Procedure for how to take Background MRP Run
1.0
PURPOSE :
To understand how to take MRP Run in Background for All Network Plants, using Transaction Code:-MDBT. 2.0
SCOPE:
To view Background MRP List. 3.0
METHOD:
Please follow the procedure as given below: Transaction code Menu Path
MDBT SAP menu Logistics Production MRP Planning Total Planning MDBT--Background MRP
Enter T. code:- MDBT
Or Select easy access
Procedure for how to take Background MRP Run
Click here to Create Planning Variant
Enter Name of Planning Variant
Procedure for how to take Background MRP Run
Select All Selection Screens
Click Here
Procedure for how to take Background MRP Run
Click Here
Select Scope of Planning Select Processing Key: NETCH, Create Purchase Req : 1, Schedule Line: 1 No Schedule Line, Create MRP List : 1 MRP List, Planning Mode: 3 Delete & recreate planning data, Scedulling : 2 Lead Time Scheduling and Capacity Planning, Planning Date: Blank
Select 001-Deterministic MRP run (Materials with MRP type 'PD')
After filling information please click on Attributes. Here you need to do configuration for Scope of Planning (Tcode: OM0E) or you can select single plant also. In Scope of planning you take multiple plants.
Procedure for how to take Background MRP Run
Save It (Ctrl S)
Enter Meaning Full Description
Here you select different option as per your requirement like protect variant.
After Saving Variant you will get Variant SCM VB Saved.
See here New Planning Variant Created.
we need to start our background MRP Run through Tcode- MDBT.
Procedure for how to take Background MRP Run
Click here to start immediately Background MRP Run
Here you will see Planning Variant is Started
Then go Tcode: SM37- Job Overview Execute
Enter User ID from which you have started Background MRP
Procedure for how to take Background MRP Run
Click on Spool
Select Background Job (RMMRP000)
After Successful completion of Background Job, please select the Job & then Click o n Spool Click here to see MRP List
Procedure for how to take Background MRP Run
Here you will MRP list generated through Background MRP Job. This list will show which materials are planned with Plant & their exception group.