Specification for commissioningDescripción completa
Pre-commissioning and commissioning of pipeline
Specification for commissioningDescrição completa
Specification for commissioning
Pre-commissioning Manual
Pre commissioning Procedure merupakan tahapan dalam pekerjaan pembangunan IPA sebelum IPA tersebut dilakukan uji cobaDeskripsi lengkap
Pre commissioning Procedure merupakan tahapan dalam pekerjaan pembangunan IPA sebelum IPA tersebut dilakukan uji cobaDeskripsi lengkap
Pre-commissioning Manual
Pre commissioning Procedure merupakan tahapan dalam pekerjaan pembangunan IPA sebelum IPA tersebut dilakukan uji cobaFull description
Pre-commissioning Manual
Description complète
Full description
Description complète
AFBC ID Fan check listFull description
ACG Commissioning Guideline
Full description
List of items to check on the rig prior spudDescripción completa
List of items to check on the rig prior spud
commissioning.pdf
Commissioning GuidelineDescrição completa
power plant commissioning process.
power plant commissioning process.
Actually I'm preparing draft schedule for Precommissioning & Commissioning schedule for LNG Terminal Project. And I come out with these activities as follows:
Precommissioning: 1. Hydrotest of Pipelines 2. Leakage Test of Pipelines 3. Flushing & Cleaning of Pipelines 4. System dry-out 5. Inerting 6. Systematic Conformity Check of Equipment 7. Static, De-energized Test of Equipment Commissioning: 1. Preliminary Check 2. Functional Check 3. Operational Test 4. Pre-Startup activities
May I ask some advise to those who had the same experience on the questions below: Q1. Are the activities and sequence are correct? Q2. Is there any missing activity? Q2. Are these set of activities can be applied to both Utility System & Process System?
Suggest the following The items you show as precommissioning and commissioning are in fact part ot the construction, inspection and testing activities.
The basic stream of the process of commisionning is as follows: Complete all the construction, testing, and testing activities
•
Carry out the complete and all the Mecancally Completion activities.
•
Then make a precommisionng plan detailing all requirements of the "Systems"
•
These systems are detailed in the P&I D's. These can be process, utilities, firewater, safyty system,
•
Powergeneration, power distibution. lichting & small power etc. Further plan all recourses, vendor assistances, commisioning engineers, consumables an spare parts,
•
labour for assistance Establish safety and workpermit systems
•
The next step is commisioning After all the precommissioning activities are completed the commissioning can commence. Take that
•
commissioning starts when the systems "are going live". In many occasions the commissing start with the electrical en instrumentation systems, such as
•
powergenerations and distribution. Then the plantoperation systems shall be done. Etc.
•
Trust that you answers some of your questions Here some element of answers: - What you call "Preliminary checks" should be done during or before the Precom (I guess this includes the piping conformity check, instrumentation calibration, machinery alignment, Manhole closure ...) - For some systems you will not have all these activities (in particular inerting, dry-out for utilities as water ...) - For gas systems, flushing (with water) and dry out may be directly remplaced by Air blowing - For process system, you should identify the Safety valves calibration as this often is a critical activity - Some times could be identified for the closure of blocking points of the punch lists, depending on the way it works on your site