Perhitungan pile cap (Dimensi 170 cm X 235 cm X 350 cm) Volume pile cap : 1,7 m X 2,35 m X 3,5 m= 13,98 m3 D16 = 1,58 kg/m Lebar = 235 cm – (selimut beton) = 235 cm – 8 cm = 227 cm = 2,27 m
Jumlah tulangan
Tinggi = 350 cm / 20 cm ( spasi antar tulangan) = 17,5 = 18 tulangan Jadi total berat tulangan:
2,27 m X 18 X 1,58 kg/m = 64,56 kg 2,27 m X 18 X 1,58 kg/m = 64,56 kg 0,18 m X 2 X 1,58 kg/m = 0,57 kg 0,34 m X 2 X 1,58 kg/m = 1,07 kg + 130,76 kg
D25 = 3,85 kg/m Tinggi = 350 cm Jumlah tulangan = 15 tulangan Jadi total berat tulangan: 3,5 m X 15 X 3,85 kg/m = 202,13 kg 0,2 m X 15 X 3,85 kg/m = 11,55 kg + 213,68 kg
D13 = 1,004 kg/m