Price List for Electrical Installation GASCO Air Separation Unit Pos.
1. 1.1 1.2 1.3 2. 2.1.
2.1.1 2.1.2 2.1.2 2.1.3 2.1.4 2.1.5 2.1.5 2.1.6 2.1.7 2.1.9 2.1.11 2.2. 2.2.1 2.2.2 2.2.3 2.2.4 2.2.5 2.2.6 2.2.7
2.2.8 2.2.9
No. Rev. Description of Pricesposition Electrical Installation
Contractors Site Facilities Mobilisation Demobilisation
Code of 1 Acc X1E1 X1E1 X1E1 X1E1
Unit Qty.
Quantity
Supply
Main Order Forecast material
1 1
Time per Unit price Bulk material
1 CONTRACTOR CONTRACTOR 1 CONTRACTOR CONTRACTOR 0
Unit in Min.
Work Manhour
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0 0 0
Material costs Total costs
Equipment Installation X1E2 Equipment Installation LV/MV Container, Transformers X1EA Switchgears, distribution boards and cabinets are installed in LV- or MV-Container. MV-Switchgear ea. 800 x 1300 x 26005 mm, weight appr. 1000 kg X1EA pc. 0 0.00 0.00 0.00 0.00 LV-Panel Transportation unit 800 x 800 x 2000 mm, weight appr. 1700 kg X1EA pc. 0 0.00 0.00 0.00 0.00 LV-Panel Transportation unit 800 x 400 x 2000 mm, weight appr. 800 kg X1EA pc. 0 0.00 0.00 0.00 0.00 Frequency Converter Panel ea. 800 x 800 x 2400 mm, weight appr. 600 kg X1EA pc. 0 0.00 0.00 0.00 0.00 UPS System consisting of 6 Panels ea 600 x 600 x 2000 mm, weight appr. 700 kg X1EA pc. 0 0.00 0.00 0.00 0.00 Battery Cubicle consisting of 54 Cells 2000 x 700 x 1000 mm, weight appr. 1900 kg X1EA pc. 0 0.00 0.00 0.00 0.00 Battery Cubicle consisting of 54 Cells 2000 x 700 x 1000 mm, weight appr. 900 kg X1EA pc. 1 1 LINDE CONTRACTOR 32.00 32.00 32.00 0.00 32.00 Marshalling Rack 800 x 600 x 2000 mm, weight appr. 200 kg X1EA pc. 0 0.00 0.00 0.00 0.00 Distribution transformator 2500 kVA, 2115 x 1345 x 2685 mm, weight appr. 5200 kg X1EA pc. 2 2 LINDE CONTRACTOR 48.00 48.00 96.00 0.00 96.00 General load Distribution Board X1EA pc. 0 0.00 0.00 0.00 0.00 HVAC Panel X1EA pc. 0 0.00 0.00 0.00 0.00 Equipment Installation Field X1EB Mounting to wall or steel structures incl. necessary metal platings and fitting accessories, complete with all cable connections and wiring, labeling, coating system acc. 0000 T-SS 0001, grey colored Lighting Distribution Board X1EB pc. 2 2 LINDE CONTRACTOR 24.00 24.00 48.00 0.00 48.00 Heat Tracing Distribution Board X1EB pc. 0 0.00 0.00 0.00 0.00 Intermediate Terminal Boxes, appr.. 150 x 100 mm X1EB pc. 0 0.00 0.00 0.00 0.00 Intermediate Terminal Boxes, appr.. 200 x 250 mm X1EB pc. 0 0.00 0.00 0.00 0.00 Intermediate Terminal Boxes, appr.. 450 x 250 mm X1EB pc. 0 0.00 0.00 0.00 0.00 Installation of Local Control Station LINDEX1EB Installationstandard E-ZA-1102 pc. 14 14 LINDE CONTRACTOR 36.00 36.00 504.00 0.00 504.00 Installation of Safety Switch at existing structure X1EB pc. 0 0.00 0.00 0.00 0.00 0 0.00 0.00 0.00 0.00 Installation of non specified small material Mounting of non specified material for special steel constructions only (no standard mounting or auxillary material, such as constructions for cable fixing) Supply of non spezified material for special steel constructions only (no standard mounting or auxilary material), complete assembled, coating system acc. 0000 T-SS 0001, grey colored up to 1 kg X1EB pc. 10 10 1.00 1.00 10.00 0.00 up to 2 kg X1EB pc. 5 5 1.00 1.00 5.00 0.00
10.00 5.00
Total Time
0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0
Price List for Electrical Installation GASCO Air Separation Unit Pos.
2.2.10 2.2.11 2.2.12 2.2.13 2.2.14 2.2.15 2.2.16 2.2.17 2.2.18 3. 3.1.
No. Rev. Description of Pricesposition Electrical Installation
up to 5 kg up to 10 kg
Code of 1 Acc
Unit Qty.
Quantity
Main Order Forecast material
X1EB X1EB
pc. 2 pc. 2 Supply and Installation of taffolite lables withe black fonts, fontsize 10mm lable, 50x25 mm, 1-lines X1EB pc. 5 lable, 50x40 mm, 2-lines X1EB pc. 4 lable, 100x50 mm, 1-lines X1EB pc. 1 lable, 100x50 mm, 2-lines X1EB pc. 1 lable, 100x50 mm, 3-lines X1EB pc. 1 X1EB X1EB Installation of Cable Support System Installation of Cable Support System below LV/MV container
Supply
Time per Unit price Bulk material
Unit in Min.
Work Manhour
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
Material costs Total costs
Total Time
2 2
1.20 2.00
1.20 2.00
2.40 4.00
0.00 0.00
2.40 4.00
0 0
5 4 1 1 1 0 0
1.00 1.00 1.00 1.00 1.00
1.00 1.00 1.00 1.00 1.00 0.00 0.00
5.00 4.00 1.00 1.00 1.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
5.00 4.00 1.00 1.00 1.00 0.00 0.00
0 0 0 0 0 0 0
1.20 1.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.20 1.50 0.00 0.00 0.00 0.00
24.00 90.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.00 30.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
24.00 90.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 12.00 30.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.00 0.00 2.00 0.00 0.00 0.00
0.00 0.00 20.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 20.00 0.00 0.00 0.00
0 0 0 0 0 0
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0 0
X1E3 X1ED
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5
Mounting of metallic standard cable ladder system, side height 60mm, steel type, coating system acc. 0000 T-SS 0001, grey colored, Cable ladder 200 mm X1ED m 20 20 1.20 Cable ladder 400 mm X1ED m 50 50 1.80 Cable ladder 600 mm X1ED m 0 Cable channel 50 mm X1ED m 0 Cable channel 100 mm X1ED m 0
3.1.6 3.1.7 3.1.8
Cover 200 mm Cover 400 mm Cover 600 mm
X1ED X1ED X1ED
m m m
3.1.9 3.1.10 3.1.11
Vertical ladder 200 mm Vertical ladder 400 mm Vertical ladder 600 mm
X1ED X1ED X1ED
m m m
3.1.12 3.1.13 3.1.14
Suspension 200 mm Suspension 400 mm Suspension 600 mm
X1ED X1ED X1ED
pc. pc. pc.
X1ED
m
3.1.15
Project Number:
3.1.16 3.1.17 3.1.18 3.1.18 3.1.19
Installation of Suspension bracket (H-profile) H-Profile 500 mm H-Profile 1000 mm H-Profile 1750 mm H-Profile 2000 mm H-Profile 3000 mm
X1ED X1ED X1ED X1ED X1ED
pc. pc. pc. pc. pc.
3.1.20 3.1.21
Installation of C-Profiles C-Profiles 200 mm C-Profiles 400 mm
X1ED X1ED
pc. pc.
10 20
10
0 0 0 0 0 0 0 0 0 10 CONTRACTOR CONTRACTOR 20 CONTRACTOR CONTRACTOR 0 0 0 0 0 0 10 CONTRACTOR CONTRACTOR 0 0 0 0 0
1.20 1.50
2.00
Price List for Electrical Installation GASCO Air Separation Unit Pos.
3.1.22 3.1.23 3.1.24 3.2.
No. Rev. Description of Pricesposition Electrical Installation
Code of 1 Acc
Unit
Quantity
Supply
Time per Unit price Unit in Min.
Work Manhour
Total costs Material Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00
0 0 0 0
1.20 1.80 2.20 0.00 0.00 0.00 0.60 0.80 0.00 0.00
120.00 90.00 572.00 0.00 0.00 0.00 60.00 40.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
120.00 90.00 572.00 0.00 0.00 0.00 60.00 40.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0
0.00 0.00 2.20 0.00
0.00 0.00 44.00 0.00
0.00 0.00 0.00 0.00
0.00 0.00 44.00 0.00
1.20 1.50 2.20 0.00 0.00 0.00 0.00
19.20 15.00 99.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
19.20 15.00 99.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0
1 CONTRACTOR CONTRACTOR 1.50 1.50 2 CONTRACTOR CONTRACTOR 2.00 2.00 0 0.00 0 0.00 0 0.00 Installation of H-Profiles as Construction for Local Control Stations, Cable Supports Distribution Boards etc. , coating system acc. 0000 T-SS 0001, grey colored, Support Bracket for Control Stations to Cable ladders, X1EE LINDE-Installationstandard E-ZA-1102 pc. 0 0.00 Support Bracket for Control Stations to Cable ladders, X1EE LINDE-Installationstandard E-ZA-1103 pc. 0 0.00 Support Bracket for Control Stations to Cable ladders, X1EE LINDE-Installationstandard E-ZA-1104 pc. 0 0.00
1.50 4.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00
1.50 4.00 0.00 0.00 0.00
0 0 0 0 0
0.00
0.00
0.00
0
0.00
0.00
0.00
0
0.00
0.00
0.00
0
0 0 0 0
3.2.9 3.2.10 3.2.11
3.2.12 3.2.13 3.2.14 3.2.15 3.2.16 3.2.17
0 Installation of support brackets, accessories for fixing trays and ladders with steel structure Complete Suspension 200 mm X1EE pc. 16 16 CONTRACTOR CONTRACTOR Suspension 400 mm X1EE pc. 10 10 CONTRACTOR CONTRACTOR Complete Suspension 600 mm X1EE pc. 45 45 CONTRACTOR CONTRACTOR X1EE pc. 0 X1EE pc. 0 X1EE m 0
3.2.18 3.2.19 3.2.20 3.2.21
Installation of Suspension bracket (H-profile) H-Profile 500 mm H-Profile 1000 mm H-Profile 1750 mm H-Profile 3000 mm
3.2.6 3.2.7 3.2.8
0
3.2.26 3.2.27 3.2.28
Material costs Total costs
Total Time
Installation of Cable Support System in Field
X1EE Mounting of metallic wide span cable ladder system, side height 100mm, coating system acc. 0000 T-SS 0001, grey colored, incl. mounting of joints, bendable joints and hinge pieces for horizontal and vertical off-set, incl. mounting of divider stips and exit plates, incl. mounting off all necessary supports and fitting accessories, average support spacing appr. 6m X1EE m Wide span cable ladder 200x100 mm (wxh) 100 100 CONTRACTOR CONTRACTOR 1.20 X1EE m Wide span cable ladder 400x100 mm (wxh) 50 50 CONTRACTOR CONTRACTOR 1.80 X1EE m Wide span cable ladder 600x100 mm (wxh) 260 260 CONTRACTOR CONTRACTOR 2.20 Cable channel 50 mm X1EE m 0 CONTRACTOR CONTRACTOR Cable channel 100 mm X1EE m 0 CONTRACTOR CONTRACTOR 0 Cover 200 mm X1EE m 100 100 CONTRACTOR CONTRACTOR 0.60 Cover 400 mm X1EE m 50 50 CONTRACTOR CONTRACTOR 0.80 Cover 600 mm X1EE m 0 CONTRACTOR CONTRACTOR 0 Vertical ladder, steel type, incl. all necessary supports and fitting accessories, average support spacing appr. 3 m Vertical ladder 200 mm X1EE m 0 CONTRACTOR CONTRACTOR Vertical ladder 400 mm X1EE m 0 CONTRACTOR CONTRACTOR Vertical ladder 600 mm X1EE m 20 20 CONTRACTOR CONTRACTOR 2.20
3.2.1 3.2.2 3.2.3 3.2.4 3.2.5
W-LX 1100
Manhour
pc. pc. pc.
Bulk material
Ruweis
Document Number:
Labour costs
X1ED X1ED X1ED
Main Order Forecast material
1110 A02K
Project Code:
Total price Manhour
C-Profiles 600 mm C-Profiles 800 mm C-Profiles 1000 mm
Qty.
Project Number:
X1EE X1EE X1EE X1EE
pc. pc. pc. pc.
1 2
1.20 1.50 2.20
Price List for Electrical Installation GASCO Air Separation Unit Pos.
3.2.29 3.2.30
No. Rev. Description of Pricesposition Electrical Installation
Code of 1 Acc
Support Bracket for Safety Switches LINDEInstallationstandard E-ZA-1122 Support Bracket for Control Stations to Cable ladders, LINDE-Installationstandard Support Bracket for Socket Outlets etc., on existing Substructures LINDE-Installationstandard E-ZA-1106
X1EE
Support Bracket for Socket Outlets etc., on existing Substructures LINDE-Installationstandard E-ZA-1107
X1EE
Unit Qty.
Quantity
Main Order Forecast material
Work Manhour
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
Material costs Total costs
Total Time
pc.
0
0.00
0.00
0.00
0.00
0
pc.
0
0.00
0.00
0.00
0.00
0
pc.
0
0.00
0.00
0.00
0.00
0
pc.
3
3.2.33 3.2.34 3.2.35 3.2.36 3.2.37
Installation of C-Profiles, coating system acc. 0000 T-SS 0001, grey colored, C-Profiles 200 mm X1EE pc. 30 C-Profiles 400 mm X1EE pc. C-Profiles 600 mm X1EE pc. 30 C-Profiles 800 mm X1EE pc. C-Profiles 1000 mm X1EE pc. 30
3.2.38 3.2.39
Installation of Cable Conduits (PVC/PE) PVC Conduit NW 1/2" PVC Conduit NW 1"
3.2.40 3.2.41 3.2.42 3.2.43 3.2.44 3.2.45
Metal Conduits, coating system acc. 0000 T-SS 0001, grey colored, Conduit NW 1/2" X1EE m Conduit NW 1" X1EE m Conduit NW 1 1/2" X1EE m Conduit NW 2" X1EE m Conduit NW 3" X1EE m Conduit NW 4" X1EE m
Cable Pulling and Connection
Unit in Min.
Ruweis
Document Number:
X1EE
3.2.32
3.2.46 3.2.47 3.2.48 3.2.49 3.2.50 3.2.51 3.2.52 3.2.53 3.2.54 4.
Time per Unit price Bulk material
1110 A02K
Project Code:
X1EE
3.2.31
Steel Structures, coating system acc. 0000 T-SS 0001, grey colored, Hot dipped galvanized material Checkerplate 3mm per m2 completely installed Support Brackets hot dipped galvanized for Equipment up to 1 kg Equipment up to 5 kg Equipment up to 10 kg Equipment up to 30 kg
Supply
Project Number:
X1EE X1EE
X1EE X1EE X1EE X1EE X1EE X1EE X1EE X1EE X1EE
m m
1.00
1.00 0.00
3.00 0.00
0.00 0.00
3.00 0.00
0 0
30 CONTRACTOR CONTRACTOR 0 30 CONTRACTOR CONTRACTOR 0 30 CONTRACTOR CONTRACTOR 0
1.00
1.00 0.00 2.00 0.00 2.80 0.00
30.00 0.00 60.00 0.00 84.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
30.00 0.00 60.00 0.00 84.00 0.00
0 0 0 0 0 0
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0.00 0.00 0.00
0 0 0
0.80 1.00 0.00 1.20 0.00 0.00 0.00
240.00 500.00 0.00 36.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00
240.00 500.00 0.00 36.00 0.00 0.00 0.00
0 0 0 0 0 0 0
0.00 0.00 0.00 1.00 1.20 2.00 3.00 0.00 0.00
0.00 0.00 0.00 10.00 6.00 4.00 6.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 10.00 6.00 4.00 6.00 0.00 0.00
0 0 0 0 0 0 0 0 0
2.00 2.80
0 0 0 300 500 30
kg m2 pc. pc. pc. pc.
3 CONTRACTOR CONTRACTOR 0
10 5 2 2
300 CONTRACTOR CONTRACTOR 500 CONTRACTOR CONTRACTOR 0 30 CONTRACTOR CONTRACTOR 0 0 0
0 0 0 10 5 2 2 0 0
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR
0.80 1.00 1.20
1.00 1.20 2.00 3.00
X1E4
Cable pulling and connection, removal of cable insulation, shrinking cable end, crimping of terminal lug to conductors, tightening of cable gland, tightening of connectors to terminal box, conductor marking, cable marking on both ends and each junction (average 3 times) of the cable with tag number,
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.1. 4.1.1 4.1.2 4.1.3 4.1.4 4.1.5 4.1.6 4.1.7 4.1.8 4.1.9 4.1.10 4.1.11 4.1.12 4.1.13 4.1.14 4.1.15 4.1.16 4.1.17 4.1.18 4.1.19 4.1.20 4.1.21 4.1.22 4.1.23 4.1.24 4.1.25 4.1.26 4.1.27 4.1.28 4.1.29 4.1.30 4.1.31 4.1.32 4.1.33 4.1.34 4.1.35 4.1.36 4.1.37 4.1.38 4.1.39 4.1.40 4.1.41
No. Rev. Description of Pricesposition Electrical Installation
Code of 1 Acc
Unit Qty.
Quantity
Supply
Main Order Forecast material
Time per Unit price Bulk material
for HV-cables making cable sealing end using heat shrinking installation kit incl. necessary fitting accessories Cable Pulling Feeder Cables X1EH X1EH m 0 XLPE-SWA 3x25/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x35/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x50/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x70/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x95/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x120/16 3,8/6,6 X1EH m 0 XLPE-SWA 3x150/25 3,8/6,6 X1EH m 0 XLPE-SWA 3x185/25 3,8/6,6 X1EH m 0 XLPE-SWA 3x240/25 3,8/6,6 X1EH m 0 X1EH m 0 X1EH m 0 XLPE-SWA 3x35/16 6,35/11 X1EH m 0 XLPE-SWA 3x50/16 6,35/11 X1EH m 0 XLPE-SWA 3x70/16 6,35/11 X1EH m 0 XLPE-SWA 3x95/16 6,35/11 X1EH m 0 XLPE-SWA 3x120/16 6,35/11 X1EH m 350 350 LINDE CONTRACTOR XLPE-SWA 3x150/25 6,35/11 X1EH m 0 XLPE-SWA 3x185/25 6,35/11 X1EH m 0 XLPE-SWA 3x240/25 6,35/11 X1EH m 0 X1EH m 0 X1EH m 0 XLPE-SWA 3x95/16 19/33 X1EH m 0 XLPE-SWA 3x185/25 19/33 X1EH m 0 XLPE-SWA 3x240/25 19/33 X1EH m 0 X1EH m 0 X1EH m 0 XLPE-AWA 1x300 0,6/1 X1EH m 0 XLPE-AWA 1x400 0,6/1 X1EH m 0 XLPE-AWA 1x500 0,6/1 X1EH m 0 X1EH m 0 X1EH m 0 XLPE-SWA 3x2,5 0,6/1 X1EH m 5,300 5,300 LINDE CONTRACTOR XLPE-SWA 3x4 0,6/1 X1EH m 0 XLPE-SWA 3x6 0,6/1 X1EH m 0 XLPE-SWA 3x10 0,6/1 X1EH m 0 XLPE-SWA 3x16 0,6/1 X1EH m 0 XLPE-SWA 3x25/16 0,6/1 X1EH m 0 XLPE-SWA 3x35/16 0,6/1 X1EH m 30 30 LINDE CONTRACTOR XLPE-SWA 3x50/25 0,6/1 X1EH m 0 XLPE-SWA 3x70/35 0,6/1 X1EH m 60 60 LINDE CONTRACTOR
Unit in Min.
Work Manhour
1.60
0.30
0.50 0.80
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.60 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.30 0.00 0.00 0.00 0.00 0.00 0.50 0.00 0.80
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 560.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,590.00 0.00 0.00 0.00 0.00 0.00 15.00 0.00 48.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 560.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1,590.00 0.00 0.00 0.00 0.00 0.00 15.00 0.00 48.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.1.42 4.1.43 4.1.44 4.1.45 4.1.46 4.1.47 4.1.48 4.1.49 4.1.50 4.1.51 4.1.52 4.1.53 4.1.54 4.1.55 4.1.56 4.1.57 4.1.58 4.1.59 4.1.60 4.1.61 4.1.62 4.1.63 4.1.64 4.1.65 4.1.66 4.1.67 4.1.68 4.1.69 4.1.70 4.2. 4.2.1 4.2.2 4.2.3 4.2.4 4.2.5 4.2.6 4.2.7 4.2.8 4.2.9 4.2.10 4.2.11 4.2.12 4.2.13
No. Rev. Description of Pricesposition Electrical Installation
XLPE-SWA 3x95/50 0,6/1 XLPE-SWA 3x120/70 0,6/1 XLPE-SWA 3x150/70 0,6/1 XLPE-SWA 3x185/95 0,6/1 XLPE-SWA 4x2,5 0,6/1 XLPE-SWA 4x4 0,6/1 XLPE-SWA 4x6 0,6/1 XLPE-SWA 4x10 0,6/1 XLPE-SWA 4x16 0,6/1 XLPE-SWA 4x25 0,6/1 XLPE-SWA 4x35 0,6/1 XLPE-SWA 4x50 0,6/1 XLPE-SWA 4x70 0,6/1 XLPE-SWA 4x95 0,6/1 XLPE-SWA 4x120 0,6/1 XLPE-SWA 4x150 0,6/1 XLPE-SWA 4x185 0,6/1 XLPE-SWA 5x6 0,6/1 XLPE-SWA CC 5x2,5 0,6/1 XLPE-SWA CC 7x2,5 0,6/1 XLPE-SWA CC 12x2,5 0,6/1 XLPE-SWA CC 19x2,5 0,6/1 Cu 1x25 0,6/1 Cu 1x70 0,6/1 Cu 1x95 0,6/1 Cable Connection Feeder Cables within Container XLPE-SWA 3x25/16 3,8/6,6 XLPE-SWA 3x35/16 3,8/6,6 XLPE-SWA 3x50/16 3,8/6,6 XLPE-SWA 3x70/16 3,8/6,6 XLPE-SWA 3x95/16 3,8/6,6 XLPE-SWA 3x120/16 3,8/6,6 XLPE-SWA 3x150/25 3,8/6,6 XLPE-SWA 3x185/25 3,8/6,6 XLPE-SWA 3x240/25 3,8/6,6
XLPE-SWA 3x35/16 6,35/11
Code of 1 Acc
Unit Qty.
X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH X1EH
m m m m m m m m m m m m m m m m m m m m m m m m m m m m m
X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL
pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
Quantity
Supply
Main Order Forecast material 780 68
2,100 200 500 400
1,700
0 780 68 0 0 2,100 0 200 500 400 0 0 0 0 0 0 0 0 0 0 1,700 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Time per Unit price Bulk material
Unit in Min.
Work Manhour
LINDE LINDE
CONTRACTOR CONTRACTOR
1.00 1.20
LINDE
CONTRACTOR
0.20
LINDE LINDE LINDE
CONTRACTOR CONTRACTOR CONTRACTOR
0.30 0.30 0.40
LINDE
CONTRACTOR
0.20
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 1.00 1.20 0.00 0.00 0.20 0.00 0.30 0.30 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 780.00 81.60 0.00 0.00 420.00 0.00 60.00 150.00 160.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 340.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 780.00 81.60 0.00 0.00 420.00 0.00 60.00 150.00 160.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 340.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.2.14 4.2.15 4.2.16 4.2.17 4.2.18 4.2.19 4.2.20 4.2.21 4.2.22 4.2.23 4.2.24 4.2.25 4.2.26 4.2.27 4.2.28 4.2.29 4.2.30 4.2.31 4.2.32 4.2.33 4.2.34 4.2.35 4.2.36 4.2.37 4.2.38 4.2.39 4.2.40 4.2.41 4.2.42 4.2.43 4.2.44 4.2.45 4.2.46 4.2.47 4.2.48 4.2.49 4.2.50 4.2.51 4.2.52 4.2.53 4.2.54 4.2.55 4.2.56
No. Rev. Description of Pricesposition Electrical Installation
XLPE-SWA 3x50/16 6,35/11 XLPE-SWA 3x70/16 6,35/11 XLPE-SWA 3x95/16 6,35/11 XLPE-SWA 3x120/16 6,35/11 XLPE-SWA 3x150/25 6,35/11 XLPE-SWA 3x185/25 6,35/11 XLPE-SWA 3x240/25 6,35/11
XLPE-SWA 3x95/16 19/33 XLPE-SWA 3x185/25 19/33 XLPE-SWA 3x240/25 19/33
XLPE-AWA 1x300 0,6/1 XLPE-AWA 1x400 0,6/1 XLPE-AWA 1x500 0,6/1
XLPE-SWA 3x2,5 0,6/1 XLPE-SWA 3x4 0,6/1 XLPE-SWA 3x6 0,6/1 XLPE-SWA 3x10 0,6/1 XLPE-SWA 3x16 0,6/1 XLPE-SWA 3x25/16 0,6/1 XLPE-SWA 3x35/16 0,6/1 XLPE-SWA 3x50/25 0,6/1 XLPE-SWA 3x70/35 0,6/1 XLPE-SWA 3x95/50 0,6/1 XLPE-SWA 3x120/70 0,6/1 XLPE-SWA 3x150/70 0,6/1 XLPE-SWA 3x185/95 0,6/1
XLPE-SWA 4x2,5 0,6/1 XLPE-SWA 4x4 0,6/1 XLPE-SWA 4x6 0,6/1 XLPE-SWA 4x10 0,6/1 XLPE-SWA 4x16 0,6/1 XLPE-SWA 4x25 0,6/1 XLPE-SWA 4x35 0,6/1 XLPE-SWA 4x50 0,6/1 XLPE-SWA 4x70 0,6/1
Code of 1 Acc X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL
Unit Qty. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
Quantity
Supply
Main Order Forecast material
10
65
2 16
26 6 6 4
0 0 0 10 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 65 0 0 0 0 0 0 0 2 0 16 0 0 0 0 26 4 6 6 4 0 0 0 0
LINDE
Time per Unit price Bulk material
Unit in Min.
Work Manhour
CONTRACTOR
2.00
CONTRACTOR CONTRACTOR
0.40
CONTRACTOR CONTRACTOR
0.80
CONTRACTOR CONTRACTOR
2.00
CONTRACTOR CONTRACTOR
0.50
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR
0.50 0.80 0.80
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80 0.00 2.00 0.00 0.00 0.00 0.00 0.50 0.00 0.50 0.80 0.80 0.00 0.00 0.00 0.00
0.00 0.00 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.60 0.00 32.00 0.00 0.00 0.00 0.00 13.00 0.00 3.00 4.80 3.20 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.60 0.00 32.00 0.00 0.00 0.00 0.00 13.00 0.00 3.00 4.80 3.20 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.2.57 4.2.58 4.2.59 4.2.60 4.2.61 4.2.62 4.2.63 4.2.64 4.2.65 4.2.66 4.2.67 4.2.68 4.2.69 4.2.70 4.2.71 4.2.72 4.2.73 4.3. 4.3.1 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 4.3.8 4.3.9 4.3.10 4.3.11 4.3.12 4.3.13 4.3.14 4.3.15 4.3.16 4.3.17 4.3.18 4.3.19 4.3.20 4.3.21 4.3.22 4.3.23 4.3.24 4.3.25
No. Rev. Description of Pricesposition Electrical Installation
XLPE-SWA 4x95 0,6/1 XLPE-SWA 4x120 0,6/1 XLPE-SWA 4x150 0,6/1 XLPE-SWA 4x185 0,6/1
XLPE-SWA CC 5x2,5 0,6/1 XLPE-SWA CC 7x2,5 0,6/1 XLPE-SWA CC 12x2,5 0,6/1 XLPE-SWA CC 19x2,5 0,6/1 XLPE-SWA 24x1,5 0,6/1 Cu 1x16 0,6/1 Cu 1x70 0,6/1 Cu 1x95 0,6/1 Cable Connection Field XLPE-SWA 3x25/16 3,8/6,6 XLPE-SWA 3x35/16 3,8/6,6 XLPE-SWA 3x50/16 3,8/6,6 XLPE-SWA 3x70/16 3,8/6,6 XLPE-SWA 3x95/16 3,8/6,6 XLPE-SWA 3x120/16 3,8/6,6 XLPE-SWA 3x150/25 3,8/6,6 XLPE-SWA 3x185/25 3,8/6,6 XLPE-SWA 3x240/25 3,8/6,6
XLPE-SWA 3x35/16 6,35/11 XLPE-SWA 3x50/16 6,35/11 XLPE-SWA 3x70/16 6,35/11 XLPE-SWA 3x95/16 6,35/11 XLPE-SWA 3x120/16 6,35/11 XLPE-SWA 3x150/25 6,35/11 XLPE-SWA 3x185/25 6,35/11 XLPE-SWA 3x240/25 6,35/11
XLPE-SWA 3x95/16 19/33 XLPE-SWA 3x185/25 19/33 XLPE-SWA 3x240/25 19/33
Code of 1 Acc
Unit Qty.
X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL X1EL
pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM
pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
Quantity
Supply
Main Order Forecast material
17
Time per Unit price Bulk material
0 0 0 0 0 0 17 CONTRACTOR CONTRACTOR 28 0 0 0 0 0 0
Unit in Min.
Work Manhour
0.50
0 0
10
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 10 LINDE 0 0 0 0 0 0 0 0
CONTRACTOR
2.00
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 8.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 8.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0 0
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 20.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.3.26 4.3.27 4.3.28 4.3.29 4.3.30 4.3.31 4.3.32 4.3.33 4.3.34 4.3.35 4.3.36 4.3.37 4.3.38 4.3.39 4.3.40 4.3.41 4.3.42 4.3.43 4.3.44 4.3.45 4.3.46 4.3.47 4.3.48 4.3.49 4.3.50 4.3.51 4.3.52 4.3.53 4.3.54 4.3.55 4.3.56 4.3.57 4.3.58 4.3.59 4.3.60 4.3.61 4.3.62 4.3.63 4.3.64 4.3.65 4.3.66 4.3.67 4.3.68
No. Rev. Description of Pricesposition Electrical Installation
XLPE-AWA 1x300 0,6/1 XLPE-AWA 1x400 0,6/1 XLPE-AWA 1x500 0,6/1
XLPE-SWA 3x2,5 0,6/1 XLPE-SWA 3x4 0,6/1 XLPE-SWA 3x6 0,6/1 XLPE-SWA 3x10 0,6/1 XLPE-SWA 3x16 0,6/1 XLPE-SWA 3x25/16 0,6/1 XLPE-SWA 3x35/16 0,6/1 XLPE-SWA 3x50/25 0,6/1 XLPE-SWA 3x70/35 0,6/1 XLPE-SWA 3x95/50 0,6/1 XLPE-SWA 3x120/70 0,6/1 XLPE-SWA 3x150/70 0,6/1 XLPE-SWA 3x185/95 0,6/1
XLPE-SWA 4x2,5 0,6/1 XLPE-SWA 4x4 0,6/1 XLPE-SWA 4x6 0,6/1 XLPE-SWA 4x10 0,6/1 XLPE-SWA 4x16 0,6/1 XLPE-SWA 4x25 0,6/1 XLPE-SWA 4x35 0,6/1 XLPE-SWA 4x50 0,6/1 XLPE-SWA 4x70 0,6/1 XLPE-SWA 4x95 0,6/1 XLPE-SWA 4x120 0,6/1 XLPE-SWA 4x150 0,6/1 XLPE-SWA 4x185 0,6/1
XLPE-SWA CC 5x2,5 0,6/1 XLPE-SWA CC 7x2,5 0,6/1 XLPE-SWA CC 12x2,5 0,6/1 XLPE-SWA CC 19x2,5 0,6/1
Code of 1 Acc X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM X1EM
Unit Qty. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
Quantity
Supply
Main Order Forecast material
65
2 16
26 6 6 4
17
0 0 0 0 0 0 0 65 0 0 0 0 0 0 0 2 0 16 0 0 0 0 26 0 6 6 4 0 0 0 0 0 0 0 0 0 0 17 0 0 0 0 0
Time per Unit price Bulk material
Unit in Min.
Work Manhour
CONTRACTOR CONTRACTOR
0.40
CONTRACTOR CONTRACTOR
0.80
CONTRACTOR CONTRACTOR
2.00
CONTRACTOR CONTRACTOR
0.50
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR
0.50 0.80 0.80
CONTRACTOR CONTRACTOR
0.50
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.40 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80 0.00 2.00 0.00 0.00 0.00 0.00 0.50 0.00 0.50 0.80 0.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.50 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.60 0.00 32.00 0.00 0.00 0.00 0.00 13.00 0.00 3.00 4.80 3.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.50 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 26.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.60 0.00 32.00 0.00 0.00 0.00 0.00 13.00 0.00 3.00 4.80 3.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8.50 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
4.3.69 4.3.70 4.3.71 4.3.72 4.3.73 4.3.74 5.
5.1
5.2
5.3
5.4
5.5
5.1
5.6
5.7 5.8 5.9 5.10 6. 6.1
No. Rev. Description of Pricesposition Electrical Installation
Cu 1x25 0,6/1 Cu 1x70 0,6/1 Cu 1x95 0,6/1
Code of 1 Acc X1EM X1EM X1EM X1EM X1EM X1EM
Unit Qty. pc. pc. pc. pc. pc. pc.
Quantity
Supply
Main Order Forecast material 0 0 0 0 0 0
Time per Unit price Bulk material
Unit in Min.
Work Manhour
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0
216.00
0
240.00
0
144.00
0
72.00
0
264.00
0
648.00
0
60.00
0
40.00
0
0.00 0.00 0.00
0 0 0
0.00
0
Material costs Total costs
Installation of Lighting System X1E5 All mounting material (incl. metall poles/columns, metal mounting plates, fitting accessories, coating system acc. 0000 T-SS 0001, grey colored, etc.) shall be in scope of the CONTRACTOR. X1EN Installation of lighting fixture acc. to standard type A1-18, flourescent lamp, incl. pole, junction box and LINDE (only CONTRACTOR mounting material, complete assembled and wired pc. 18 18 lighting fittings) ( pole, bulk) 12.00 12.00 216.00 0.00 X1EN Installation of lighting fixture acc. to standard type B4-70, high pressure sodium lamp, incl. pole, junction box and mounting material, complete assembled and LINDE (only CONTRACTOR wired pc. 20 20 lighting fittings) ( pole, bulk) 12.00 12.00 240.00 0.00 X1EN Installation of lighting fixture acc. to standard type LINDE (only CONTRACTOR D1-18/58, flourescent lamp, junction box and mounting material, complete assembled and wired pc. 12 12 lighting fittings) ( pole, bulk) 12.00 12.00 144.00 0.00 X1EN Installation of lighting fixture acc. to standard type D3-250, high-pressure mercury lamp, junction box and LINDE (only CONTRACTOR mounting material, complete assembled and wired pc. 6 6 lighting fittings) ( pole, bulk) 12.00 12.00 72.00 0.00 X1EN Installation of lighting fixture acc. to standard type E1-18/58, flourescent lamp, Ex 2x36W, incl. wall bracket, junction box and mounting material, complete LINDE (only CONTRACTOR assembled and wired pc. 22 22 lighting fittings) ( pole, bulk) 12.00 12.00 264.00 0.00 Installation of street light columns acc. to standard type X1EN S1-250, pole height 8m, high pressure sodium lamp, incl. column, junction box and mounting material, LINDE (only CONTRACTOR complete assembled and wired pc. 27 27 lighting fittings) ( pole, bulk) 24.00 24.00 648.00 0.00 X1EN Installation of individual junction boxes, plastic type, with max. 4 cable entries, cable up to 10 mm², incl. plating and mounting material, complete assembled and wired pc. 5 5 LINDE CONTRACTOR 12.00 12.00 60.00 0.00 X1EN Installation of manual switch/pushbutton (ON/OFF), plastic housing, incl. plating and mounting material, complete assembled and wired pc. 5 5 LINDE CONTRACTOR 8.00 8.00 40.00 0.00 X1EN Installation of photo cell incl. plating and mounting material, complete assembled and wired pc. 0 0.00 0.00 0.00 X1EN pc. 0 0.00 0.00 0.00 X1EN pc. 0 0.00 0.00 0.00 Installation of Heat Tracing X1E6 Installation of self limiting heating cable
X1EP
m
0
0.00
0.00
0.00
Total Time
Price List for Electrical Installation GASCO Air Separation Unit Pos.
6.2 6.3 6.4 6.5 6.6 7. 7.1. 7.1.1 7.1.2 7.1.3 7.1.4 7.1.5 7.1.6 7.1.7 7.1.8 7.1.9 7.1.10 7.1.11 7.1.12 7.1.13 7.1.14 7.1.15 7.1.16 7.1.17 7.1.18 7.1.19 7.1.20 7.1.21 7.1.22 7.1.23 7.1.24 7.1.25 7.1.26 7.2. 7.2.1 7.2.2
No. Rev. Description of Pricesposition Electrical Installation
Connection of a leflimiting heating cable including installation of terminal box to pipe, insulation bushing, sealing of insulation Installation of End seal Installation of warning lable "Electrically heated" on Insulation Installation of Thermostate to Pipe including installation of temperature probe Earthing / Lighning Protection and Cathodic Corr. Protection Earthing / Lighning Protection Installation of Earthing conductor 16mm² copper, yellow/green insulated 35mm² copper, yellow/green insulated 50mm² copper, yellow/green insulated 70mm² copper, yellow/green insulated 95mm² copper, yellow/green insulated 120mm² copper, yellow/green insulated
Code of 1 Acc
Unit Qty.
Quantity
Supply
Main Order Forecast material
Cathodic Corrosion Protection
Unit in Min.
Work Manhour
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
Material costs Total costs
Total Time
X1EP X1EP
pc. pc.
0 0
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0 0
X1EP
pc.
0
0.00
0.00
0.00
0.00
0
X1EP X1EP
pc. pc.
0 0
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0 0
0.00 0.20 0.00 0.20 0.00 0.00
0.00 40.00 0.00 160.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00
0.00 40.00 0.00 160.00 0.00 0.00
0 0 0 0 0 0
0.00 0.20 0.00 0.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 8.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 8.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0 0 0
X1E7 X1ER X1ER X1ER X1ER X1ER X1ER X1ER
m 0 m 200 200 m 0 m 800 800 m 0 m 0 Connection of Earthing conductor yellow/green to existing structure or equipment 16mm² copper, yellow/green insulated X1ER pc. 0 35mm² copper, yellow/green insulated X1ER pc. 40 40 50mm² copper, yellow/green insulated X1ER pc. 0 70mm² copper, yellow/green insulated X1ER pc. 20 20 95mm² copper, yellow/green insulated X1ER pc. 0 120mm² copper, yellow/green insulated X1ER pc. 0 Installation of earthing busbar X1ER pc. 0 Installation of a T-splice X1ER 0 16mm² X1ER pc. 0 25mm² X1ER pc. 0 50mm² X1ER pc. 0 70mm² X1ER pc. 0 95mm² X1ER pc. 0 120mm² X1ER pc. 0 Installation of galvanized earthing strip 30 x 3,5 mm Connection of galvanized earthing strip 30 x 3,5 mm to existing structure or equipment Welding of earthing lug to existing structure and corrossion protection Earth cable branch connection Installation of earthing rod / electrode ( E-ZC-1120 )
Time per Unit price Bulk material
Project Number:
CONTRACTOR CONTRACTOR
0.20
CONTRACTOR CONTRACTOR
0.20
CONTRACTOR CONTRACTOR
0.20
CONTRACTOR CONTRACTOR
0.20
X1ER
m
0
0.00
0.00
0.00
0.00
0
X1ER
pc.
0
0.00
0.00
0.00
0.00
0
X1ER X1ER X1ER X1ER
pc. pc. pc. pc.
0.00 0.50 8.00 0.00
0.00 50.00 160.00 0.00
0.00 0.00 0.00 0.00
0.00 50.00 160.00 0.00
0 0 0 0
X1ES X1ES X1ES
pc. pc.
0.00 0.00
0.00 0.00
0.00 0.00
0.00 0.00
0 0
100 20
0 100 CONTRACTOR CONTRACTOR 20 CONTRACTOR CONTRACTOR 0 0 0
0.50 8.00
Price List for Electrical Installation GASCO Air Separation Unit Pos.
7.2.3 7.2.4 7.2.5 7.2.6 7.2.7 7.2.8 7.2.9 7.2.10 7.2.11 7.2.12 7.2.13 7.2.14 8. 8.1 8.2 8.3 8.4 8.5 8.6 8.7 8.8 8.9 8.10 8.11 8.12 8.13 9. 9.1 9.2 9.3 9.4 9.5 9.6 9.7 9.8 9.9
No. Rev. Description of Pricesposition Electrical Installation
Code of 1 Acc
Unit Qty.
Quantity
Main Order Forecast material
X1ES X1ES X1ES X1ES X1ES X1ES X1ES X1ES X1ES X1ES X1ES X1ES
pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
Communication Systems Installation of Fire Alarm Panel Installation smoke detector Installation af manual alarm button indoor Installation of Intercomsystem (19"-rack) Installation of Operator Console Unit Installation of Call Station indoor Installation of Loudspeaker Installation of CCTV System (19"-rack) Installation of Camera incl. junction box Installation of Monitor Manual Alarm outdoor w.
X1E8 X1ET X1ET X1ET X1ET X1ET X1ET X1ET X1ET X1ET X1ET X1ET
pc. pc. pc. pc. pc. pc. pc. pc. pc. pc. pc.
1 30 10 1 1 6 14 1 5 1 7
Call station outdoor incl. support
X1ET
pc.
4
junction box incl. support
X1ET
Modification- and Testing Hourly rates for foreman /engineer Hourly rates for electrician/helper Hourly rates for test engineer Modification work general
X1E9 X1EU X1EU X1EU X1EU X1EU X1EU X1EU X1EU X1EU
pc. h h h h
Supply
Time per Unit price Bulk material
Unit in Min.
Work Manhour
0 0 0 0 0 0 0 0 0 0 0 0
4 50 100 30
1 30 10 1 1 6 14 1 5 1 7
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Manhour
Manhour
Manhour
h
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0 0 0 0
Material costs Total costs
Total Time
LINDE LINDE LINDE LINDE LINDE LINDE LINDE LINDE LINDE LINDE LINDE
CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR CONTRACTOR
16.00 4.00 4.00 16.00 4.00 4.00 4.00 16.00 4.00 4.00 4.00
16.00 4.00 4.00 16.00 4.00 4.00 4.00 16.00 4.00 4.00 4.00
16.00 120.00 40.00 16.00 4.00 24.00 56.00 16.00 20.00 4.00 28.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
16.00 120.00 40.00 16.00 4.00 24.00 56.00 16.00 20.00 4.00 28.00
0 0 0 0 0 0 0 0 0 0 0
4 LINDE
CONTRACTOR ( support, bulk)
4.00
4.00
16.00
0.00
16.00
0
4 LINDE
CONTRACTOR ( support, bulk)
4.00
4.00
16.00
0.00
16.00
0
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
0 0 0 0 0 0 0 0 0
0 0 128
0 0 0
0 0 128
0 0 0
50 CONTRACTOR CONTRACTOR 100 CONTRACTOR CONTRACTOR 30 CONTRACTOR CONTRACTOR 0 0 0 0 0 0
Installation Costs overview 1. 2. 2.1.
Contractors Site Facilities X1E1 Equipment Installation X1E2 Equipment Installation LV/MV Container, Transformers X1EA
Price List for Electrical Installation GASCO Air Separation Unit Pos.
2.2. 3. 3.1. 3.2. 4. 4.1. 4.2. 4.3. 5. 6. 7. 7.1. 7.2. 8. 9.
No. Rev. Description of Pricesposition Electrical Installation
Code
Unit
of 1 Acc
Qty.
Quantity
Main Order Forecast material
X1EB Equipment Installation Field X1E3 Installation of Cable Support System Installation of Cable Support System below LV/MV container X1ED X1EE Installation of Cable Support System in Field Cable Pulling and Connection X1E4 X1EH Cable Pulling Feeder Cables X1EL Cable Connection Feeder Cables within Container X1EM Cable Connection Field Installation of Lighting System X1EN Installation of Heat Tracing X1EP Earthing / Lighning Protection and Cathodic Corr. Protection X1E7 Earthing / Lighning Protection X1ER Cathodic Corrosion Protection X1ES Communication Systems X1ET Modification- and Testing X1EU
Total costs
Supply
Manhour
Time per Unit price Bulk material
Unit in Min.
Work Manhour
Project Number:
1110 A02K
Project Code:
Ruweis
Document Number:
W-LX 1100
Total costs Material Manhour
Total price Manhour
Labour costs
Material costs Total costs
Total Time
Manhour
Manhour
Manhour
h
585 0 176 2,044 0 4,205 112 112 1,684 0 0 422 0 376 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
585 0 176 2,044 0 4,205 112 112 1,684 0 0 422 0 376 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
9,844
0
9,844
0