Jack-In pile submission Company
Hong Kiat Construction Pte Ltd
No. of pages To
1 + 46 Mr Ang Eng Leng / Ms Wan Chin
From Subject :
Ms Poh Siew
Date
3-Aug-15
Phone
6744 5586
Fax
6748 7346
Jack-in piling works at No. at No. 70 Buangkok View
The following documents are for your onward transmittal to the Engineer for approval :
1 2 3 4
Jack-in pile equip Pressure-force conversion chart Pressure gauge calibration certificate Method statement L.M. Certificate
1 1 1 1
Pile size 250 300 SW L (ton) 69.5 69.5 Remarks :
5 6 7
Ultimate / Static load test Pressure-force conversion chart Pressure gauge calibration certificate Method statement
1 1 2
8
PDA test Pile Set Calculations for PDA load test
2
(Calculation may be resubmited base on actual site data)
9
10 11 12 13 14 15 16 17 18 19 20 21
Method statement Others L.M. Certificate (mini crane) Crane Operator License Lifting Supervisor Certificate Rigging Certificate Signalling certificate Wel Welder certificates R.C pile specif ecifiication Vibration monitoring location (proposed) Risk Assessment Form Safe W ork Procedure Licensed Builders
10
1 1 1 1 1 2 2 * 9 7 1 * Items will be submitted if required
**This submission shall deemed to be approved for site use if we do not receive any comments from your goodself or the engineer before commencement of piling works.**
Please kindly acknowledge the Engineer's acceptance on the the above submission by signing below ASAP & fax back to us for our record. Thank you. For acceptance,
Name : ______________________ Date :____ / ____ / ____
Method Statement Jack-In pile system 1. The piling machine is positioned central to the pile peg position. 2. The pile is placed directly over piling over piling peg and hydraulic pressure is exerted to penetrate the pile into the ground. 3. Verticality of the of the pile is checked using a spirit level. 4. Hydraulic force is applied continuously at a pressure corresponding to the resistance of the pile. The pressure gauge’s reading (in psi ) can be interpolated into resistance of the soil in metric ton. 5. The pile is jacked is jacked to a level ready for the for the insertion of the of the second pile section. 6. The second pile section is inserted and jacked to the required level for welding to be performed. 7. Butt weld all round the perimeter of the pile is carried out on the joint the joint & a cooling time of 3 minutes is observed before jacking before jacking continues. 8. The above procedures are repeated for the for the subsequent sections until the pile is set. The pile is considered set when it does not penetrate further to further to the ground when jacked when jacked to the required . (please refer to the respective conversion charts, which will be submitted upon tonnage* confirmation of equipment of equipment to be used on used on site. ) site. ) 9. Procedures for taking for taking set: a) After the After the required jacking required jacking pressure is achieved, a masking (paper) tape is pasted onto the pile. An independent stable horizontal platform guide for marking for marking lines onto the tape is set up. b) The first line is drawn onto the paper tape by moving a pencil along the platform. The line drawn represents the pile jacked pile jacked to the required capacity (usually 2 times SWL). c) The pressure is maintained for 2 for 2 minutes & the second line is drawn. d) If the If the first & second line coincides, no settlement of pile of pile has occurred. Otherwise extent of the of the settlement is determined by the difference between the first & second drawn line. The pile is considered set if the if the distance between the first & second lines does not exceed not exceed 10mm 10mm.. e) The third line is drawn after the hydraulic pressure is released completely. The rebound or temporary compression (T.C.) of the of the pile is indicated by measuring the difference between the second & third drawn line. (The T.C. is due to elastic shortening behaviour of pile & is proportional to the load applied & length of pile of pile installed.) Other works Other works a. Pile extension “dolly” to be allowed for usage to install piles below work platform level. b. Kentiledge load tests to 2 times Safe Working Load (SWL) of pile shall be conducted on selected pile(s) to verify the capacity of piles of piles installed (if required). (if required).
Rev 4 – Nov 2012
Static Load Test Pile Size : 250mm x 250mm & 300mm x 300mm
Project :
Proposed Extension, Additions & Alterations To Existing 7-Storey Nursing Home To Become 8-Sty (Supervisory Health Care Facilities) On Lots 01402A PT & 02390W PT MK 21 At No. 70 Buangkok View (Hougang Planning Area)
Load testing procedural for
69.5 tons
working load
1) Preparation The selected pile has to be cut-off or built up t o a appropriate level for placement of the necessary loading equipment. Where the bearing surface of the test pile is not at its mildsteel end cap, the brunt pile head has to be built-up such that a horizontal bearing surface that is perpendicular to the axis of the test pile is available. 2) Method of loading The load test is applied by means of a jack which obtained its reaction from the kentledge heavier than the required test load. T he kentledge will be the Jack-In pile equipment made up of counter weight approx. 1 ton to 2 tons each stacked neatly on top of each other. T he pressure gauge used shall be calibrated by an approved laboratory before commencement of load test. The sequence of stacking of test blocks shall be at the discretion of the foreman on site. 3) Measurement of settlement The level and staff method would be used to measure pile settlement. The surveyor's level shall be mounted on a rigidly anchored support. Scale rules (4nos.) shall be used for taking settlement reading to an accuracy of 0.5mm. Two nos. of scale rules shall be securely fixed to the pile for checking its settlement. Another two are fixed on two separate stable permanent support away from the kentledge to serve as bench marks or datum. By taking the difference in scale reading between the scale on the pile and its datum, the pile settlement could be established. 4) Test proper In the First Cycle, the test pile is incrementally loaded to its working load of Day 1 Step 1 2 3 4 5
Loading time Time (hourly)
9:00 9:30 10:00 10:30
& & & &
9:00 9:30 10:00 10:30 11:00
Load jacking 69.5 tons Loading (tons)
Load stage
0 17.375 34.75 52.125 69.5
0% 25% 50% 75% 100%
69.5 tons Readings
% take initial reading 2nd & 3rd 4th & 5th 6th & 7th 8th & 9th
Project :
Proposed Extension, Additions & Alterations To Existing 7-Storey Nursing Home To Become 8-Sty (Supervisory Health Care Facilities) On Lots 01402A PT & 02390W PT MK 21 At No. 70 Buangkok View (Hougang Planning Area)
The load holding is maintained for
Day 2
Unloading time Time (hourly)
Step 1 2 3 4 5
11:00 11:30 12:00 12:30
& & & &
11:00 11:30 12:00 12:30 13:00
24 hrs
and being released on the 2nd day.
Load release 0 tons Loading (tons)
Load stage
69.5 52.125 34.75 17.375 0
100% 75% 50% 25% 0%
Readings
% take initial reading 2nd & 3rd 4th & 5th 6th & 7th 8th & 9th
Second Cycle The test pile is incrementally loaded to its 2 times SWL of
139.0
After 1 hour rest Day 2 Step 1 2 3 4 5 6 7
Loading time Time (hourly)
14:00 14:30 15:00 15:30 16:00 16:30
& & & & & &
14:00 14:30 15:00 15:30 16:00 16:30 17:00
The load holding is maintained for Day 3 Step 1 2 3 4 5
Unloading time Time (hourly)
17:00 17:30 18:00 18:30
& & & &
17:00 17:30 18:00 18:30 19:00
Load jacking 139.0 tons Loading (tons)
Load stage
0 34.75 69.5 86.875 104.25 121.625 139
0% 50% 100% 125% 150% 175% 200%
24 hrs
Readings
% take initial reading 2nd & 3rd 4th & 5th 6th & 7th 8th & 9th 10th & 11th 12th & 13th
and being released on the 3rd day.
Load release 0 tons Loading (tons)
Load stage
139 104.25 69.5 34.75 0
200% 150% 100% 50% 0%
Readings
% take initial reading 2nd & 3rd 4th & 5th 6th & 7th 8th & 9th
Date :
3-Aug-15
FOR DRIVEN / PDA TEST ONLY
PILE SET CALCULATION Proposed Extension, Additions & Alterations To Existing 7-Storey Nursing Home To Become 8Storey (Supervisory Health Care Facilities) On Lots 01402A PT & 02390W PT MK 21 At No. 21 At No. 70 Buangkok View (Hougang Planning Area) Pile Information 1 2 3 4 5 6 7 8 9 10 11
Pile size Pile working load Negative skin friction Pile Length Pile Weight / meter Ultimate resistance Temporary compression Coefficient of restitution Weight of pile Efficiency Final Set per blow
FOS 2 times 1 time(s)
R C n P h
-3.13
-1.01
1.7 1480 -31.3
2.2 1480 -10.1
250 69.5 0.0 43.0 162.56 139.0 15.0 0.30 6.99 0.90 0.40 1.39
2
mm ton ton m kg/m ton mm ton 1.45
1.47
mm
2.8 1410 14.5
3.3 1100 14.7
ton
Proposed driving criteria
A Hammer weights B Effective stroke C Set per 10 blows
W H
Hiley's formula
R
WH h s
c 2
Pile size & wt.
W
W
2
n P
P
Size 114.3 141.3 168.3 150 175 200 225 250 275 300
kg/m 16.07 21.78 28.26 57.8 79.2 103.0 132.3 162.6 203.1 232.6
2.5 1480 4.0
2.7 1480 13.9
mm mm
Date :
3-Aug-15
FOR DRIVEN / PDA TEST ONLY
PILE SET CALCULATION Proposed Extension, Additions & Alterations To Existing 7-Storey Nursing Home To Become 8Storey (Supervisory Health Care Facilities) On Lots 01402A PT & 02390W PT MK 21 At No. 21 At No. 70 Buangkok View (Hougang Planning Area) Pile Information 1 2 3 4 5 6 7 8 9 10 11
Pile size Pile working load Negative skin friction Pile Length Pile Weight / meter Ultimate resistance Temporary compression Coefficient of restitution Weight of pile Efficiency Final Set per blow
FOS 2 times 1 time(s)
-3.88
-2.14
300 69.5 0.0 43.0 232.56 139.0 15.0 0.30 10.00 0.90 -0.98 -0.17
1.7 1480 -38.8
2.2 1480 -21.4
2.5 1480 -9.8
R C n P h
2
mm ton ton m kg/m ton mm ton 0.26
1.47
mm
2.8 1480 2.6
3.3 1330 14.7
ton
Proposed driving criteria
A Hammer weights B Effective stroke C Set per 10 blows
W H
Hiley's formula
R
WH h s
c 2
Pile size & wt.
W
W
2
n P
P
Size 114.3 141.3 168.3 150 175 200 225 250 275 300
kg/m 16.07 21.78 28.26 57.8 79.2 103.0 132.3 162.6 203.1 232.6
2.7 1480 -1.7
mm mm
Euroc ode comp liant SS EN / BS EN
Eurocode Compliant SS EN / BS EN
Eurocode Compliant SS EN / BS EN
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks Company
PECK BROTHERS Construction Pte Ltd
Process Location
Rev No.
Edmund Peck – Senior Project Manager 25th Jun 2015
Approved by (Name, Designation, Date)
Last Review Date
1. Hazard Identification
No.
Work Activity
6.1
Mobilisation & demobilisation of machine using lorry crane
6.2
Unloading of machine parts from lorry crane
Movement of machine
Severity (S)
Hazard / Environmental Aspect
Unsafe access or ground condition
Parts or Machine detaching from the lifting gear while lifting
Blind spot at rear of machine beyond sight of operator
Likelihood (L)
Brandon Wong – Assistant Project Manager, Myo Hlaing – Senior Supervisor, Brandon Lee – Project Executive Saw Zaw Moe Aung – Site Supervisor
Conducted by (Names, Designations, Date)
6. Jack piling
Original Assessment Date
6.3
Page 22 to 46
25th Jun 2015
7
Next Review Date
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
25th Jun 2018
3. Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Toppling of crane while unloading machine parts
The operator of the lorry crane is to ensure that the crane stablilisers have been properly setup
4
2
8
Use additional steel plates for setting the jacks. Lifting Supervisor to ensure before lifting starts
3
1
3
Toppling of the lorry causing death to the rigger man
he piling operator and signal & rigger accompanying the machine is to ensure that the machine has been 4 properly shackled prior to lifting. Ensure all lifting gears used are within the calibration of 12 months.
2
8
Usual inspect of lifting gear. Lifting permit with lifting plan approved on site before start work.
3
1
3
3
9
Cordon off the machine radius while operation
2
2
4
Musculoskeletal injury
Where uncertain, operator is to halt machine & perform a visual check of the blind spot. Banksman on site
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
Almost Certain (5) 25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Action Officer, Designation (Follow-up date)
Lifting Supervisor
Lifting Supervisor
Piling Operator cum supervisor (site), on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks Company
PECK BROTHERS Construction Pte Ltd
Process Location
Rev No.
Edmund Peck – Senior Project Manager 25th Jun 2015
Approved by (Name, Designation, Date)
Last Review Date
1. Hazard Identification
No.
Work Activity
6.1
Mobilisation & demobilisation of machine using lorry crane
6.2
Unloading of machine parts from lorry crane
Movement of machine
Severity (S)
Hazard / Environmental Aspect
Unsafe access or ground condition
Parts or Machine detaching from the lifting gear while lifting
Blind spot at rear of machine beyond sight of operator
Likelihood (L)
Brandon Wong – Assistant Project Manager, Myo Hlaing – Senior Supervisor, Brandon Lee – Project Executive Saw Zaw Moe Aung – Site Supervisor
Conducted by (Names, Designations, Date)
6. Jack piling
Original Assessment Date
6.3
Page 22 to 46
25th Jun 2015
7
Next Review Date
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
25th Jun 2018
3. Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Toppling of crane while unloading machine parts
The operator of the lorry crane is to ensure that the crane stablilisers have been properly setup
4
2
8
Use additional steel plates for setting the jacks. Lifting Supervisor to ensure before lifting starts
3
1
3
Toppling of the lorry causing death to the rigger man
he piling operator and signal & rigger accompanying the machine is to ensure that the machine has been 4 properly shackled prior to lifting. Ensure all lifting gears used are within the calibration of 12 months.
2
8
Usual inspect of lifting gear. Lifting permit with lifting plan approved on site before start work.
3
1
3
3
9
Cordon off the machine radius while operation
2
2
4
Musculoskeletal injury
Where uncertain, operator is to halt machine & perform a visual check of the blind spot. Banksman on site
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
1. Hazard Identification
6.3
6.4
Movement of machine (cont’d)
Assembly and dismantling of Machine
Severity (S)
Lifting Supervisor
Piling Operator cum supervisor (site), on going
Page 23 to 46
2. Risk Evaluation
3. Risk Control
Hazard / Environmental Aspect
Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Machine losing balance or even get trapped in soft ground
Damage to property, musculoskeletal injury
To overlay soft ground with steel plates or wooden beams where necessary.
3
3
9
Fumes from machinery
Air pollution / ill health
Monthly maintenance of machinery
3
1
3
Machine parts detaching from machine’s Main body
Damage to property, musculoskeletal injury
100% of all locking pin in place with secure pin at one end
4
2
8
Machine parts detaching from the lifting gears.
Toppling of crane causing death to the rigger man
Rigger is to ensure that the parts are properly shackled prior to lifting.
4
2
8
Greasy/Slippery machine parts.
Worker slipping while working on machine part during dismantling/ assembly
Proper maintain/ cleaning of machine
4
1
4
Counterweights slip from the counterweight frame
Damage to neighbouring properties, injuries to workmen
The base counterweight has a lock to prevent any movement. Visual inspection of lifting hook before any lift
4
1
4
Counterweights lifting hooks break
Sudden drop to ground causing injuries to workers
Rigger is to ensure that the parts are properly shackled prior to lifting
4
2
8
Likelihood (L)
Lifting Supervisor
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks
Work Activity
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
No.
Action Officer, Designation (Follow-up date)
Existing Risk Control (if any)
Occasional (3)
y t i r e v e S
d o o h i l e k i L
Frequent (4)
/ l e v e t L c k a s p i m R I
Additional Risk Control
Operator Check the stability of equipment before operation
y t i r e v e S
d o o h i l e k i L
2
2
/ l e v e t L c k a s p i m R I
Action Officer, Designation (Follow-up date)
4
Piling Operator cum supervisor (site), on going Piling Operator to check all locking pin in place & in good condition before moving the machine
Ensure all lifting gears used are within the calibration period of 12 months.Additional plates to be weld to side of counterweights to further prevent movement. Workers not to step on greasy/ lubricated machine parts. Operator must go through machine checklist after assembly of machine.
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Lifting Supervisor, on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.3
6.4
Movement of machine (cont’d)
Assembly and dismantling of Machine
Severity (S)
2. Risk Evaluation
3. Risk Control
Hazard / Environmental Aspect
Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Machine losing balance or even get trapped in soft ground
Damage to property, musculoskeletal injury
To overlay soft ground with steel plates or wooden beams where necessary.
3
3
9
Fumes from machinery
Air pollution / ill health
Monthly maintenance of machinery
3
1
3
Machine parts detaching from machine’s Main body
Damage to property, musculoskeletal injury
100% of all locking pin in place with secure pin at one end
4
2
8
Machine parts detaching from the lifting gears.
Toppling of crane causing death to the rigger man
Rigger is to ensure that the parts are properly shackled prior to lifting.
4
2
8
Greasy/Slippery machine parts.
Worker slipping while working on machine part during dismantling/ assembly
Proper maintain/ cleaning of machine
4
1
4
Counterweights slip from the counterweight frame
Damage to neighbouring properties, injuries to workmen
The base counterweight has a lock to prevent any movement. Visual inspection of lifting hook before any lift
4
1
4
Counterweights lifting hooks break
Sudden drop to ground causing injuries to workers
Rigger is to ensure that the parts are properly shackled prior to lifting
4
2
8
Work Activity
Likelihood (L)
Page 23 to 46
Existing Risk Control (if any)
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Additional Risk Control
Operator Check the stability of equipment before operation
y t i r e v e S
d o o h i l e k i L
2
2
/ l e v e t L c k a s p i m R I
4
Piling Operator cum supervisor (site), on going Piling Operator to check all locking pin in place & in good condition before moving the machine
Ensure all lifting gears used are within the calibration period of 12 months.Additional plates to be weld to side of counterweights to further prevent movement. Workers not to step on greasy/ lubricated machine parts. Operator must go through machine checklist after assembly of machine.
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.5
Work Activity
Hoisting with mini crawler crane
Severity (S)
Existing Risk Control (if any)
Cranes have been erected & tested by approved crane contractors & Approved person & Appro ved Crane Operator. Lifting carried by lifting teams,lifting supervisor, rigger signalman
3. Risk Control
y t i r e v e S
d o o h i l e k i L
4
1
/ l e v e t L c k a s p i m R I
Serious injury or death to workers & properties
Falling object while hoisting materials
Serious injury or death to workers
Approve crane operator Lifting zone barricaded Only authorized personnel allowed in the lifting zone
4
2
8
Serious injury
Keep clear the lifting areas. Approved Crane Operator Lifting carried by lifting teams, lifting supervisor, rigger signalman Lifting zone barricaded
4
2
8
Push / pull down to ground when receiving loads on upper levels
Likelihood (L)
Page 24 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Topple of crane
Hit by loads
Lifting Supervisor, on going
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
Hazard / Environmental Aspect
Action Officer, Designation (Follow-up date)
Serious injury or death to workers
Use of safety harness when working at building edges. Lifting carried by lifting teams, lifting supervisor, rigger signalman
Occasional (3)
4
Frequent (4)
1
4
4
Additional Risk Control
SWP for Safe Use of Lifting Appliance & Gear, Grd condition checked by engineer in charge
SWP for lifting Appliance and Gear, Lifting permit approved before start work. Lifting permit approved before start work. Using tagline. Proper communication system avail between crane operators, lifting supervisor & signalman
Ensure load had reached the unloading bay or designated area control the load only with tag line, Do not push/pull the load while loading/unloading. Proper communication system avail between crane operators, lifting supervisor & signalman
/ l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Action Officer, Designation (Follow-up date)
Lifting Supervisor, on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.5
Hazard / Environmental Aspect
Work Activity
Hoisting with mini crawler crane
Existing Risk Control (if any)
3. Risk Control / l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
4
1
4
Cranes have been erected & tested by approved crane contractors & Approved person & Appro ved Crane Operator. Lifting carried by lifting teams,lifting supervisor, rigger signalman
Serious injury or death to workers & properties
Falling object while hoisting materials
Serious injury or death to workers
Approve crane operator Lifting zone barricaded Only authorized personnel allowed in the lifting zone
4
2
8
Serious injury
Keep clear the lifting areas. Approved Crane Operator Lifting carried by lifting teams, lifting supervisor, rigger signalman Lifting zone barricaded
4
2
8
Push / pull down to ground when receiving loads on upper levels
Severity (S)
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Topple of crane
Hit by loads
Likelihood (L)
Page 24 to 46
Serious injury or death to workers
Use of safety harness when working at building edges. Lifting carried by lifting teams, lifting supervisor, rigger signalman
4
1
4
Additional Risk Control
SWP for Safe Use of Lifting Appliance & Gear, Grd condition checked by engineer in charge
SWP for lifting Appliance and Gear, Lifting permit approved before start work. Lifting permit approved before start work. Using tagline. Proper communication system avail between crane operators, lifting supervisor & signalman
Ensure load had reached the unloading bay or designated area control the load only with tag line, Do not push/pull the load while loading/unloading. Proper communication system avail between crane operators, lifting supervisor & signalman
/ l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.5
Work Activity
Hoisting with mini crawler crane (cont’d)
Piling 6.6 operation
Severity (S)
Page 25 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
3. Risk Control
y t i r e v e S
Existing Risk Control (if any)
All the lifting gea rs certified by approved person within 12 months. Lifting carried by lifting teams, lifting supervisor, rigger signalman Lifting team. Lifting carried by lifting teams, lifting supervisor, rigger signalman, Approved Crane Operator Only one crane allowed at a time, Coordinate between crane when more than one crane involved
Additional Risk Control
/ l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
3
1
3
4
1
4
4
1
4
Permit to hoist Proper communication system avail between crane operators Lifting supervisor & signalman
3
1
3
3
1
3
3
2
6
Break time for workers during operation
2
1
2
3
2
6
Competent Operator carryout daily inspection for any fault & rectify
2
1
2
2
8
Any services detected under ground, the diversion work carryout by specialist contractors, outsource to other contractors Service plan provided for site personnel
3
1
3
1
3
Competent Operator carryout daily inspection for any fault & rectify
2
1
2
Failure of lifting gears
Collision with cranes
Serious injury or death to workers
Fumes from machinery
Air pollution / ill health
Unsafe act due to insufficient rest
Injury to worker or coworker
MOM approved and standard working hours of workers and operators
Toppling of piling frame
Damage to property, musculoskeletal injury
Piling machine parked on steel plate and level ground.
Live underground services, electrical, water line, sewer
Electrocution, Flood, suffocation,
Confirmation of under ground services, Keep away from existing services, Divert the affected services
4
Failure of piling frame cause damage to the piles installed
Damage to property, musculoskeletal injury
Monthly inspection/ maintenance check. Piling machine tested by the approved person
3
Occasional (3)
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Crane operation, Lifting supervisor Carryout visual check replace immediate for any damages Do not over load the lifting gears
Serious injury or death to workers
Likelihood (L)
Lifting Supervisor, on going
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
Hazard / Environmental Aspect
Action Officer, Designation (Follow-up date)
Rare (1)
Remote (2)
Frequent (4)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Action Officer, Designation (Follow-up date)
Lifting Supervisor, on going
Piling Operator cum supervisor (site), on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.5
Hazard / Environmental Aspect
Work Activity
Hoisting with mini crawler crane (cont’d)
Piling 6.6 operation
Severity (S)
Page 25 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Failure of lifting gears
Serious injury or death to workers
Collision with cranes
Serious injury or death to workers
Fumes from machinery
Air pollution / ill health
3. Risk Control
y t i r e v e S
Existing Risk Control (if any)
All the lifting gea rs certified by approved person within 12 months. Lifting carried by lifting teams, lifting supervisor, rigger signalman Lifting team. Lifting carried by lifting teams, lifting supervisor, rigger signalman, Approved Crane Operator Only one crane allowed at a time, Coordinate between crane when more than one crane involved
4
d o o h i l e k i L
1
/ l e v e t L c k a s p i m R I
d o o h i l e k i L
4
Crane operation, Lifting supervisor Carryout visual check replace immediate for any damages Do not over load the lifting gears
3
1
3
Permit to hoist Proper communication system avail between crane operators Lifting supervisor & signalman
3
1
3
Additional Risk Control
4
1
4
3
1
3
3
2
6
Break time for workers during operation
2
1
2
3
2
6
Competent Operator carryout daily inspection for any fault & rectify
2
1
2
3
1
3
2
1
2
Unsafe act due to insufficient rest
Injury to worker or coworker
MOM approved and standard working hours of workers and operators
Toppling of piling frame
Damage to property, musculoskeletal injury
Piling machine parked on steel plate and level ground.
Live underground services, electrical, water line, sewer
Electrocution, Flood, suffocation,
Confirmation of under ground services, Keep away from existing services, Divert the affected services
4
2
8
Any services detected under ground, the diversion work carryout by specialist contractors, outsource to other contractors Service plan provided for site personnel
Failure of piling frame cause damage to the piles installed
Damage to property, musculoskeletal injury
Monthly inspection/ maintenance check. Piling machine tested by the approved person
3
1
3
Competent Operator carryout daily inspection for any fault & rectify
Likelihood (L)
/ l e v e t L c k a s p i m R I
y t i r e v e S
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
1. Hazard Identification
6.6
Existing Risk Control (if any)
Wo rk a t h ei gh t
M us cu lo sk el et al i nj ur y
Unsafe access & egress to work platform
d o o h i l e k i L
Personnel protective equipment safety harness when work more then 2m height
4
2
8
Musculoskeletal injury
Steps provided
3
2
6
Pile holes, falling, tripping hazard
Musculoskeletal injury
Cover all the holes to prevent fall, Barricade affected area
3
1
3
Hit by falling pile locking pin and pile wedge
Serious injury
Proper Personal Protective Equipment. Safe work procedure brief to workers
3
2
Hand / fingers caught in between mast & pile
Musculoskeletal injury
Workman to push & control the pile movement on front facing surface of pile and not on the sides of the pile, unless is below the mast. Operator to ensure that workman is not in the vicinity when moving the machine parts. Workers to stay clear of machine moving parts.
4
Machine parts detaching during operation
Damage to property, musculoskeletal injury
Ensure all pin locks are fully installed with safety pins
Damage to property, musculoskeletal injury
To overlay soft ground with layer of compacted hardcore, steel plates or wooden beams where necessary. Broken RC pile heads can be used for additional stability
Piling operation (cont’d)
Severity (S)
3. Risk Control / l e v e t L c k a s p i m R I
y t i r e v e S
Machine losing balance or even get trapped in soft ground Likelihood (L)
Page 26 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Work Activity
Piling Operator cum supervisor (site), on going
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks
No.
Lifting Supervisor, on going
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
Hazard / Environmental Aspect
Action Officer, Designation (Follow-up date)
Occasional (3)
/ l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
All the open e dges should be barricaded to prevent fall from height Proper access/egress
3
1
3
Always ensure the ac cess reach the work platform, Do not run any cable or obstruct the access way
2
1
2
6
Ground workmen to keep clear when “pinman” is inserting/removing pin
2
1
2
2
8
Use crow bar / pile fork instead of bare hands
3
1
3
4
2
8
Operator must go through machine checklist before operating of machine
3
1
3
3
3
9
Operator Check the stability of equipment before operation
2
2
4
Frequent (4)
Additional Risk Control
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Action Officer, Designation (Follow-up date)
Piling Operator cum supervisor (site), on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.6
2. Risk Evaluation
3. Risk Control
Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
Wo rk a t h ei gh t
M us cu lo sk el et al i nj ur y
Personnel protective equipment safety harness when work more then 2m height
4
2
Unsafe access & egress to work platform
Musculoskeletal injury
Steps provided
3
Pile holes, falling, tripping hazard
Musculoskeletal injury
Cover all the holes to prevent fall, Barricade affected area
Hit by falling pile locking pin and pile wedge
Serious injury
Hand / fingers caught in between mast & pile
/ l e v e t L c k a s p i m R I
d o o h i l e k i L
8
All the open e dges should be barricaded to prevent fall from height Proper access/egress
3
1
3
2
6
Always ensure the ac cess reach the work platform, Do not run any cable or obstruct the access way
2
1
2
3
1
3
Proper Personal Protective Equipment. Safe work procedure brief to workers
3
2
6
Ground workmen to keep clear when “pinman” is inserting/removing pin
2
1
2
Musculoskeletal injury
Workman to push & control the pile movement on front facing surface of pile and not on the sides of the pile, unless is below the mast. Operator to ensure that workman is not in the vicinity when moving the machine parts. Workers to stay clear of machine moving parts.
4
2
8
Use crow bar / pile fork instead of bare hands
3
1
3
Machine parts detaching during operation
Damage to property, musculoskeletal injury
Ensure all pin locks are fully installed with safety pins
4
2
8
Operator must go through machine checklist before operating of machine
3
1
3
Machine losing balance or even get trapped in soft ground
Damage to property, musculoskeletal injury
To overlay soft ground with layer of compacted hardcore, steel plates or wooden beams where necessary. Broken RC pile heads can be used for additional stability
3
3
9
Operator Check the stability of equipment before operation
2
2
4
Hazard / Environmental Aspect
Piling operation (cont’d)
Likelihood (L)
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
y t i r e v e S
Work Activity
Severity (S)
Page 26 to 46
Additional Risk Control
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.7
Work Activity
Shifting of Piling machine
Poor ground stability
Machine parts detaching from Lifting gears 6.8
Dismantling of machine
Greasy/Slippery machine parts. Counterweight lifting hooks break
Presence of flammable material 6.9
Severity (S)
Likelihood (L)
Page 27 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
Property damage / Musculoskeletal injury
Operator ensure the ground stability. Do not park near excavation edges. Ensure the steel plates & Support beams are landed safety after every movements
Toppling of crane causing death to the rigger man Worker slipping while working on machine part during dismantling/ assembly Damage to neighbouring properties, injuries to workmen Sudden drop to ground causing injuries to workers
3. Risk Control
y t i r e v e S
d o o h i l e k i L
4
2
/ l e v e t L c k a s p i m R I
Proper maintain/ cleaning of machine
3
Piling Operator cum supervisor (site), on going
3
1
3
Lifting Supervisor, on going
3
1
3
2
8
2
8
Regular inspection by Supervisor; Emergency Evacuation Plan
Serious injury or death to workers & nearby pple due to fire or explosion
Competent & licensed welder. Regular inspection of fire fighting equipment
4
Action Officer, Designation (Follow-up date)
1
4
4
/ l e v e t L c k a s p i m R I
3
Ensure all lifting gears used are within the calibration period of 12 months. Additional plates to be weld to side of counterweights to further prevent movement. Workers not to step on greasy/ lubricated machine parts. Operator must go through machine checklist after assembly of machine.
Competent & experienced welder; Regular house keeping; Fire watchman on site; cordon off work area; fire fighting equipment ready on site
d o o h i l e k i L
Machine load transfer bearing calculation
Rigger is to ensure that the parts are properly shackled prior to lifting.
Occasional (3)
Additional Risk Control
y t i r e v e S
8
Visual inspections of lifting hook before any lift
Serious injury or death to workers & nearby pple due to fire or explosion
Welding Fire fighting eqpmt not suitable for electrical fire
Piling Operator cum supervisor (site), on going
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
Hazard / Environmental Aspect
Action Officer, Designation (Follow-up date)
Welder, on going
Frequent (4)
2
8
Emergency Evacuation Plan
3
1
3
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.7
Hazard / Environmental Aspect
Work Activity
Shifting of Piling machine
Poor ground stability
Machine parts detaching from Lifting gears 6.8
Dismantling of machine
Greasy/Slippery machine parts. Counterweight lifting hooks break
Presence of flammable material 6.9
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
Property damage / Musculoskeletal injury
Operator ensure the ground stability. Do not park near excavation edges. Ensure the steel plates & Support beams are landed safety after every movements
Toppling of crane causing death to the rigger man Worker slipping while working on machine part during dismantling/ assembly Damage to neighbouring properties, injuries to workmen Sudden drop to ground causing injuries to workers
Severity (S)
Likelihood (L)
3. Risk Control
y t i r e v e S
d o o h i l e k i L
4
2
/ l e v e t L c k a s p i m R I
Proper maintain/ cleaning of machine
Additional Risk Control
3
Piling Operator cum supervisor (site), on going
3
1
3
Lifting Supervisor, on going
3
1
3
8
2
8
Regular inspection by Supervisor; Emergency Evacuation Plan
Rigger is to ensure that the parts are properly shackled prior to lifting.
Competent & licensed welder. Regular inspection of fire fighting equipment
4
Welder, on going 2
8
Emergency Evacuation Plan
3
1
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.9
Hazard / Environmental Aspect
Work Activity
Welding (cont’d)
Severity (S)
Page 28 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
3. Risk Control
Existing Risk Control (if any)
y t i r e v e S
d o o h i l e k i L
4
1
/ l e v e t L c k a s p i m R I
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
4
Eme rgency Evacuati on Pl an
3
1
3
Finished work not checked upon completion
Burns to workers & nearby people due to outbreak of fire
Competent & experienced welder; Regular Housekeeping; Regular inspection of fire extinguisher equipment; fire watchman on site; cordon off work area; fire fighting equipment on site
Obstructed emergency escape route
Serious injury or death to workers & nearby people due to fire or explosion
Regular housekeeping
4
1
4
Regular inspection of fire escape route Emergency Evacuation Plan
3
1
3
Competent & licensed welder; Hot work permit approval
4
1
4
Regular inspection or test by Supervisor for flammable gases
3
1
3
Presence of flammable gases in structure / pipes / tanks
Serious injury or death to workers & nearby people due to fire or explosion
Hot Surface
Burn
Greasy & torn clothing
Burn
No indication of welded parts
Burn
Work piece not earthed separately
Electrical shock
Likelihood (L)
Action Officer, Designation (Follow-up date)
1
2
Serious injury or death to workers & nearby pple due to fire or explosion
/ l e v e t L c k a s p i m R I
3
4
4
d o o h i l e k i L
Machine load transfer bearing calculation
Ensure all lifting gears used are within the calibration period of 12 months. Additional plates to be weld to side of counterweights to further prevent movement. Workers not to step on greasy/ lubricated machine parts. Operator must go through machine checklist after assembly of machine.
Competent & experienced welder; Regular house keeping; Fire watchman on site; cordon off work area; fire fighting equipment ready on site
y t i r e v e S
8
Visual inspections of lifting hook before any lift
Serious injury or death to workers & nearby pple due to fire or explosion
Welding Fire fighting eqpmt not suitable for electrical fire
Page 27 to 46
Welder, on going
Competent & experience welder; Proper Personal Protective Equipment Hot work permit approval Clean & proper clothing wore before start of work; Proper Personal Protective Equipment Competent & experience welder; Proper Personal Protective Equipment, Hot work Permit Competent & experience welder; Proper Personal Protective Equipment; Monthly LEW inspection
Occasional (3)
Action Officer, Designation (Follow-up date)
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Frequent (4)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.9
Severity (S)
3. Risk Control
Existing Risk Control (if any)
d o o h i l e k i L
Finished work not checked upon completion
Burns to workers & nearby people due to outbreak of fire
Competent & experienced welder; Regular Housekeeping; Regular inspection of fire extinguisher equipment; fire watchman on site; cordon off work area; fire fighting equipment on site
4
1
Obstructed emergency escape route
Serious injury or death to workers & nearby people due to fire or explosion
Regular housekeeping
4
Competent & licensed welder; Hot work permit approval
4
Work Activity
Presence of flammable gases in structure / pipes / tanks
Welding (cont’d)
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
y t i r e v e S
Hazard / Environmental Aspect
Serious injury or death to workers & nearby people due to fire or explosion
Burn
Greasy & torn clothing
Burn
No indication of welded parts
Burn
Work piece not earthed separately
Electrical shock
/ l e v e t L c k a s p i m R I
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
4
Eme rgency Evacuati on Pl an
3
1
3
1
4
Regular inspection of fire escape route Emergency Evacuation Plan
3
1
3
1
4
Regular inspection or test by Supervisor for flammable gases
3
1
3
Competent & experience welder; Proper Personal Protective Equipment; Monthly LEW inspection
3
1
3
3
1
3
3
1
3
3
1
3
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.9
Hazard / Environmental Aspect
Work Activity
Severity (S)
Existing Risk Control (if any)
Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check
3. Risk Control / l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
Electrical shock
Wet area
Electrical shock
Poor earthing of area
Electrical shock
Incorrect shade of filter glass
Eye injury to workers
Striking of arc
Bodily injury due to hot flying fragments
Absence of screens
Arc radiation burns
Emission of welding fumes & gases
Adverse health effect
Well ventilated area; Proper Personal Protective Equipment
3
1
3
Cables damage or cut by machine moving parts
Electrical shock
Designated area for storing hanging of cables; Proper Personal Protective Equipment
3
2
6
Likelihood (L)
Page 29 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Damaged leads, holders & connections
Welding (cont’d)
Action Officer, Designation (Follow-up date)
Welder, on going
Competent & experience welder; Proper Personal Protective Equipment Hot work permit approval Clean & proper clothing wore before start of work; Proper Personal Protective Equipment Competent & experience welder; Proper Personal Protective Equipment, Hot work Permit
Hot Surface
Likelihood (L)
Page 28 to 46
Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check
Occasional (3)
Frequent (4)
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Action Officer, Designation (Follow-up date)
Welder, on going
Monthly equipment check
2
1
2
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
Hazard / Environmental Aspect
Work Activity
Damaged leads, holders & connections
6.9
Severity (S)
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact Electrical shock
Existing Risk Control (if any)
3. Risk Control / l e v e t L c k a s p i m R I
y t i r e v e S
d o o h i l e k i L
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
3
1
3
Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check Competent & experience welder; Proper Personal Protective Equipment; monthly equipment check
Wet area
Electrical shock
Poor earthing of area
Electrical shock
Incorrect shade of filter glass
Eye injury to workers
Striking of arc
Bodily injury due to hot flying fragments
Absence of screens
Arc radiation burns
Emission of welding fumes & gases
Adverse health effect
Well ventilated area; Proper Personal Protective Equipment
3
1
3
Cables damage or cut by machine moving parts
Electrical shock
Designated area for storing hanging of cables; Proper Personal Protective Equipment
3
2
6
Welding (cont’d)
Likelihood (L)
Page 29 to 46
y t i r e v e S
Additional Risk Control
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Welder, on going
Monthly equipment check
2
1
2
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Almost Certain (5)
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.10
6.11
Hazard / Environmental Aspect
Work Activity
Cutting-off of piles using concrete cutter, grinder & breaker and air compressor
Human factor
6.12
Human behaviour
6.13
Storage of Material
Severity (S)
Page 30 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
3. Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
H it b y F ly in g o bj ec t
E ye i nj ur y
Use of Personnel protective equipment
3
1
3
High Noise
Noise induced Deafness
Use of Ear plug
3
1
3
Generation of noise
Noise pollution
Use of Ear plug
3
1
3
Dep letion of resource s
Switch off appliances or machineries when not in used
3
1
3
3
2
6
Monthly Equipment Check
2
1
2
3
1
3
Intermittent rest time
2
1
2
Use of powe r
Designated area for storing hanging of cables;
Electrical shock
Long exposure to sun
Sun burnt, heat stroke
Exposure to bad weather
Bodily injury due to lightning strike
Stop work when heavy rain
3
2
6
Provide shelter at work site
2
1
2
Manual handling of materials more than 25kg
M us cu lo sk el et al
E xt ra ma np ow er t o r emo ve m at er ia ls
2
2
4
Use of lifting equipments such as pellet jack
2
1
2
Unsafe act due to insufficient rest
Injury to worker or coworker
MOM approved and standard working hrs of workers & operators
3
2
6
Break time for workers during operation
2
1
3
Spillage of lubricate
Land & water pollution
Use drip tray
3
1
3
Proper housekeeping
3
1
3
Toppling of R.C. piles
Damage to 3 rd party property, injuries to workman
Proper stacking of R.C. piles
3
1
3
Cordon off work area from public
3
1
3
Proper Personal Protective Equipment 1. Put on light & long sleeve clothing 2. Drink plenty of water
Occasional (3)
Frequent (4)
Action Officer, Designation (Follow-up date)
Piling Operator cum supervisor (site), on going
Cables damage or cut by machine moving parts
Likelihood (L)
Action Officer, Designation (Follow-up date)
Rare (1)
Remote (2)
Almost Certain (5)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
Piling Operator cum supervisor (site), on going
PECK BROTHERS Construction Pte Ltd
4310-F02 (Rev 6)
List of Aspect / Impact and Hazard / Risks 1. Hazard Identification
No.
6.10
6.11
Hazard / Environmental Aspect
Work Activity
Cutting-off of piles using concrete cutter, grinder & breaker and air compressor
Human factor
6.12
Human behaviour
6.13
Storage of Material
Severity (S)
Page 30 to 46
2. Risk Evaluation Possible Accident / Ill Health & Personsat-Risk / Environmental Impact
Existing Risk Control (if any)
3. Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
Additional Risk Control
y t i r e v e S
d o o h i l e k i L
/ l e v e t L c k a s p i m R I
H it b y F ly in g o bj ec t
E ye i nj ur y
Use of Personnel protective equipment
3
1
3
High Noise
Noise induced Deafness
Use of Ear plug
3
1
3
Generation of noise
Noise pollution
Use of Ear plug
3
1
3
Use of powe r
Dep letion of resource s
Switch off appliances or machineries when not in used
3
1
3
3
2
6
Monthly Equipment Check
2
1
2
3
1
3
Intermittent rest time
2
1
2
Designated area for storing hanging of cables;
Piling Operator cum supervisor (site), on going
Cables damage or cut by machine moving parts
Electrical shock
Long exposure to sun
Sun burnt, heat stroke
Exposure to bad weather
Bodily injury due to lightning strike
Stop work when heavy rain
3
2
6
Provide shelter at work site
2
1
2
Manual handling of materials more than 25kg
M us cu lo sk el et al
E xt ra ma np ow er t o r emo ve m at er ia ls
2
2
4
Use of lifting equipments such as pellet jack
2
1
2
Unsafe act due to insufficient rest
Injury to worker or coworker
MOM approved and standard working hrs of workers & operators
3
2
6
Break time for workers during operation
2
1
3
Spillage of lubricate
Land & water pollution
Use drip tray
3
1
3
Proper housekeeping
3
1
3
Toppling of R.C. piles
Damage to 3 rd party property, injuries to workman
Proper stacking of R.C. piles
3
1
3
Cordon off work area from public
3
1
3
Likelihood (L)
Proper Personal Protective Equipment 1. Put on light & long sleeve clothing 2. Drink plenty of water
Piling Operator cum supervisor (site), on going
Rare (1)
Remote (2)
Occasional (3)
Frequent (4)
Catastrophic (5)
5
10
15
20
25
Major (4)
4
8
12
16
20
1 to 3
Low risk
Moderate (3)
3
6
9
12
15
4 to 14
Medium risk
Minor (2)
2
4
6
8
10
15 to 25
High risk
Insignificant (1)
1
2
3
4
5
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Date th
9 May 2011
Action Officer, Designation (Follow-up date)
Almost Certain (5)
Saf e Pr actices in Piling Wor ks Page 1 / 7
Rev No : 1
Doc No: SWP-SPP
Description of Change Initial release for ISO 9001:2008, ISO 14001:2004 & OHSAS 18001:2007
Rev No 0
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Date th
9 May 2011
Saf e Pr actices in Piling Wor ks Page 1 / 7
Rev No : 1
Doc No: SWP-SPP
Description of Change Initial release for ISO 9001:2008, ISO 14001:2004 & OHSAS 18001:2007
Rev No 0
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
1.
Saf e Pr actices in Piling Wor ks Page 2 / 7
Rev No : 1
Doc No: SWP-SPP
Purpose The purpose of this procedure is to provide guidance for carrying out piling operation safely, prevent injury to person involved in the operation and incident to neighbour.
2.
Scope This procedure is applicable to all project sites.
3.
Related documents/reference
3.1 3.2 3.3
Workplace Safety & Health Act 2006 (Cap 354A) Workplace Safety & Health (Constructions) Regulations 2007 SPP-F01 Permit to Pile
4.
Responsibility
4.1
The Project Manager/ designated Person-in-Charge shall
4.2
4.1.1
Ensure that the following arrangement are planned before work commences on site: Detail of ground conditions obtained a) Effect of piling on adjacent properties considered b) Suitable plant and equipment, ladder, etc. c) Measure to prevent falls from piling rig or when pitching of piles d) Underground services locations e) Maintenance of servicing of plant f) Noise control measures and hearing protection for operatives g) Protection of public or other effected h) Protective clothing and equipment i) Training for supervisory staff and operatives j) Method statement agreed k)
4.1.2
Ensure that all preparation works and requirements are carried out as planned.
4.1.3
Ensure that no person is allowed to operate piling plant or equipment or enter piling areas unless authorised.
4.1.4
Check that work in carried out as planned and that operatives use all safety equipment, protective clothing, etc as required.
4.1.5
Ensure that all plant and equipment in use is checked regularly during the working shift and any defect noted or reported is rectified, and where any defect could affected safe use of any piling plant or equipment, take it out of use immediately.
4.1.6
Ensure that all the control measures identified in risk assessment are being implemented.
The Site Supervisor (SS) / Foreman
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
4.3
Saf e Pr actices in Piling Wor ks Page 3 / 7
Rev No : 1
Doc No: SWP-SPP
The SS / foremen is responsible for continual observational safety checks of their work operations and to enforce the procedure, any unsafe acts or conditions identified shall rectified immediately. Employees / Piling Crew Members It is the responsibility of the employees to understand and adhere to the procedures and to follow the instructions of the SS / Foreman. Employees shall bring to the management’s attention any unsafe or hazardous conditions or acts that may cause injury to either themselves or any other employees.
4.4
Safety Personnel Safety Personnel is responsible for the development, implementation and administration of this procedure. This involves: 4.4.1 Maintaining records and reviewing on hazard assessments 4.4.2 Assist the project team on conducting hazards assessment of the activities. 4.4.3 Provide training and technical assistance to supervisor on the proper use, care and cleaning of approved personal protective equipment. 4.4.4 Periodically re-evaluating the suitability of previously selected personal protective equipment. 4.4.5 Reviewing, updating and evaluating the overall effectiveness of this procedure.
5.
Procedure
5.1
Control Measures 5.1.1
Stability of adjacent structures Where there is any question of the stability of structure adjoining areas to be piled, the structures shall be supported where necessary by sheet piling, shoring, under pinning, bracing or other means in accordance with the design of a professional engineer to prevent injury to any person.
5.1.2
Inspection and Permit-to-Work a) All pile driving equipment shall be inspected daily/regularly by a designated person before the start of work and every defect shall be immediately corrected before piling driving commences. Every piling frame and its attachment shall be thoroughly examined by a authorized b) examiner at least once in every 12 months. In additional Permit-to-Work shall be obtained form the site management before c) commencement of piling operation.
5.1.3
Protection of Operator The operator of every pile drivers shall be protected from falling objects, steam, cinders and water by substantial covering.
5.1.4
Qualifications of Operator Each member of the pile driving crew shall be properly instructed in the work he is to do and the operation shall be in charge by a designated person, who shall personally direct the work and give operating signals.
5.1.5
Handling of Piles The preparation of pile shall be carried out at a safe distance from the driving operation. During the hoisting of piles, all persons not actually engaged in operating the equipment and handling the piles shall be kept out of the area.
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Saf e Pr actices in Piling Wor ks Page 4 / 7
Rev No : 1
Doc No: SWP-SPP
5.1.6
Pile Drivers not in use When the driver is not in use the hammer shall be choked or blocked in the leads or lowered to the ground.
5.1.7
Ladders A ladder extending from the bottom of the leads to the overhead sheaves shall be permanently attached to the structure supporting the leads.
5.1.8
Machine Mobilisation Driven Steel Micropile Rig or Crane or excavator is mobilized into site using jack a) lorry. Steel plates 6mx4nos and 3mx2nos to send in by 10ton lorry. May need additional b) steel plates at entrance culverts. Depending on site access as well for additional steel plates if ground condition is bad. E.g. marine clay area such as Tanjong Katong areas.
5.1.9
Setup of Jack-In Pile(JP) equipment a)
Setup for JP3, JP6 to JP12 i) The base of the equipment is mobilized in using lorry cranes. The lorry cranes range from 25ton to 40ton depending on which mach base. The base is then set onto 2nos of 6m steel plates. nd ii) The 2 part of machine, i.e. lower body is then stacked onto the base. The 2 parts are connected using 24nos of bolts. rd nd iii) The 3 part of machine, i.e. main body is stacked onto the 2 part and connected using 8 pins. iv) The mast is fitted next. The connection is done using 6 pins. v) Counterweight frame is then fitted on the machine, 4 pins are used to connect the frame to the machine. vi) The power pac stand is bolted to the machine using 6 bolts and the powerpac is the put onto the stand and secured firmly using 4 pins. vii) The counterweights are then stacked neatly on the counterweight frame. viii) After all counterweights are in place, the standing platform will be erected on the last counterweights. The platform and all counterweights are secured by tying a chain around it.
b)
Setup for JP4 and 5 i) The main body together with powerpac are mobilized to site using a 12ft” lowbed trailer. ii) The mast is fitted to either the centre (25ton lorry crane) or side (20ton lorry crane) of the machine using 6 pins. iii) The counterweight frame is then fitted using 4 pins. iv) The counterweights are then stacked neatly on the counterweight frame. v) After all counterweights are in place, the standing platform will be erected on the last counterweights. The platform and all counterweights are secured by tying a chain around it.
5.1.10 Dismantling of Jack-In Pile(JP) equipment a)
Dismantling for JP3, JP6 to JP12 i) The standing platform and counterweights are first unloaded onto the ground. ii) The power pac is dismantled followed by its frame. iii) The counterweight frame is then dismantled.
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Saf e Pr actices in Piling Wor ks Page 5 / 7
Rev No : 1
Doc No: SWP-SPP
iv) The mast will then be dismantle using by lorry crane ranging from 10ton to 25ton depending on the position of the mast, rd v) The 3 part of machine, i.e. main body is disconnected by dismantling the 8 pins. nd vi) The 2 part of machine, i.e. lower body is disconnected from the base by dismantling 24nos of bolts. vii) The base of the equipment is mobilized in using lorry cranes. The lorry cranes range from 25ton to 40ton depending on which mach base. The base is then set onto 2nos of 6m steel plates.
b)
Dismantling for JP4 and 5 i) The platform and all counterweights are first unloaded onto the ground.. ii) The counterweight frames is then disconnected from the machine by dismantling 4 pins. iii) The mast will be disconnected by taking out the 6 pins and dismantled from the machine by using either 20ton or 25ton lorry crane depending on the position of the mast. iv) The main body together with powerpac will then be demobilized to site using a 12ft” lowbed.
5.1.11 Movement of Jack-in Pile(JP) Machine a)
The ground is to be laid with steel plates before any machine manoeuver.
b)
Three watchmen will be position at the rear and side of the machine to warn operator should there be any obstruction to the jacks or sliding beam.
c)
When the 4 jacks are being jacked down, the machine is hence elevated. Depending on which direction to move, the sliding beam can slide left to right or the machine body can slide front and rear along the jack beams.
d) After the 4 jacks are being released, the machine body can slide to left or right along the sliding beam. The jack beams can also slide either front or rear depending on the pile position. e)
For JP4 and JP5 which are on tracks, the machine can move by itself in whichever directions. However, steel plates need to be laid so that the weight of the machine can be spread evenly onto the ground.
5.1.12 Working Platform on Piling Frame Where a structural tower supports the leads, suitable working platform of adequate a) strength shall be provided on levels of the leads at which it is necessary for men to work. The platform shall be provided with safety railings and toe board on all sides, except b) on the hammer or lead side of the platform. Where such platform can not be provided, a safety belt/harness shall be used. c) When R.C pile inserted in to the mast, pin man have to hook up all safety harness d) to prevent the R.C pile falling. Ensure safety harness hook up at all times. e) During movement of platform, pin man have to coordinated with operator if any f) movement to the working platform. During movement of piling frame, pin man should not be at the working platform. g) Pin man will use the proper access to go up to the working platform. h)
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Saf e Pr actices in Piling Wor ks Page 6 / 7
Rev No : 1
Doc No: SWP-SPP
5.1.13 Pile Testing The testing of piles shall be conducted under the direct supervision of a designated a) person. Reasonably practical measures shall be taken to warn persons not to approach with b) 50m of a pile under test. Under no circumstances shall anyone permitted to approach a test pile while the c) process of increasing or decreasing test loading is being carried out. While the process of increasing or decreasing test loading is not in progress anyone d) approaching a test pile for any purpose shall only permitted to do so under the specific instruction of the designated person who shall take reasonably practical measures to ascertain that the kentledge is in a stable condition and is safe for approach. 5.1.14 Footing Before placing or advancing a pile driver, the ground shall be inspected by a a) designated person and firm and level footing should be provided, timber or steel plate should be provided when necessary. b) After placing or advancing a pile driver, inspection and correction of the footing shall be made to maintain the stability. 5.1.15 Drive Pile / Sheet Piling Ensure that there is a safe access and working position for pitching of piles. a) If work from a ladder is necessary, a safety harness shall be worn and attached b) securely to a firm anchorage point. Kentledge and Kelly blocks must be in good order, place securely and sufficient for c) the operation. Wear safety helmet, footwear, hearing protector and other PPE required. d) Ensure all hammers, swivels, anchors, pile helmets; guides etc have been inspected e) regularly. Ensure that the winch control the hammer and cover for moving part in good f) condition before use. Ensure all underground services have been located and identified before work g) starts. Ensure that crane / piling rig is on a firm level base. If there is any doubt then h) excavator mats will be used. Stack pile safely and ensure that they are not liable to topple over. i) Use tag lines when guiding piles during lifting / positioning operations. j) Ensure that operations are clear of overhead cables and obstructions during any of k) the work. Follow instructions when work take place next to properties, highways, railways, l) public area etc. and ensure the site is left safe and secure when left unattended, especially with regards to children. 5.2
Record Keeping 5.2.1
5.3
Safety Personnel shall keep all the records as per requirements such as Personal protective equipment issuing record a) Employees training records b) Examination / test certificate of the equipment c) Equipment inspection & maintenance records d) Permit-to-Work records e)
Non-conformance
PECK BROT HERS Construction Pte Ltd Saf e Wor k Pr ocedur es
Saf e Pr actices in Piling Wor ks Page 7 / 7
Rev No : 1
Doc No: SWP-SPP
5.3.1
In case of any non-conformance such as expired certificates, damage /non-availability of proper safety device etc. the Safety Personnel shall inform the PIC to stop the operation immediately.
5.3.2
The PIC shall take actions against the responsible parties and shall ensure that the rectification work has been done accordingly.