PRINTED COPY NOT CONTROLLED
PRINTED COPY NOT CONTROLLED Page 2 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
SAFE WORK PRACTICES ON LINE BREAKING TABLE OF CONTENTS
#
Page
1.0
INTRODUCTION
3
2.0
SCOPE
3
3.0
REFERENCES
3
4.0
DEFINITIONS
4
5.0
STANDARDS/GUIDELINES
6
5.1
NEW
PROJECTS
AND
MODIFICATIONS
TO
EXISTING
6
SYSTEMS
6.0
5.2
TRAINING
7
5.3
JOB PLANNING
7
5.4
SYSTEM PREPARATION
8
5.5
LOCKOUT/ISOLATION
8
5.6
JOB EXECUTION
9
HAZARDS ON WORKING ON FLARE LINES
12
6.1 SOURCE OF AIR
12
6.2
PRECAUTIONS
13
6.3
ADDITIONAL INFORMATION
14
7.0
INCIDENT INVESTIGATION
14
8.0
MANAGEMENT SYSTEMS
14
8.1
DOCUMENT CONTROL
14
8.2
AUDIT REQUIREMENTS
14
8.3
DOCUMENT RENEWAL PROCESS
15
8.4
DEVIATION PROCESS
15
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 3 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
1.0 INTRODUCTION Spreading of flange joints, disconnecting unions and removing spool pieces or bends in process and utility lines are required during most maintenance activities and tie-in related to project activities. Accidents have occurred due to negligence of safety aspects during such jobs. All parties involved in such jobs shall ensure appropriate precautions. 2.0 SCOPE To provide the minimum provisions for planning and executing all line breaks and to specify the line break considerations to be addressed at an early stage in the design process of new and modified equipment. Mandatory rules are characterized by the word “SHALL” throughout the text. Advisory rules or recommendations are indicated by the word “SHOULD”. The words shall and should have been used to remain in line with the terminology used by the American National Standards Institute. Various designations mentioned in the document are refinery based. Equivalent designations shall be applicable for other locations/ sites.
3.0 REFERENCES
− KPC HSE Document No. 24; Line Break Procedure − Maintenance Work Practices; Lock-Out/Tag-Out KNPC-SMM-1-PRC0403.
− Maintenance Work Practices; Zero Energy Test KNPC-SMM-1-PRC-0404 − Procedure for Multi-Lock System in Refineries MAA-ELAC-03-1330 − PPE Program SHE-TSOH-04-1315. − KNPC Design Engineering Practices − SWP on Work Permit & Risk Assessment SHE-TSSA-06-2029 − SWP on Plant Operations SHE-TSSA-05-2002 − SWP on Confined Space Entry SHE-TSSA-04-SP-2007
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 4 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
4.0 DEFINITIONS 4.1 Cleared —all lines and equipment associated with a system are verified by standard practices to have been positively isolated and, where appropriate, drained, flushed, and/or purged of hazardous material, and made ready for hotwork as applicable and the following criteria are met:
− The system’s temperature is lower than 140°F (60°C) and higher than 14°F (-10°C).
− Atmospheric pressure has been attained. − Hazards associated with toxicity, corrosiveness, flammability of gases, vapors, or mists, and/or airborne combustible dust are reduced to acceptable levels, that is meeting normal operating conditions. 4.2 Controlled bleed —a valved opening (bleed) located between two block valves. The bleed consists of an open block valve and terminates with an open end or pressure gauge. The bleed serves as an indicator of the integrity of the upstream block valve. Selection and positioning of the bleed termination point are dependent on the hazards associated with the process material and local conditions at the time of the line break. 4.3 Double isolation —double block valve and controlled bleed (i.e., block valve/controlled bleed/block valve) or block valve and blank/blind flange. 4.4 Engineered process plug —a means of isolating process flow by solidifying a portion of the process in a pipeline in a controlled, predesigned, and approved manner. 4.5 Front-end loading —design activities before final design and approval executed to uncover possible hidden problems and expense. 4.6 Hazardous process or system —a process or system that contains any material at any pressure that could cause an injury to an individual(s), a possibility of fire or explosion, an environmental hazard, or an off-site hazard. Examples of hazardous processes or systems include, but are not limited to, compressed fluids, especially gases in pipes and vessels; corrosive and/or flammable substances; and other lines that could contain
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 5 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
material that is hazardous on contact or inhalation, including fluid whose temperature is higher than 140°F (60°C) or lower than 14°F (-10°C). 4.7 Isolation—Complete obstruction and elimination of flow to system (piping or equipment) ensuring full protection against the release of fluid to the system by means such as blinding, removal of section of piping (along with blinding the live end), double block and bleed system, manually valved and/or blanked or blind flanged etc to completely isolate the line or equipment from the process material and documented such isolation by blind lists and locations clearly identified by tags. 4.8 Line break —opening cleared or uncleared lines or equipment that has contained any fluid at a volume, pressure or temperature capable of causing injury or damage to property by actions that may include, but are not limited to, the following:
− Breaking flanges − Removing one or more bolts from flanges − Removing valve bonnets and non-return (i.e., check) valves − Turning spectacle plates (i.e., blanks) − Breaking pipe joints − Removing slip plates (i.e., blanks), instrument orifice plates, blind flanges, plugs, and caps
− Disconnecting tubing − Disconnecting loading and unloading process hoses − Penetrating a line by mechanical or other means − Opening inspection ports − Making subtle adjustments (e.g., replacing packing on a valve) 4.9 PPE —Personal Protective Equipment. 4.10
Qualified personnel —those who by extensive knowledge, training, and
experience have successfully demonstrated their ability to solve or resolve problems related to line breaks in accordance with this document.
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 6 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
5.0 STANDARDS/ GUIDELINES 5.1 NEW PROJECTS AND MODIFICATIONS TO EXISTING SYSTEMS Operations Dept.,/ Process Engg. Division shall work with Asset Custodian Dept/ Division during the design and engineering stages of a project so that line break issues are considered in both new projects and modifications to existing systems. Systems shall be designed and built to enable isolation and clearing of the hazard. The following points shall be considered: 1. Isolation and clearing shall be primary considerations during project front-end loading activity.
− The design shall consider the balance between added potential leak points (catastrophic and fugitive) vs. the benefit of providing additional connections for flushing and clearing access to systems and equipment.
− The design shall include the ability to isolate secondary energy sources for polymer and melt systems where the material is “frozen” (i.e., solidified) to eliminate the hazard.
− All systems shall be designed with the ability to isolate secondary energy sources. Examples of secondary energy sources include steam and electric tracing and jacketed vessels and pipe. 2. Experienced field operators and mechanics shall be involved in the front-end loading efforts. 3.
The design team shall consider the following hierarchy for isolating hazardous processes. The decision should be based on the level of protection to people and environment vs. additional hazards introduced as the result of adding additional valves. a. Double block valve and controlled bleed b. Block valve and blank/blind flange c. Double block valves d. Single block valve e. Engineered process plug (i.e., solidifying the process)
If neither double block valve and controlled bleed or block valve and blank/blind flange isolation is feasible, then appropriate safeguards Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 7 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
(for example regular testing of single valves) shall be provided, documented, and included as a part of the Hazop study. 5.2 TRAINING Team Leader of the Executing Dept shall ensure that qualified personnel perform all work on hazardous processes or systems, including planning and execution. Team Leaders of Executing and Asset Custodian Departments shall also ensure that training is provided to persons involved on line break procedures. The topic shall be included in the SHE training program at SHE Training Center. Key elements for determining personnel qualifications are listed below: 1.
Initial training shall be provided for
− Operating personnel, including supervisors. − Maintenance and construction personnel, including supervisors. − Contractors and contract administrators. − Planners/schedulers. − Personnel who issue line break permits. 2.
Refresher Training shall be provided every 3 years.
3.
Training shall be documented.
4.
There should be a system to check that the training had been effective.
5.3 JOB PLANNING 1.
A written Risk Assessment that specifically addresses safety, health,
and
environmental
issues
shall
be
prepared
and
implemented for all line breaks on hazardous processes and systems. This shall be as per document: SHE-TSSA-06-2029 SWP Work Permit & Risk Assessment. 2.
A line break permit shall be issued and precautions as per the Risk Assessment shall be mentioned in the Permit.
3.
Personnel performing the work shall be made aware of the safety, health, and environmental requirements. The Issuer and Executor shall ensure that the plan details are communicated to all the
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 8 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
personnel involved. These details include lockout points, flushing and clearing, and standby person responsibilities. 4.
Team Leaders of the Custodian and Executing Dept shall ensure that a process is in place to do the following:
a.
Periodically review the Risk Assessment for inclusion of all mandatory requirements of this document.
b.
Document the line break training and periodic retraining of the people performing the routine line break jobs
5.4 SYSTEM PREPARATION The system must be properly prepared before line breaks are made on any system. Key elements for proper system preparation include establishing and verifying acceptable levels of cleanliness, elimination and verification of chemical hazards. The clearing and draining of pipelines and equipment must follow approved waste management procedures to protect the environment. 5.5 LOCKOUT / ISOLATION All systems prepared for line breaks shall be properly isolated. The following documents shall serve as a guideline in this regard
- Maintenance Work Practices; Lock-Out/Tag-Out KNPC-SMM-1-PRC-0403. - Maintenance Work Practices; Zero Energy Test KNPC-SMM-1-PRC-0404 - Procedure for Multi-Lock System in Refineries MAA-ELAC-03-1330 - KNPC Blinding Deblinding Procedure The following points shall be considered in isolation: 1. Tagging procedure: Systematic tagging of blinds used for positive isolation of lines and equipment. Blanks and blind flanges shall be tagged as described in the above document. 2. The bleed (drain/ vent) valve (for block & bleed) for the isolated system shall be maintained in the open position and the line cleared to prevent trapping process material in the line/equipment. 3. The specific steps for isolating all primary and secondary (e.g., steam tracing, electric tracing, cathodic protection etc) energy sources shall be identified.
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 9 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
This is especially important in polymer and melt systems that are “frozen” (i.e., solidified) to isolate them and for acids that can vaporize if cooled and then reheated. 4. Various means of isolating systems or equipment that contain hazards can be used. A listing, from the most protective to the least protective, is given under 5.1 (3). Examples of manual valves used for isolation are gate valves, plug valves, and ball valves. The use of control valves for isolation is not allowed. 5. The degree of isolation depends on the hazards of the material being isolated, the surrounding area (including its electrical classification), the configuration of the piping system, the frequency of the line break, the added chance of leaks from additional isolation valves, and the experience gained from past line breaks. 6. Where work on hazardous systems is to be performed behind a single blocking valve, the line break permit or procedure shall indicate how the hazard is to be mitigated, including worst-case scenarios and contingency plans. 5.6 JOB EXECUTION The first break does not always verify that the system or equipment is free of hazard. Experience has shown that incidents still occur after the first break is completed. These incidents have a variety of causes, including trapped pockets of pressure or hazardous process material, not isolating all sources of pressure or hazardous process material, or not draining the low point and venting the high point. The following documents shall be referred for further guidance.
- SWP on Work Permit System and Risk Assessment;SHE-TSSA-06-2029 - SWP on Confined Space Entry:SHE-STSA-04-SP-2007 - SWP on Plant Operations: SHE-TSSA-05-2002 Rev 1 (Sec 8: Safe Operating Practices) 1. Permit issuer shall ensure that the system is properly prepared before any line breaks are made. If clearing cannot be accomplished as Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 10 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
expected, the job shall be stopped and the following steps shall be performed: re-plan, document, authorize, and communicate. 2. Maintenance personnel should never break a line without obtaining a work permit from the Operations Supervisor. The work should proceed only after Operations has clearly identified the flanges that are to be opened. 3. Presence of permit issuer is essential at the work site during the commencement of line break and also during lining up after completion of job. 4. All parties involved in the line breaking shall be made aware of the status of the equipment and the hazards involved. 5. Proper protective clothing and equipment are worn if toxic, corrosive or other harmful substances could be present. 6. Lines and equipment are drained or depressurized of all possible contents of flammable, corrosive liquid and toxic contents or asphyxiating gas before opening. 7. Operations supervisor assures to the Maintenance personnel that there are no naked lights, fires or other sources of ignition within 15m radius, especially downwind of the line of the equipment to be opened. Hot work Permits shall not be issued within this radius. 8. Ensure that both sides of the flange are properly supported/anchored to avoid falling or spring action. 9. Workers should remain upwind, loosen the bolts without fully removing them and spread the joint slightly to check that it has no pressure. 10. The area shall be barricaded to warn people not involved in the line break of any unexpected release of hazardous material. 11. The location shall be monitored continuously for presence of toxic or flammable gases if required by the permit. Necessary monitoring equipment shall be available at site. 12. Note the location of safety shower before commencing work on chemical lines.
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 11 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
13. The joint shall be opened very slowly to ensure that there is no hold-up of gas or liquid and that block valves are holding. 14. Slacken the bolts farthest away from the person first. Do not remove the last bolt until inserting a wedge at far end to remove any remaining content. Work above the flange and not below. 15. Precautions are taken to contain the leftover material/sludge and minimize spillage. (providing drip tray, diking, etc) 16. Waste management guidelines issued by Environment Division shall be followed in the handling and disposal of waste. 17. If it appears that the line is under pressure, the joint should be closed immediately and reopened only under the direction of Operations supervisor after corrective action has been taken. In such cases the job plan shall be reviewed. The Risk Assessment will have to be reviewed again before proceeding further in such cases. 18. Use non-sparking tools when working on hydrogen, ethylene, acetylene and carbon disulphide lines. 19. Lines or vessels shall be considered full or hazardous until proven safe for work 20. When work spans over two shifts the next shift people shall be made aware of the ongoing job. 21. Steam Lines: It is possible that there could be presence of hydrocarbons in steam lines.
This occurs when process units are
subjected to emergency shutdowns including the steam system. This could create vacuum conditions in the steam line sucking in hydrocarbons. It is therefore advisable to conduct gas tests during blinding/ deblinding of steam lines also. 22. Other Utility Lines: (Plant Air, Instrument Air, Nitrogen line, Water lines including Sea Water). All utility lines shall be considered as hydrocarbon contaminated.
Gas tests shall be conducted during
spreading of the flange and precautions & procedures determined accordingly.
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 12 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
23. Modified Blinds: Large volatile hydrocarbon lines with passing valves shall
be
blinded
with
modified
blinds
which
have
a
draining/depressurising connection especially when the system is under pressure beyond the isolation valve. Content between valve and the blind shall be emptied before deblinding. 24. Double Block & Bleed: Some high pressure or hazardous content lines are provided with two block valves separated by a spool piece that has a bleed connection vented to a safe location. Any passing material will be vented instead of reaching the danger end. 25. Unions: Inserting a disc between union faces is not considered as positive isolation. Union shall be disconnected and capped/plugged at the danger end. 26. Blinds that were in position for a long time should be removed and inspected before being used as positive isolation. 27. When taking into service, the system shall be checked at full operating conditions, for example hot bolting where required.
6.0 HAZARDS OF WORKING ON FLARE LINES Work on flare lines is far more susceptible to mishaps than are most other plant piping arrangements. Hazards associated with such work and means of carrying out the work safely are mentioned below 6.1 SOURCE OF AIR: Keeping air out of a flare system is of paramount importance. Air is most likely to find its way into a flare system in one of the following ways: 1. Through open vents, drains or other connections 2. When flare lines are opened for maintenance or other system repair 3. While venting equipment (for example during start-up) into the flare system 4. By the rapid condensation of hot vapour inducing a vacuum and pulling air back into the system through the flare stack and seal. 5. Air is most likely to enter when a section of the system is to be gas freed to permit 'hot work' on lines or equipment in preparation for Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 13 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
entering system vessels or in connection with work on the flare and its auxiliaries. A combustible mixture can reach the flare during blinding or gas freeing of lines. 6.2 PRECAUTIONS Flare lines should be purged with steam or inert gas before connected equipment or lines are opened (i.e. before permitting entry of air). Purging is especially important as flare streams contain H2S or pyrophoric iron sulfide deposits providing an ignition source when air is admitted. The procedures given below shall be followed during shutdown and maintenance activities:1. Shutdown all units serviced by the flare system before the flare is taken out of service or else line up standby flare system if available. 2. Replace sweep gas with purge gas and continue until all system bleeders test as safe. 3. Ensure that purge gas gets into all laterals in a complex flare system, not just to the main collection header. 4. Extinguish flare pilot. 5. Blind all flare header inlets from the units as per the blind list and notify all concerned personnel of the system's status. 6. All personnel during blinding/deblinding jobs shall wear airline masks or SCBA and fire retardant clothing. 7. Purge gas shall be maintained at all times during the blinding operation. 8. All mobile equipment shall be located upwind wherever possible. 9. Proper access facilities and work platforms shall be provided. More than one ladder shall be provided to work platform as a means of emergency escape. 10. Water spray systems and other fire protection shall be available at location.
A continuous water curtain shall be provided between
work area and adjacent operating refinery units. 11. All connected unit personnel are alerted before the start of the job. Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 14 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
12. All material are available on site before work starts. 13. Sufficient bolts shall remain while a gradual opening is made by the use of a flange spreader. 14. Once work has begun, continue without stopping until the job is completed. 6.3 ADDITIONAL INFORMATION 1. Even with pilots extinguished and no pyrophoric material present, autoignition still can occur so long as oxygen is present. 2. Hydrogen and hydrogen sulfide are especially hazardous due to their broad flammability limits in air 4-74% and 4-45% respectively. 3. Lines from knockout drums to flare stacks and the flare stacks themselves should drain back by gravity to the knockout drum. 4. While water washing of flare lines and KOD, hydrogen sulfide and ammonium salts are released. It is possible that units and facilities get contaminated with hydrogen sulfide as this wash water is carried enroute to Waste Water Treatment facilities.
7.0 INCIDENT INVESTIGATION All line break incidents shall be investigated according to KNPC Incident Investigation Procedure.
8.0 MANAGEMENT SYSTEMS 8.1 DOCUMENT CONTROL Records shall be retained in compliance with the KNPC Document Control Programme. The contact for this document is the KNPC SH&E Department. 8.2 AUDIT REQUIREMENTS Compliance with this document shall be audited as part of SHEMS audit program. 8.3 DOCUMENT RENEWAL PROCESS This document shall be reviewed and revised by KNPC SHE Dept as necessary and, at a minimum, not later than three years from the date of the last revision. Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking
PRINTED COPY NOT CONTROLLED Page 15 of 15
KUWAIT NATIONAL PETROLEUM COMPANY
8.4 DEVIATION PROCESS Deviations from this document shall be authorised by the Manager SH&E. Deviations shall be documented, and documentation shall include the relevant facts supporting the deviation decision. Deviation authorization shall be renewed periodically and no less frequently than every three years.
Reference: SHE-TSSA-07-2026 ( Rev 0) Date of Issue: June 2007
Title: SWP on Line Breaking