security
14
What’s New – Group & Sort Dialog •
New Checkbox for Show Group Totals, Shrink Vertical Bands
SHOW PIX & EXPLAIN
15
What’s New - Search in Pop-Up Dialog and Type Ahead in Drop Down
SHOW PIX & EXPLAIN
16
What’s New - Copy Baselines •
Checkbox in Copy Project Options
•
Copy Baselines Dialog
# Copies Controlled by New Setting in Admin Preferences 17
Admin preferences Setting for Copying Baselines
18
What’s New - Role Limits •
Similar to Limits for Resources
•
Effective Date and Max Units/Time
19
What’s new – Project Specific Layouts (Yeah!) •
Layout with Filter when Project Exported
•
Reduces Need for Global Layouts
•
Only Global and Layout Filters will Restrict Use
•
Expanded & Collapsed Bars & Row Height Setting when switching between layouts and Windows (Yeah!)
20
Use of Indicators
21
Useful Global Changes – De-Status the Schedule Re-create a Baseline, Copy an Existing Schedule that has Been Progressed Project Detail Calculations Tab =
Any Actual Units that Exist Must be set to 0 •
See Actual Units Slide
Run 2 Global Changes to Reset Activities to Not Started •
See De-Progress GCs
Make any Needed Changes and Reschedule
Skip 22
Useful Global Changes – De-Status the Schedule (cont.)
Actual Work Units Go Back
23
Useful Global Changes – De-Status the Schedule (cont.)
De-Status the GC’s
Go Back
24
Errors? Sometimes...
An Activity may have a Unit without a Resource Assigned...
25
Useful Global Changes – De-Status the Schedule (cont.)
Set Cols for All Units Delete Manually, or Use the FillDown Feature
26
Useful Global Changes – Change WBS Based on Filters
27
Exporting and Importing Projects Primavera PM/MM (.xer) MS Project Project Planner (P3) Spreadsheet (.xls) Primavera Contractor 4.1 (.xer)
28
Exporting and Importing Projects – Spreadsheet (.XLS)
1. Select Items for Export
2. Separate Sheet for Each Item
29
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
3. Select a Project (it must be open)
30
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
4. Establish Templates for each Item
31
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
5. Certain items are mandatory, and you can filter & sort
32
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
6. Select any or all templates
33
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
7. Select the file path and name
34
Exporting and Importing Projects – Spreadsheet (.XLS) (cont.)
8. Confirm before you finish
35
Exporting and Importing Projects (cont.)
One Worksheet Per Subject 36
Exporting and Importing Projects (cont.)
Caution! – Don’t Edit this Sheet 37
Importing Projects
Importing is a Snap!
38
Importing Projects (cont.)
39
Project details that are often forgotten
40
Project details that are often forgotten
41
Project details that are often forgotten
42
Renumbering Activities Many GCs like Intelligent IDs CSI Code – Bldg – Floor Establish UDF (Activity) or Activity Code Put in Column in Layout Type Codes in Column Use Global Change Codes Become Activity IDs
43
Renumbering Activities (cont.)
Leave Blank
44
Renumbering Activities (cont.) For those a bit more familiar with (GC’s) Create Activity Code Add Activity Code column in Layout Fill Column Create GC’s that add suffix for Bldg & Floor
45
Building your schedule – Making a list
46
Building your schedule – Making a list
47
Building your schedule – Linking shortcuts
the order to link the activities, then your mouse and choose “Link Activities.” They are now linked in the order you clicked on them.
48
Building your schedule – The Schedule Report When you schedule your project, don’t forget to choose “Log to file” and click on the ellipsis to specify the location of the “schedule.txt” file. Always view the log to spot errors.
49
Building your schedule – The Schedule Report
50
Building your schedule – The Schedule Report
51
Building your schedule – The Schedule Report
52
Lag Calendars and Schedule Result - Version 5.0
+
= 53
Lag Calendars
Reschedule
This has been changed in v 6.0 to default to the predecessor
+
=
?
54
Fragnets
• Time Saving – why recreate the wheel? – Building a Single Schedule – Modifying Many Schedules • Create New or Modify Existing – New = As You Would New Project – Modify = Delete from Existing • WBS is the Key to Integration
55
2 Projects
Fragnets (cont.) Move to 2 WBS elements
Modify a template with a Fragnet
To Here From Here
56
Fragnets (cont.)
Objective – Add 22 new Activities in Template to 2 WBS Nodes •
Copy the Template as Fragnet, Delete All Activities Except those to Remain in Planning & Design WBS Nodes
•
Add the 22 New Activities & All Links to Fragnet
•
Open Template & Fragnet
•
Delete All Activities in Planning & Design Template WBS Nodes
•
Select & Copy All Fragnet Activities 57
Fragnets (cont.)
• Paste into one of the empty Template Nodes (Preserves all Links) • Control-Click all Activities to be moved to other Node • (Cut) • (Paste) into other Node • Re-establish any Links from 2 Nodes to others • Use Template to create new Schedules 58
Coding and WBS Shortcuts
Here is one person’s Layout
59
Coding and WBS Shortcuts (cont.)
60
Coding and WBS Shortcuts (cont.)
61
Coding and WBS Shortcuts (cont.)
Here. the work is organized by WBS1 and Level
62
Coding and WBS Shortcuts (cont.)
Here, the work is organized only by Level
63
Finding and Filtering Activities
Unleash the power of Find with
64
Finding and Filtering Activities (cont.)
65
Roles and Resource Loading
Roles are placeholders for Resources that are not yet assigned. • Roles allow teams to be assigned quickly to project activities, once the resource team is identified. • Only resources for roles that are unfilled are shown in the assign resources for roles dialogue box. • and can be used to select the activities being assigned resources by roles. • A project team could be assigned to all of the project’s activities at once. •
66
Schedule Crashing Basics
28 Days Total Duration
67
Schedule Crashing Basics (cont.)
Assume We Need to Reduce Duration by 5 Days 28 Days Total Duration
68
Advanced Layouts to Enhance Communication
• User Defined Fields • Bring in Related Data from Other Sources • Tabular + Graphic Presentation
69
Advanced Layouts to Enhance Communication (cont.)
User Defined Random Data
Schedule Data
70
Advanced Layouts to Enhance Communication (cont.)
71
Advanced Gantt Chart Formatting
72
Advanced Gantt Chart Formatting
73
Advanced Gantt Chart Formatting
74
Advanced Gantt Chart Formatting
75
Advanced Gantt Chart Formatting
76
Exporting and Importing Layouts and Reports
.plf filename extension
77
BC1
Adding Barchart Graphics to Reports
1. Create a layout that you want to print in your report 2. From the tool menu or print preview, choose Publish 3. Choose the directory for the report 4. Open a notebook topic and insert the graphic 5. Include that notebook topic in your tabular report 6. Run the report
78
Slide 78 BC1
Please doublecheck first bullet. Thanks, BC Bill Camarda, 10/17/2006
Adding Barchart Graphics to Reports (cont.)
Publish to HTML
From the Tool menu or Print Preview, choose Publish
79
Adding Graphics to Reports
80
Adding Graphics to Reports (cont.)
Click on the Picture Icon, and browse for a graphic file to insert into the Notebook topic
81
Adding Graphics to Reports (cont.)
82
83
Working with Baselines Baselines are an established method of tracking progress and measuring results When you first begin using Baselines, you may see some strange results that are difficult to diagnose Baselines can refer to either the Current Project or another Project How can you know which, without opening?
84
Working with Baselines (cont.) Sort
Add a Baseline Column ?
Why Alpha Prefix?
Baseline Code Project Date Resp
Sort by BL Name
85
Working with Baselines (cont.)
Are we a year ahead?
Is the Current Schedule Ahead or Behind the Original Plan?
86
Working with Baselines (cont.) Something is Wrong?
Summarized Dates
MAGIC!
87
Working with Baselines (cont.)
Perform a Global Change on a Baseline
88
Working with Baselines (cont.)
1
2
PL Strt = Start (Milestone): If = SM, Then, PS = Start
Here are the details...
3 89
Working with Baselines (cont.)
Here are the changes
90
Questions?