NPV Calculation for one branch Input values System cost System size
Total Total system cost cost Efciency rating Salvage value Salvage value
Ta! Ta! cre"it cre"it
Year Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1,
-105000 18% 15% o systems cost 15750
#0$00%
/ereciation er year Ta! Ta! rate Ta! Ta! cre"it cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-1000 #8% #0%
-0$50%
KWH production production KW by solar solar #,5$00 #5##$7 #1,$07 #.8$.. #18$50 #0,,$58 .51$5 8#,$. 7$#1 ,08$70 .5$,, #8#$18 71$,
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
15.$.1 0.$11 1.#8$8,
$5# $5 $50
Systems cost cost *105000$00+
17 18 1. 0 1 # 5 , 7 8 . #0
18.$17 170$0 1,11$ 150#$#, 1#.5$85 188$87 118$ 107,$51 0.71$1# 08,,$7 07,1$. 0,58$1# 055$8 05$07
$. $8 $7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total Total S2P re3ate re3ate
15$00 0$18 87,0$00 #,5$00
1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3l Possi3le e scenario scenarioss- t4ere t4ere may 3e c4anges c4anges in t4e variou various s costs costs -mosty -mosty increas increas
17 18 1. 0 1 # 5 , 7 8 . #0
18.$17 170$0 1,11$ 150#$#, 1#.5$85 188$87 118$ 107,$51 0.71$1# 08,,$7 07,1$. 0,58$1# 055$8 05$07
$. $8 $7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total Total S2P re3ate re3ate
15$00 0$18 87,0$00 #,5$00
1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3l Possi3le e scenario scenarioss- t4ere t4ere may 3e c4anges c4anges in t4e variou various s costs costs -mosty -mosty increas increas
Input
Base case- as givenMinimum
Most Likely
Electricity Price ro
3% (given)
7%
:aintenance ;ost
2% (given)
3.50%
Additional Maintenance, Year 5
$400/kW (given)
$550/kW
!nverter "e#laceent, Year
$250/kW (given)
$400/kW
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
0.65%
!n&'rance o&t +rot"ate
2% (given)
5%
Calculation of the salvage value System cost -105000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -1000 15750 0
Ta! Ta! cre"it cre"it on salvage value
#%
.7,5
yr yr yr yr
-8.50 -17850
KW %
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-5.85
)ter ta! salvage value
2n KW>
for for for for
%
Insurance &aint costs 'otal &ain cost
SIP rebate 081$1
0$17 0$18 0$18 0$1. 0$1. 0$0 0$0 0$1 0$ 0$ 0$# 0$ 0$
00$8 10$7, #$1, #8$10 #5$,, 55$88 ,58$85 77$, 8.#$7 501$87 51#.$. 5,7$0 5#.8$0.
*15$00+ *15$#0+ *15$,1+ *15$.+ *1,$+ *1,$5,+ *1,$8.+ *17$#+ *17$57+ *17$.#+ *18$8+ *18$,5+ *1.$0+
*5$00+ *.$50+ *#$0.+ *#8$77+ *#$55+ *8$+ *5#$#.+ *58$5+ *,#$,+ *,8$.0+ *7$7+ *7.$7,+ *85$#5+
*#15$00+ *#1$#0+ *#7$7#+ *##$8+ *#0$.7+ *#7$7.+ *#5$7+ *#,1$8+ *#,.$07+ *#7,$5+ *#8#$.8+ *#.1$,,+ *#..$50+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
0$5 0$, 0$,
55#$ 5,,.$71 5810$,1
*1.$0+ *1.$7.+ *0$1.+
*.1$0,+ *,.,$88+ *#0$8+
*07$.+ *15$,+ *#$.5+
0$00 0$00 0$00
0$7 0$8 0$. 0$#0 0$#1 0$# 0$## 0$# 0$#5 0$#, 0$#7 0$#8 0$#. 0$0
5.55$00 ,10$.8 ,5$, ,10$07 ,5,.$#, ,7#$,1 ,8..$.1 7071$#7 77$10 77$1. 7,11$75 7800$.1 7..$7, 81.#$#
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*0$5.+ *1$00+ *1$+ *1$85+ *$.+ *$7#+ *#$1.+ *#$,5+ *$1#+ *$,1+ *5$10+ *5$,0+ *,$1+ *,$,+
*058$88+ *#15$05+ *#1$#,+ *#7$78+ *##$#+ *#1$0+ *#7$85+ *#5$80+ *#,1$.0+ *#,.$1+ *#7,$5+ *#8$05+ *#.1$7#+ *#..$57+
*#$#+ *1$08+ *.$.0+ *58$.0+ *,8$07+ *77$#+ *8,$.8+ *.,$7+ *50,$,,+ *51,$7.+ *57$1#+ *5#7$,7+ *58$+ *55.$#.+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
Maximum
% 5% $700/k
$550/k
!.00%
"%
*$+
!,-*.$ #,--*-. /#/$*/" .$%.*"-
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8.18$5.+ #1500$00 *5118$5.+ *5118$5.+ *17850$00+ *1#,.$1,+ *5,0$8+ *8.08$88+ 8.1$1 *17850$00+ *180$0+ *5,$+ *885#$,#+ 8..,$#7 *17850$00+ *1188$,,+ *5#.1$,.+ *87.,$.7+ .05#$0# *17850$00+ *10.$.5+ *5#5,$08+ *87#8$87+ .111$1# *17850$00+ *1#..8$8,+ *5#1.$57+ *8,7.$.+ .170$71 #..$,8 1500$88 8$80 8$80 050$7 15#.$7 511$5 511$5 15$## 1578$,5 575$,. 575$,. ,0$57 1,1.$0 ,1$5, ,1$5, #,.$5 1,,0$ 70.$10 70.$10 81$# 170$87 778$#, 778$#, 5.5$78 17,$0 8.$#8 8.$#8 71#$ 17.1$0# .$1 .$1 8##$,. *10$81+ 508#$8
18#,$80 *#.,$7+ 1.#1$8,
..,$8. *,,$5+ #151$.8
..,$8. *,,$5+ #151$.8
1,#$,. 5#,$85 58#$#. 5,#$#. 57,,$.5 5.1$15 ,0,5$08 ,1.$85 ,#78$5 ,51$, ,708$11 ,87.$1. 705$,1 7#$7
55,$0 0#1$80 08#$,. 1#,$8. 1.1$ 7$#8 #0$7# #,#$5 #$85 85$,8 5.$08 ,1$0. ,80$75 7.$10
.07$. ##15$05 ##..$70 #8,$50 #575$51 #,,,$77 #7,0$#5 #85,$#1 #.5$70 055$58 15.$0# ,5$10 #7#$8, 85$#7
.07$. ##15$05 ##..$70 #8,$50 #575$51 #,,,$77 #7,0$#5 #85,$#1 #.5$70 055$58 15.$0# ,5$10 #7#$8, 85$#7
Input values System cost System size
Total system cost Efciency rating Salvage value Salvage value
Ta! cre"it
Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1, 17 18
-105000 18% 15% o systems cost 15750
#0$00%
/ereciation er year Ta! rate Ta! cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-1000 #8% #0%
-0$50%
KWH production KW by solar #,5$00 #5##$7 #1,$07 #.8$.. #18$50 #0,,$58 .51$5 8#,$. 7$#1 ,08$70 .5$,, #8#$18 71$,
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
15.$.1 0.$11 1.#8$8, 18.$17 170$0
$5# $5 $50 $. $8
Systems cost *105000$00+
.7,5$00
1. 0 1 # 5 , 7 8 . #0
1,11$ 150#$#, 1#.5$85 188$87 118$ 107,$51 0.71$1# 08,,$7 07,1$. 0,58$1# 055$8 05$07
$7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total S2P re3ate
15$00 0$18 87,0$00 #,5$00
1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3le scenarios- t4ere may 3e c4anges in t4e various costs -mosty increas
Calculation of the salvage value System cost -105000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -1000 15750 0
Ta! cre"it on salvage value
KW 5%
0$17 0$18 0$1. 0$1 0$ 0$ 0$, 0$7 0$. 0$#1 0$## 0$#, 0$#8
00$8 80$7. 557$5 85$1. 51,5$88 5..$85 5855$ ,##$.7 ,,#7$00 70,,$08 75$.0 800.$, 857$0,
0$1 0$ 0$7 0$50 0$5
.078$## .,,5$ 10.0$10 10.55$#, 11,,#$,
yr yr yr yr
.7,5
2n KW>
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-5.85
)ter ta! salvage value
7%
for for for for
5%
Insurance &aint costs 'otal &ain cost *15$00+ *15$75+ *1,$5+ *17$#,+ *18$#+ *1.$1+ *0$10+ *1$11+ *$1,+ *#$7+ *$#+ *5$,,+ *,$.+
SIP rebate 081$1
*5$00+ *#,$5+ *8$0,+ *,0$7+ *7#$.+ *87$1,+ *#01$5+ *#1,$,0+ *##$#+ *#.$05+ *#,,$50+ *#8$8#+ *0$07+
*,8$50+ *71,$,#+ *75$,+ *7.0$08+ *8.$58+ *871$0,+ *.1$,+ *.,0$#5+ *1008$#,+ *1058$78+ *1111$7+ *11,7$#1+ *15$,7+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
*8$8+ *$7+ *.$70+ *10.5$8+ *#1$18+ *,7$7,+ *#$7+ *871$15+ *#$#8+ *515$70+
*18,$.,+ *1#51$#0+ *118$87+ *18.$81+ *15,$#0+
0$00 0$00 0$00 0$00 0$00
0$57 0$,1 0$,, 0$70 0$75 0$81 0$8, 0$. 0$.. 1$0, 1$1# 1$1
117$,7 1#0$8 1075$18 1.85$1 15.5#$.# 1,.85$#5 1808#$5 1.5$55 0.7$# 18$#7 ###$1. 7#5$1
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*#,$10+ *#7$.0+ *#.$80+ *1$7.+ *#$88+ *,$07+ *8$#8+ *50$80+ *5#$#+ *5,$00+ *58$80+ *,1$7+
*51$.+ *5,8$5,+ *5.,$..+ *,,$8+ *,58$18+ *,.1$0.+ *75$,5+ *7,1$.#+ *800$0#+ *80$0#+ *88$0#+ *.,$1#+
*1,$5+ *17$,+ *1810$88+ *1.01$+ *1..,$.+ *0.,$#1+ *01$1#+ *#11$1.+ *,$75+ *58$08+ *,75$.+ *80.$,+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
*$+
%-$%*$. "/-/,*," #"!-*// #-#%-*$"
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8.18$5.+ #1500$00 *5118$5.+ *5118$5.+ *1000$00+ *1788,$,,+ *,7.,$.#+ *1108.$7#+ ..10$7 *1000$00+ *17,7$0.+ *,715$#.+ *10.5,$,.+ 100#$#1 *1000$00+ *17$.8+ *,,8$##+ *1081$,5+ 10185$#5 *1000$00+ *171.8$#,+ *,5#5$#8+ *10,,$.8+ 10##7$0 *1000$00+ *717$1.+ *75$#+ *,$7,+ 1,55#$ #1$,# 1,.$8 ,.1$81 ,.1$81 ,#.$8 17,$.# 87,$#5 87,$#5 .57$0# 188#$,7 #07#$#, #07#$#, 5.,$1 01$5, #8#$,5 #8#$,5 5,58$5 150$1# #508$11 #508$11 ,0$,8 .,$.8 #77$70 #77$70 ,57$1 5#$71 00#$ 00#$ ,8.7$# ,0$.8 7,$# 7,$# 7#,7$10 *,#1$5+ 80#$7 7$0 .58#$,1
7..$50 *...$..+ #1.#$# 75$7 #,1$77
5,7$,0 *1,#1$5,+ 510$15 .$1# 5.1$8
5,7$,0 *1,#1$5,+ 510$15 .$1# 5.1$8
10##$,7 10.7$7 11,,7$#1 15,$88 1#..$, 11.7$. 1515,$,8 1,17.$# 1770$5 18#$, 1.,75$,7 0...$8
#888$7. 15$#, ##$58 7##$,1 505#$7 5#.5$ 575.$5 ,18$18 ,5,$77 7005$0 77,$7, 7.7.$.#
,#$87 ,77$.1 7##$7# 77#$7 85$5 880$7# .#.7$1 100#1$5 10707$,8 11.$ 11.8$. 1#01.$8.
,#$87 ,77$.1 7##$7# 77#$7 85$5 880$7# .#.7$1 100#1$5 10707$,8 11.$ 11.8$. 1#01.$8.
Input values System cost System size
Total system cost Efciency rating Salvage value Salvage value
Ta! cre"it
Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1, 17 18
-105000 18% 15% o systems cost 15750
#0$00%
/ereciation er year Ta! rate Ta! cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-1000 #8% #0%
-0$50%
KWH production KW by solar #,5$00 #5##$7 #1,$07 #.8$.. #18$50 #0,,$58 .51$5 8#,$. 7$#1 ,08$70 .5$,, #8#$18 71$,
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
15.$.1 0.$11 1.#8$8, 18.$17 170$0
$5# $5 $50 $. $8
Systems cost *105000$00+
.7,5$00
1. 0 1 # 5 , 7 8 . #0
1,11$ 150#$#, 1#.5$85 188$87 118$ 107,$51 0.71$1# 08,,$7 07,1$. 0,58$1# 055$8 05$07
$7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total S2P re3ate
15$00 0$18 87,0$00 #,5$00
1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3le scenarios- t4ere may 3e c4anges in t4e various costs -mosty increas
Input
Base case- as givenMinimum
Most Likely
Electricity Price ro
3% (given)
7%
:aintenance ;ost
2% (given)
3.50%
Additional Maintenance, Year 5
$400/kW (given)
$550/kW
!nverter "e#laceent, Year
$250/kW (given)
$400/kW
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
0.65%
!n&'rance o&t +rot"ate
2% (given)
5%
Calculation of the salvage value System cost -105000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -1000 15750 0
Ta! cre"it on salvage value
yr yr yr yr
.7,5
2n KW>
KW 5%
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-5.85
)ter ta! salvage value
.%
for for for for
8%
Insurance &aint costs 'otal &ain cost
SIP rebate 081$1
0$17 0$1. 0$0 0$ 0$ 0$, 0$. 0$#1 0$# 0$#7 0$0 0$ 0$8
00$8 #,0$80 7.$51 51.$#. 55,#$08 ,0##$ ,5#$5, 70.,$8 7,.,$8, 8#7$,# .05#$ .818$88 10,.$07
*15$00+ *15$75+ *1,$5+ *17$#,+ *18$#+ *1.$1+ *0$10+ *1$11+ *$1,+ *#$7+ *$#+ *5$,,+ *,$.+
*5$00+ *#,$5+ *8$0,+ *,0$7+ *7#$.+ *87$1,+ *#01$5+ *#1,$,0+ *##$#+ *#.$05+ *#,,$50+ *#8$8#+ *0$07+
*1050$00+ *11#$00+ *1$7+ *1#$70+ *18$51+ *15$7.+ *1,,,$+ *17..$5+ *1.#$8+ *0.8$.5+ *,,$87+ *8$+ *,$08+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
0$5 0$57 0$, 0$,7 0$7
115.$5 155$., 1#585$0# 17##$, 15.7.$#7
*8$8+ *$7+ *.$70+ *10.5$8+ *#1$18+ *,7$7,+ *#$7+ *871$15+ *#$#8+ *515$70+
*855$,0+ *#08$05+ *###0$78+ *#5.7$+ *#885$0+
0$00 0$00 0$00 0$00 0$00
0$80 0$87 0$.5 1$0 1$1# 1$# 1$# 1$7 1$,0 1$7 1$.0 $07
17##0$ 187.5$71 0#8$8. 108$# #.77$70 ,005$01 80#$7 #0588$#, ##17$,1 #5.7.$5 #.01$5. #0$87
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*#,$10+ *#7$.0+ *#.$80+ *1$7.+ *#$88+ *,$07+ *8$#8+ *50$80+ *5#$#+ *5,$00+ *58$80+ *,1$7+
*51$.+ *5,8$5,+ *5.,$..+ *,,$8+ *,58$18+ *,.1$0.+ *75$,5+ *7,1$.#+ *800$0#+ *80$0#+ *88$0#+ *.,$1#+
*1.5$8+ *5#1$.+ *8.$01+ *585$5#+ *5708$#7+ *,1,5$0+ *,,58$+ *71.0$.0+ *77,,$17+ *8#87$,+ *.058$,+ *.78#$1+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
Maximum
% 5% $700/k
$550/k
!.00%
"%
*$+
,-#/*/! "/!,#*!. #"/,-*$, #/!!"*!$
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8.18$5.+ #1500$00 *5118$5.+ *5118$5.+ *1000$00+ *185$1,+ *,.#,$58+ *11#17$58+ .,8$ *1000$00+ *1800.$5+ *,8#$5.+ *111,5$8,+ .8#$1 *1000$00+ *177#$7+ *,7$+ *11000$8#+ ....$17 *1000$00+ *175#$78+ *,,#$#+ *1081$#+ 10178$,, *1000$00+ *7#7#$.+ *80$0.+ *571$8#+ 1,8$17 0#$8 15.7$# ,0,$1, ,0,$1, 575$8 17#8$81 8#7$01 8#7$01 .80$71 18.$,7 #088$0 #088$0 50$.5 05.$., ##,0$.. ##,0$.. 58..$, 1$8, #,57$77 #,57$77 ,0$05 #.$, #.80$# #.80$# ,.85$8 ,5$, ##1$ ##1$ 7,00$.# 888$#5 71$57 71$57 8,.$57 *150#$58+ .78,$. #.5$5 11578$,5
#1$ *571$#,+ #718$87 .10$0 #..$8.
517$1 *.#$+ ,0,7$, 185$0, 7178$7,
517$1 *.#$+ ,0,7$, 185$0, 7178$7,
15.#$11 1#,.5$,, 18.#$8. 1,1.,$07 17,11$15 1.18$88 081.$85 ,#5$5 ,08$1 ,75$0# .081$10 #1,11$,0
785$#8 50$#5 5,5.$,8 ,15$50 ,,.$ 77,$58 7.11$5 8,01$50 .#51$0 101,5$77 11050$8 101$1
7807$7# 8.1$#1 .#$1 1001$5, 10.18$.1 1187$#1 1.08$#1 10#$0# 1557$ 1,58,$, 180#0$8 1.5..$1.
7807$7# 8.1$#1 .#$1 1001$5, 10.18$.1 1187$#1 1.08$#1 10#$0# 1557$ 1,58,$, 180#0$8 1.5..$1.
Input
#
Base case- as given-Minimum
Electricity Price rot4 &at
130 *r&
3% (given)
:aintenance ;ost rot4
12 *r&
2% (given)
Additional Maintenance, Year 5
1 5 *r&
$400/kW (given)
!nverter "e#laceent, Year
1 *r&
$250/kW (given)
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
!n&'rance o&t +rot- "ate
2% (given)
#
Most Likely
#
Maximum NPV
3034.5
7%
435.5
%
244.4
5%
646.
5%
6265.6
$700/k
2034.66
$700/k
5.4
$550/k
2424.5
$550/k
0.65%
!.00%
5%
"%
.#,$,0 1,0.$08 1,.$5. ,001$05
Input values System cost System size
Total system cost Efciency rating Salvage value Salvage value
Ta! cre"it
Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1, 17 18
-#15000 18% 15% o systems cost 750
#0$00%
/ereciation er year Ta! rate Ta! cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-,#000 #8% #0%
-0$50%
KWH production KW by solar 70.5,$00 70,01$ 708$1 ,.8.,$.7 ,.57$. ,.1..$75 ,885#$75 ,850.$8 ,81,,$. ,78,$10 ,78,$.7 ,71.$5 ,,81#$7.
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
,,7.$7 ,,17$# ,581,$58 ,587$50 ,51,0$0,
$5# $5 $50 $. $8
Systems cost *#15000$00+
1. 0 1 # 5 , 7 8 . #0
,8#$, ,510$0. ,187$5 ,#8,,$,0 ,#57$7 ,#.$5# ,.1#$#. ,5.8$8 ,85$8# ,1.7$0 ,1,,$5 ,1#5,$0
$7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total S2P re3ate
..5$00
15$00 0$18 87,0$00 #,5$00 70.5,$00 1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3le scenarios- t4ere may 3e c4anges in t4e various costs -mosty increas
Input
Base case- as givenMinimum
Most Likely
Electricity Price ro
3% (given)
7%
:aintenance ;ost
2% (given)
3.50%
Additional Maintenance, Year 5
$400/kW (given)
$550/kW
!nverter "e#laceent, Year
$250/kW (given)
$400/kW
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
0.65%
!n&'rance o&t +rot"ate
2% (given)
5%
Calculation of the salvage value System cost -#15000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -,#000 750 0
Ta! cre"it on salvage value
yr yr yr yr
..5
2n KW>
KW %
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-17.55
)ter ta! salvage value
#%
for for for for
%
Insurance &aint costs 'otal &ain cost
SIP rebate ,,$#
0$17 0$18 0$18 0$1. 0$1. 0$0 0$0 0$1 0$ 0$ 0$# 0$ 0$
10,$5 1#,$7 1,,.$8 1.8$#1 1##0,$.7 1#,#7$,5 1#.7,$55 1##$8, 1,7.$81 150$,1 1518$, 15801$,1 1,1.$8
*15$00+ *15$#0+ *15$,1+ *15$.+ *1,$+ *1,$5,+ *1,$8.+ *17$#+ *17$57+ *17$.#+ *18$8+ *18$,5+ *1.$0+
*,75$00+ *,88$50+ *70$7+ *71,$#+ *7#0$,+ *75$5+ *7,0$1,+ *775$#,+ *7.0$87+ *80,$,.+ *8$8+ *8#.$8+ *85,$0,+
*.5$00+ *.,#$.0+ *.8#$18+ *100$8+ *10$.0+ *10#$#,+ *10,$+ *1085$51+ *1107$+ *11.$#,+ *1151$.5+ *117$..+ *11.8$.+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
0$5 0$, 0$, 0$7 0$8
1,5.,$71 1700.$1 17#1$8 178,5$00 18#08$.
*1.$0+ *87#$18+ *1.$7.+ *188.0$,5+ *0$1.+ *.08$,+ *0$5.+ *117,$,#+ *1$00+ *.5$1,+
*1$,+ *1,$.1+ *171$85+ *1.7$8+ *1##$#+
0$00 0$00 0$00 0$00 0$00
0$. 0$#0 0$#1 0$# 0$## 0$# 0$#5 0$#, 0$#7 0$#8 0$#. 0$0
187,#$. 1.#0$0 1.708$07 01.7$8 0,..$7# 11$1 171$. 81$5, 8#5$, #0$7 #.8$8 580$8
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*1$+ *1$85+ *$.+ *$7#+ *#$1.+ *#$,5+ *$1#+ *$,1+ *5$10+ *5$,0+ *,$1+ *,$,+
*.,$07+ *.8#$#5+ *100#$01+ *10#$07+ *10#$5+ *10,$1+ *1085$70+ *1107$1+ *11.$5,+ *115$15+ *1175$1.+ *11.8$70+
*1#.$,.+ *1#7,$,.+ *10$+ *1#$#0+ *1,0$.5+ *1.0$17+ *151.$.7+ *1550$#7+ *1581$#8+ *1,1#$01+ *1,5$7+ *1,78$17+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
Maximum
% 5% $700/k
$550/k
!.00%
"%
*$+
""%,,*$ #$!*# -,,/*/ -",-*#"
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8755$77+ .500$00 *1555$77+ *1555$77+ *,#000$00+ *5557$8+ *1..71$8+ *#585$,+ #01$#, *,#000$00+ *5.0$1#+ *1.870$5+ *#1.$88+ #0580$1 *,#000$00+ *5015$.7+ *1.7,,$07+ *#.$.0+ #0750$10 *,#000$00+ *517#$8+ *1.,5.$+ *#075$,0+ #0.$0 *,#000$00+ *51,$57+ *1.5.$70+ *#18.,$87+ #110#$1# 118.$0 50$, 7#,$0 7#,$0 115$1, ,17$8 75#$# 75#$# 1,$.. 7#5$. 777$0, 777$0, 1781$7 857$05 7.$,7 7.$,7 1#108$5, .81$5 817$#0 817$#0 1##$,. 5108$,0 8##5$0. 8##5$0. 1#787$#5 5#.$1. 858$15 858$15 11#.$7# 5#7#$10 87,,$,# 87,,$,# 1501$07 *#18$+ 1551$51 #.1$08 1,00$55
5510$1 *1188$80+ 57.5$57 1,,8$,1 ,0.5$1
8..0$,, *1.#.$,+ .55$. 7$7 ..5$1
8..0$,, *1.#.$,+ .55$. 7$7 ..5$1
1,50$1, 1,870$17 17#00$8 177$ 181.5$5 18,5.$55 1.1#5$,# 1.,#$78 01$# 0,#7$5, 11,#$8 50..8$
,51$0, ,10$,, ,57$# ,7$1# ,.1$1. 70.0$,# 771$5 757$0 7,7$ 78$7 80$5 1.#7.$0
101..$10 105.$50 107,$5 11000$#1 1181$05 115,8$. 118,$0. 11,,$75 177$08 17.5$. 1#11$57 #1,1.$0
101..$10 105.$50 107,$5 11000$#1 1181$05 115,8$. 118,$0. 11,,$75 177$08 17.5$. 1#11$57 #1,1.$0
Input values System cost System size
Total system cost Efciency rating Salvage value Salvage value
Ta! cre"it
Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1, 17 18
-#15000 18% 15% o systems cost 750
#0$00%
/ereciation er year Ta! rate Ta! cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-,#000 #8% #0%
-0$50%
KWH production KW by solar 70.5,$00 70,01$ 708$1 ,.8.,$.7 ,.57$. ,.1..$75 ,885#$75 ,850.$8 ,81,,$. ,78,$10 ,78,$.7 ,71.$5 ,,81#$7.
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
,,7.$7 ,,17$# ,581,$58 ,587$50 ,51,0$0,
$5# $5 $50 $. $8
Systems cost *#15000$00+
..5$00
1. 0 1 # 5 , 7 8 . #0
,8#$, ,510$0. ,187$5 ,#8,,$,0 ,#57$7 ,#.$5# ,.1#$#. ,5.8$8 ,85$8# ,1.7$0 ,1,,$5 ,1#5,$0
$7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total S2P re3ate
15$00 0$18 87,0$00 #,5$00 70.5,$00 1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3le scenarios- t4ere may 3e c4anges in t4e various costs -mosty increas
Input
Base case- as givenMinimum
Most Likely
Electricity Price ro
3% (given)
7%
:aintenance ;ost
2% (given)
3.50%
Additional Maintenance, Year 5
$400/kW (given)
$550/kW
!nverter "e#laceent, Year
$250/kW (given)
$400/kW
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
0.65%
!n&'rance o&t +rot"ate
2% (given)
5%
Calculation of the salvage value System cost -#15000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -,#000 750 0
Ta! cre"it on salvage value
yr yr yr yr
..5
2n KW>
KW 5%
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-17.55
)ter ta! salvage value
7%
for for for for
5%
Insurance &aint costs 'otal &ain cost
SIP rebate ,,$#
0$17 0$18 0$1. 0$1 0$ 0$ 0$, 0$7 0$. 0$#1 0$## 0$#, 0$#8
10,$5 18$#, 1#,7$, 155,$5, 15.7$, 1,..$5, 175,,$, 18701$.1 1..10$.. 11.8$ 5,8$70 07$77 5581$17
*15$00+ *15$75+ *1,$5+ *17$#,+ *18$#+ *1.$1+ *0$10+ *1$11+ *$1,+ *#$7+ *$#+ *5$,,+ *,$.+
*,75$00+ *708$75+ *7$1.+ *781$0+ *80$7+ *8,1$.+ *.0$5,+ *..$7.+ *..7$8+ *107$15+ *10..$50+ *115$8+ *11$0+
*07$50+ *1.$88+ *57$#7+ *#70$+ *88$75+ *,1#$1.+ *7#$85+ *881$0+ *#05$0.+ *#17,$#+ *###5$1,+ *#501$.+ *#,77$0+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
0$1 0$ 0$7 0$50 0$5
7#$.. 8..5$7# #0870$#1 #8,,$07 #..0$8,
*8$8+ *17$81+ *.$70+ *#8#,$5+ *#1$18+ *10#$8+ *#$7+ *,#$+ *#$#8+ *157$11+
*#8,0$87+ *05#$.1+ *5,$,1+ *,.$+ *,.$.1+
0$00 0$00 0$00 0$00 0$00
0$57 0$,1 0$,, 0$70 0$75 0$81 0$8, 0$. 0$.. 1$0, 1$1# 1$1
#75#$0 #.,,1$# 5$5 .55$ 78,1$7. 50.5,$05 550$#, 57757$,5 ,1.1$,8 ,5,7$1 ,.,..$57 705$,
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*#,$10+ *#7$.0+ *#.$80+ *1$7.+ *#$88+ *,$07+ *8$#8+ *50$80+ *5#$#+ *5,$00+ *58$80+ *,1$7+
*1,$7+ *1705$,.+ *17.0$.8+ *1880$5+ *1.7$55+ *07#$8+ *17,$.+ *85$7.+ *00$08+ *50$08+ *,,$0.+ *778$#.+
*.7$55+ *517#$.#+ *5#$,#+ *570$,+ *5.8.$7+ *,88$.+ *,,0#$#.+ *,.##$5,+ *780$+ *7,$5+ *80,$,+ *87$7.+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
Maximum
% 5% $700/k
$550/k
!.00%
"%
*$+
##!%#*% -,-!,*%/"!*,. %#.#*$
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8755$77+ .500$00 *1555$77+ *1555$77+ *,#000$00+ *5#,5.$.8+ *0#.0$7.+ *##,.$1.+ .7#0$81 *,#000$00+ *5#01,$,+ *01,$18+ *#870$08+ #01.$. *,#000$00+ *5#8$.+ *1.885$00+ *##$.+ #055,$0, *,#000$00+ *515.5$08+ *1.,0,$1#+ *#1.88$.5+ #1011$05 *,#000$00+ *151,$58+ *817,$#0+ *1##0$8+ .,5.$7 1#0$88 ..$, 8075$# 8075$# 1#.17$85 588$78 8,.$0, 8,.$0, 1871$08 5,51$01 .0$07 .0$07 15888$, ,0#7$,8 .850$. .850$. 1,.7$75 ,50$0 105$# 105$# 181#$0 ,8.0$.# 11#$10 11#$10 1.#71$#7 7#,1$1 1010$5 1010$5 0,.1$.5 78,$. 18.$01 18.$01 101$#1 *78.$,#+ 510$ 17#$1. 8750$8
8#.8$50 *...$.,+ .57.$., 85$81 10.5$#
1#70$81 *8.$,7+ 15,#0$, 1#7$#8 1785$5
1#70$81 *8.$,7+ 15,#0$, 1#7$#8 1785$5
#0701$00 #781$81 #5001$. #7#70$, #.8.7$77 5.#$8# 570$0# 85#8$#0 51811$#, 55#0$78 5.07$0 ,...$7
11,,,$#8 157$0. 1##00$7 100$8 151,1$15 1,185$,, 1778$,1 18$55 1.,88$# 1015$0, #0$7 #.#.$80
1.0#$, 0#$7 1701$0 #1,.$80 7#,$, ,08$18 81.1$ #00.#$7 #1#$0 #87$7# #,5.,$75 #.05.$,7
1.0#$, 0#$7 1701$0 #1,.$80 7#,$, ,08$18 81.1$ #00.#$7 #1#$0 #87$7# #,5.,$75 #.05.$,7
Input values System cost System size
Total system cost Efciency rating Salvage value Salvage value
Ta! cre"it
Year 0 1 # 5 , 7 8 . 10 11 1 1# 1 15 1, 17 18
-#15000 18% 15% o systems cost 750
#0$00%
/ereciation er year Ta! rate Ta! cre"it rate
&ate increase 'P( )nalysis or 15 years
7000 Per KW 15 KW
-,#000 #8% #0%
-0$50%
KWH production KW by solar 70.5,$00 70,01$ 708$1 ,.8.,$.7 ,.57$. ,.1..$75 ,885#$75 ,850.$8 ,81,,$. ,78,$10 ,78,$.7 ,71.$5 ,,81#$7.
$70 $,. $,7 $,, $,5 $,# $, $,1 $5. $58 $57 $5, $5
,,7.$7 ,,17$# ,581,$58 ,587$50 ,51,0$0,
$5# $5 $50 $. $8
Systems cost *#15000$00+
..5$00
1. 0 1 # 5 , 7 8 . #0
,8#$, ,510$0. ,187$5 ,#8,,$,0 ,#57$7 ,#.$5# ,.1#$#. ,5.8$8 ,85$8# ,1.7$0 ,1,,$5 ,1#5,$0
$7 $5 $ $# $ $1 $#. $#8 $#7 $#, $#5 $##
KW production cost System size efciency rate time System size efciency rate Time Energy Pro"uction cost Calculation of SIP rebate )moount o S2P re3ate S2P re3ate System rating /esign actor )mount o S2P re3ate Total S2P re3ate
15$00 0$18 87,0$00 #,5$00 70.5,$00 1.50$00 System rating "esi 1$58 0$. 1.50 1$.5 081$1
Possi3le scenarios- t4ere may 3e c4anges in t4e various costs -mosty increas
Input
Base case- as givenMinimum
Most Likely
Electricity Price ro
3% (given)
7%
:aintenance ;ost
2% (given)
3.50%
Additional Maintenance, Year 5
$400/kW (given)
$550/kW
!nverter "e#laceent, Year
$250/kW (given)
$400/kW
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
0.65%
!n&'rance o&t +rot"ate
2% (given)
5%
Calculation of the salvage value System cost -#15000
Hurdle rate
'o o years o "ereciation /ereciation Salvage value
NPV NPV NPV NPV
5 -,#000 750 0
Ta! cre"it on salvage value
yr yr yr yr
..5
2n KW>
KW 5%
(rid 'otal )lectricit electric y charges savings
! "# "$ "%
-17.55
)ter ta! salvage value
.%
for for for for
8%
Insurance &aint costs 'otal &ain cost
SIP rebate ,,$#
0$17 0$1. 0$0 0$ 0$ 0$, 0$. 0$#1 0$# 0$#7 0$0 0$ 0$8
10,$5 1#08$1 1188$5 15#88$1, 1,,8.$# 18100$#1 1.,#0$,. 1.0$, #0.0$57 50$88 71,0$5 .5,$,5 #1.7$1
*15$00+ *15$75+ *1,$5+ *17$#,+ *18$#+ *1.$1+ *0$10+ *1$11+ *$1,+ *#$7+ *$#+ *5$,,+ *,$.+
*,75$00+ *708$75+ *7$1.+ *781$0+ *80$7+ *8,1$.+ *.0$5,+ *..$7.+ *..7$8+ *107$15+ *10..$50+ *115$8+ *11$0+
*#150$00+ *#0$00+ *#,7$1,+ *#.,8$0.+ *85$5+ *,8$#8+ *..8$,5+ *5#.8$55+ *58#0$#+ *,.,$8,+ *,800$,1+ *7#$,,+ *7.#$+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
0$5 0$57 0$, 0$,7 0$7
#,8$#5 #7577$87 0755$08 00$. 7.#8$11
*8$8+ *17$81+ *.$70+ *#8#,$5+ *#1$18+ *10#$8+ *#$7+ *,#$+ *#$#8+ *157$11+
*85,,$81+ *.5$1,+ *...$##+ *107.1$7+ *11,55$0,+
0$00 0$00 0$00 0$00 0$00
0$80 0$87 0$.5 1$0 1$1# 1$# 1$# 1$7 1$,0 1$7 1$.0 $07
51..1$7 5,#87$1 ,115$,7 ,,#5$#0 71.##$10 78015$0 8,11$ .17,5$0. ..5#$8# 107.#8$57 1170,$78 1,.,$,1
#,5 KW>
Per KW n actor
s 4ic4 may a6ect t4e 'P(
*#,$10+ *#7$.0+ *#.$80+ *1$7.+ *#$88+ *,$07+ *8$#8+ *50$80+ *5#$#+ *5,$00+ *58$80+ *,1$7+
*1,$7+ *1705$,.+ *17.0$.8+ *1880$5+ *1.7$55+ *07#$8+ *17,$.+ *85$7.+ *00$08+ *50$08+ *,,$0.+ *778$#.+
*1587$,+ *1#5.$,+ *1,8$0+ *1585,$58+ *1715$10+ *18.5$11+ *1..7$7+ *157$70+ *#.8$51+ *51,$#.+ *7175$#.+ *.#.$+
0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00 0$00
Maximum
% 5% $700/k
$550/k
!.00%
"%
*$+
#.#%!,*.! -.#%/*#/$!.*%. %.!!*"/
0epreciation
'otal cash 1o2'a3 rate Net income4Cash 1o2 *8755$77+ .500$00 *1555$77+ *1555$77+ *,#000$00+ *57,$8+ *080.$7+ *##.5$7+ .07$, *,#000$00+ *508$#+ *05#0$77+ *##.7$57+ .50$# *,#000$00+ *5#.$8+ *07$##+ *##00$.+ ...7$51 *,#000$00+ *5#,1$##+ *1.8.7$#0+ *#,$0+ #05#5$.8 *,#000$00+ *11$77+ *80,$7+ *1#715$50+ .8$50 1,10$# 7.1$., 7818$7 7818$7 1#77$7 51,$ 8511$0# 8511$0# 1.$1 5,78$01 .,$1 .,$1 1,,$8, ,17.$8. 1008$.7 1008$.7 17,.8$87 ,75$57 10.7#$#0 10.7#$#0 1.,0$1 7#18$85 11.1$8 11.1$8 0.57$51 7.,#$85 1..#$,, 1..#$,, 80$78 8,,5$05 11#7$7 11#7$7 808$7 *510$7+ .#5.$7 7185$7, #7#5$.
.7$#1 *171$08+ 1115,$,0 7#0$5. 1#1..$,,
15#81$1 *7.,$,,+ 180$87 55$17 15#,$8
15#81$1 *7.,$,,+ 180$87 55$17 15#,$8
#777.$# 108,$.. ,81$,8 8588$0 58##$5 57,$,5 ,5.$55 ,7.0,$,1 7#85$ 805,$10 87#$#1 .8#$80
1#5,$15 15,1#$0, 1,.7.$0 18,#$51 007,$71 18.$7# #7#$,# 580$51 805#$5. #0.7$# ##15$, #,0#7$
##$1. 57#$.# 770$, #01$,8 #75,$7 #5,1,$.# #87$. 10$10 5771$,5 .758$78 50.0$85 587.7$58
##$1. 57#$.# 770$, #01$,8 #75,$7 #5,1,$.# #87$. 10$10 5771$,5 .758$78 50.0$85 587.7$58
Input
#
Base case- as given-Minimum
Electricity Price rot4 &at
130 *r&
3% (given)
:aintenance ;ost rot4
12 *r&
2% (given)
Additional Maintenance, Year 5
1 5 *r&
$400/kW (given)
!nverter "e#laceent, Year
1 *r&
$250/kW (given)
!n&'rance o&t (a& % o &*&te co&t)
0.30% (given)
!n&'rance o&t +rot- "ate
2% (given)