ep' * (footing width - column area) 1559.04 kN (also N for column calc.)
= at column face, max shear stress, v =
N/ud =
2.706667
<
0.8√(f cu cu)
or 5 N/mm2 N/mm2
4.732864 N/ N/mm2 Cracking spacing spacing at 3d @ 3d = 1080 mm
750 mm max
Clear spacing =
380 mm
.'. So take <
750 mm
.'. Ok
750 mm O.K
h > 200mm Bent up anchorage bond length , 38 * 20 mm rebar = 760 mm (from column face) (footing width-col width)/2-c-anchor length = 250 mm of space .'. no bent up needed