ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE
Health, Safety and Environmental Management Health, Safety & Environmental Impact Assessment Guidelines Guidelines
Page
H
Effective Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
HEALTH, SAFETY AND ENVIRONMENTAL MANAGEMENT POLICY GUIDELINES
ADNOC GROUP Guidelines on HEALTH, SAFETY & ENVIRONMENTAL IMPACT ASSESSMENT
APPROVED BY :
DATE: GENERAL MANAGER
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 1 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
TABLE OF CONTENTS
1. INTRODUCTION TO IMPACT ASSESSMENT............................................................................................................2 2. REQUIREMENTS FOR HSEIA........................................................................................................................................2 3. PROJECT PHASES............................................................................................................................................................4 4. DEMINIMIS DETERMINATIONS .................................................................................................................................5
4.1. NO IMPACT..............................................................................................................................................................5 4.2. DEMINIMIS IMPACT DETERMINATION ..............................................................................................................................5 4.2.1. Construction...........................................................................................................................................................5 4.2.1.1. 4.2.1.2. 4.2.1.3. 4.2.1.4. 4.2.1.5. 4.2.1.6.
Air...................................................................................................................................................................................5 Surface Water..................................................................................................................................................................6 Ground Water..................................................................................................................................................................6 Solid Wastes....................................................................................................................................................................6 Hazardous Wastes...........................................................................................................................................................6 Noise...............................................................................................................................................................................7
4.2.2. Operation or Decommissioning.............................................................................................................................7 4.2.2.1. 4.2.2.2. 4.2.2.3. 4.2.2.4. 4.2.2.5. 4.2.2.6.
Air...................................................................................................................................................................................7 Surface Water..................................................................................................................................................................7 Ground Water..................................................................................................................................................................7 Solid Wastes....................................................................................................................................................................8 Hazardous Wastes...........................................................................................................................................................8 Noise...............................................................................................................................................................................8
4.3. OTHER R EQUIREMENTS OF DEMINIMIS PROJECTS..............................................................................................................8 4.4. LISTED DEMINIMIS PROJECTS.......................................................................................................................................9 4.4.1. Criteria..................................................................................................................................................................9 4.4.2. Listed Projects.....................................................................................................................................................10 4.5. DETERMINATION OF DISCHARGES .................................................................................................................................10 5. OVERALL IMPACTS:.....................................................................................................................................................10 6. ADDITIVE IMPACTS:.....................................................................................................................................................10 7. APPROVAL PROCESS:...................................................................................................................................................11
7.1. DEMINIMIS :............................................................................................................................................................11 7.2. HSEIA R EQUIRED:.................................................................................................................................................11 7.3. OTHER APPROVALS..................................................................................................................................................11 8. HEALTH, SAFETY AND ENVIRONMENTAL IMPACT ASSESSMENT (HSEIA)..............................................11
8.1. LIFE CYCLE DOCUMENT..........................................................................................................................................11 8.2. HSEIA DOCUMENT STRUCTURE ...............................................................................................................................11 8.2.1. Executive Summary.............................................................................................................................................11 8.2.2. HSE Impact Assessment Summary......................................................................................................................12 8.2.3. HSE Data and Assessments.................................................................................................................................14
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 2 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
1...................................INTRODUCTION TO IMPACT ASSESSMENT An Environmental Impact Assessment (EIA) means an examination, analysis and assessment of potential environmental impacts of new projects and major modifications of existing operations, with a view to ensure environmentally sound and sustainable development. In the EIA process all relevant significant environmental issues must be identified and duly addressed. Likewise, the possible impacts on employees, neighbouring communities and continued operation of ADNOC Group facilities must be addressed by including Health and Safety issues. This Health, Safety and Environmental Impact Assessment (HSEIA) will provide a true evaluation of all project Health, Safety & Environmental (HSE) aspects. All efforts must be made to identify these issues at the conceptual stage of the project. For new projects it must be determined whether or not a project will require a complete HSEIA or be deemed deminimis. If assessed deminimis, it may proceed with the approval of the Group or Affiliate Company HSE Manager/Department Head. Otherwise, for those major, new projects an HSEIA will be required. The screening process to make a deminimis determination is based mostly on environmental impact assessment criteria. For such deminimis projects it is presumed that the existing company Occupational Health, Safety and Community Awareness Programs are sufficient. However, if the project fails the deminimis screening criteria and is deemed to be a major project, a full HSEIA is required. This issue of deminimis determination and the threshold values for the determination will allow flexibility while complying with the impact assessment requirement of Law Number 1 of 1997 on the revision of Law Number 4 of 1996 on the Establishment of Environment and Natural Life Research and Development Authority (ENLRDA). Likewise, it will satisfy the U.A.E. Federal Environment Agency (FEA) requirements. The deminimis and new project criteria are described below in this document.
2..............................................................REQUIREMENTS FOR HSEIA Unless otherwise specifically stated in this guideline: A Health, Safety and Environmental Impact Assessment (HSEIA) will be required for new hydrocarbon related projects and projects involving modifications to existing operations. This will include, for ADNOC, its Group Companies and Affiliates, at least the following: a)
Seismic surveys
b)
Exploration drilling
c)
Field development
d)
Well testing
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 3 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
e)
Producing operations
f)
Pipeline construction
g)
Terminaling and Loading operations
h)
Gas Processing & LNG facilities
i)
Petroleum distillation, refining, reforming, recycling
j)
Chemical and Petrochemical operations
k)
Marketing and Sales
l)
Power Generation and other utilities
m)
Potable Water Production
n)
Owned and leased buildings
o)
Waste treating, handling, storage and disposal operations
p)
Other projects with potential to cause significant harm or impacts to the environment or health and safety of our employees and neighbours.
HSEIAs are to be prepared for each of the four phases of a project. Each phase may be considered separately or two or more phases combined into an integrated document. Each HSEIA phase must be satisfactorily completed and approved before the project may proceed. It is intended that Phase I must be approved before the project moves to final design and tender. Phase II must be approved before construction starts. Phase III should be approved before construction starts and must be approved before operations begin. Phase IV which comes at the end of a project’s life should be addressed and approved before shutdown. Planning must allow for the time required to accomplish the HSEIA preparation, review and approval by ADNOC. For some projects it may be necessary for the Abu Dhabi ENLRDA and /or FEA, as appropriate to review and approve the HSEIA. The HSEIA is to be prepared by a third party that is independent of the project contractor or sub-contractor. This independent contractor should not be hired by the project contractor. The HSEIA Contractor should be hired directly by the Operating Company or Projects Directorate to avoid any conflict of interest. Projects addressed in previously approved HSEIAs or that are deemed deminimis (not major) as described in Section 4 may be exempted from this process.
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 4 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
3...................................................................................PROJECT PHASES For the purpose expressed in this document, it should be considered that a project consists of four stages. These are termed as Phase I, Phase II, Phase III and Phase IV. These phases describe certain time periods during the conception, design, tender, construction, operation, decommissioning and site restoration of a project. Phase I: Conceptual Design and FEED stage (Front End Engineering and Design) of the project - included is all work up to the decision to go to final design and/or tender for the project. The Phase I HSEIA must be approved before the project may proceed to Phase II. Phase II: Construction phase of the project - commences at the end of the FEED stage and encompasses tender and award, mobilisation, construction, performance testing, acceptance of the finished project and demobilisation of contractor. The Phase II HSEIA must be approved before the actual start of construction. Phase III: Operational phase of a project - commences at acceptance from contractor of finished project for continuous operation. The Phase III HSEIA should be approved before construction starts but must be approved before normal operations begin. Phase IV: Shutdown phase of a project - the shutdown, mothballing, decommissioning, and/or removal or discontinuation of an operation, including site restoration. The Phase IV HSEIA should be approved before such decommissioning starts. Phase IV should be addressed in the Phase I and Phase II HSEIAs to assure the “design out” of decommissioning and site restoration issues. By addressing Phase IV up front, total project costs can be evaluated.
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 5 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
4........................................................DEMINIMIS DETERMINATIONS For purposes of this section a project may be deemed to have no impacts or to have minimal impacts. Such projects will be termed “deminimis” and will not require a HSEIA. To qualify for a deminimis determination a project must meet the following conditions of sub-sections 4.1 to 4.5. A project can be deemed to have “no impact” if all of the conditions of subsections 4.1 and 4.3 are met. A project can be deemed to have “deminimis impact” if all of the conditions of subsections 4.2 and 4.3 are met. A project can be deemed to have “deminimis impacts” if a procedure is developed, approved by ADNOC Group HSE Committee, and the procedure, which is to be strictly followed, is listed in subsection 4.4.
4.1.......................................................................................................................No Impact 4.1.1. There will be no change in the quantity or quality of existing emissions, effluents, or wastes will not result from the operational phase of the project. An increase in the amount or a change in the type or components of the discharges will be considered “new”. 4.1.2. No new infrastructure such as building, rebuilding or enlarging of camps, utilities, government services, roads, etc. will be required. [This does not include routine maintenance and refurbishment.] 4.1.3. All criteria of the ADNOC HSE Guidelines must be met for discharges to the air, land, surface water and groundwater during the project phase.
4.2.................................................................................Deminimis Impact Determination 4.2.1.........................................................................................................Construction During construction, reconstruction, plant turnarounds and start-up of a project that will create new emissions, effluents or wastes, the discharges to the air (excluding exhaust emission from construction vehicles), land, surface water or ground water shall not exceed: 4.2.1.1.
Air
Pollutant
Chalr/Rnc/18-2-97
U.S. Ton/Yr.
Metric Ton/Yr.
lbs/24hrs.
Kg/24hrs.
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 6 of 0
Health, Safety and Environmental Management
Effective Date: April 15, 1997
Health, Safety & Environmental Impact Assessment Guidelines
Approved by General Manager Version: 1.0
NOx
250
227
6,000
2,700
SOx
250
227
6,000
2,700
1,000
910
24,000
11,000
250
227
6,000
2,700
PAH/BETEX
25
22
600
270
H2S
17
15
400
180
PM10 *
---
---
---
CO VOC
* 4.2.1.2.
150µg/m3
24 hour Average
Surface Water
Must meet ADNOC HSE Guideline limits. 4.2.1.3.
Ground Water
Injected water must meet ADNOC HSE Guidelines for formation selection. Discharges to soil surface or unlined pits must meet ADNOC HSE Guidelines for Discharges to the Desert. 4.2.1.4.
Solid Wastes
No solid wastes such as galley wastes, garbage, office and camp trash, paint debris, etc., will be disposed on site. Wastes can be disposed at existing ADNOC approved garbage disposal sites. This subsection does not include inert, non-hazardous construction debris recycled as fill or materials for firewalls, drainage, road or other civil construction. [The intent is not to dispose of waste that can be putrescible, infectious, attract vermin/pests, or be hazardous. Also, no wastes are to be disposed that could decay, dissolve, corrode, etc. and thus cause a fill area (burialsite) to slump, cave-in or otherwise present a possible safety hazard.] For future liability control, efforts must be made to confine disposal to a few, approved, managed sites. 4.2.1.5.
Hazardous Wastes
No hazardous materials will be disposed on site. No more than 100 Kg (220 lbs) of hazardous wastes in total can be generated. All such wastes will be handled, stored, transported and disposed according to ADNOC HSE Guidelines.
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 7 of 0
Health, Safety and Environmental Management
Effective Date: April 15, 1997
Health, Safety & Environmental Impact Assessment Guidelines
Approved by General Manager Version: 1.0
4.2.1.6.
Noise
Maximum cannot exceed 115 dB(A) at worksite, weighted average cannot exceed 85 dB(A) 1m from equipment. Weighted average cannot exceed, at the closest point of public contact or the fence line, 60 dB(A) during day light hours or 40 dB(A) during non-daylight hours.
4.2.2. Operation or Decommissioning During operation or decommissioning of the project, discharges to the air, land, surface water or ground water shall not exceed: 4.2.2.1.
Air
Pollutant
U.S. Ton/Yr.
Metric Ton/Yr.
lbs/24hrs.
Kg/24hrs.
NOx
250
227
2,000
910
SOx
250
227
2,000
910
1,000
910
3,000
1,360
250
227
2,000
910
PAH/BETEX
25
22
200
90
H2S
17
15
100
45
PM10 *
---
---
---
CO VOC
150µg/m3
* 24 hour Average 4.2.2.2.
Surface Water
Must meet ADNOC HSE Guideline limits. 4.2.2.3.
Ground Water
Injected water must meet ADNOC HSE Guidelines for formation selection. Discharges to soil surface or unlined pits must meet ADNOC HSE Guidelines for Discharges to the Desert. Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 8 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
4.2.2.4.
Solid Wastes
No solid wastes such as galley wastes, garbage, office and camp trash, paint debris, etc., will be disposed on site. Wastes can be disposed at existing ADNOC approved garbage disposal sites. This subsection does not include inert, non-hazardous construction debris recycled as fill or materials for firewalls, drainage, road or other civil construction. [The intent is not to dispose of waste that can be putrescible, infectious, attract vermin/pests, or be hazardous. Also, no wastes are to be disposed that could decay, dissolve, corrode, etc. and thus cause a fill area (burialsite) to slump, cave-in or otherwise present a possible safety hazard.] For future liability control, efforts must be made to confine disposal to a few, approved, managed sites. Coming 4.2.2.5.
Hazardous Wastes
No hazardous materials will be disposed on site except through ADNOC approved deep well injection or incineration. All ADNOC HSE Guidelines and provisions of 4.2.2.1 to 4.2.2.3 above must be observed. (It is desirable to first not generate such wastes and for those so generated to dispose of them at the ADNOC Waste Treatment and Disposal Facility.) 4.2.2.6.
Noise
Maximum cannot exceed 115 dB(A) at worksite, weighted average cannot exceed 85 dB(A) 1m from equipment. Weighted average cannot exceed, at the closest point of public contact or the fence line, 60 dB(A) during day light hours or 40 dB(A) during non-daylight hours.
4.3.
Other Requirements of Deminimis Projects 4.3.1. The project, when combined with emissions to the air from other nearby sources within a 16 km radius, during normal operation, will not contribute to degradation of the ambient air by more than 5% for any one pollutant, nor will combined impacts from all area sources exceed ADNOC HSE Guidelines. 4.3.2. The project, when combined with discharges to surface water from other surrounding sources within a 5 km radius, during normal operation, will not contribute to degradation of the ambient surface water quality conditions by more than 1% at the perimeter of a 500 meter radius from the outfall and must meet ADNOC HSE Guidelines for discharges to surface water. 4.3.3. Any wastes injected to underground formations in onshore areas shall be injected to Dammam, Simsima or Umm El Radhuma or deeper formations. In offshore
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 9 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
areas these same formations may be used. Alternate formations may be used. However, the formation must have a seal /cap so as to prevent possible migration upward to usable groundwater as defined in the ADNOC HSE Guidelines. Offshore, the seal/cap must prevent migration upward to the sea. Alternate formations must be approved by ADNOC E&S Division. 4.3.4. On site construction shall not last more than 90 consecutive calendar days. 4.3.5. An existing building that is purchased or leased and was not purposely built for ADNOC, Group Companies or Affiliates and will require only minor refitting or decorating will be considered deminimis. [The intent here is to avoid the commissioning of buildings that have not reviewed and approved under the ADNOC HSEIA and ADNOC HSE Guidelines.] 4.3.6. The project is located more than 1.5km from a home, business, park, wildlife refuge, archaeological site, public road or other public accommodation area. [This distance criteria does not include other ADNOC industrial facilities, camps and housing. Likewise, it does not include a project that would be located within a designated industrialised park] 4.3.7. The project will not destroy local specimens of a threatened or endangered species or impact unnecessarily flora and fauna directly or indirectly through excessive discharges and/or habitat degradation.
4.4.
Listed Deminimis Projects
4.4.1. Criteria Certain projects are deemed “deminimis” provided they are included in subsections 4.4.2 Listed Projects, and adhere strictly to the listing criteria. Repetitive projects for which clear, concise, operating parameters can be defined and impacts reduced to As Low As Reasonably Possible (ALARP) can be added to this list upon approval of the ADNOC Group HSE Committee. For each such project there must be the following:
Chalr/Rnc/18-2-97
a)
A written procedure describing the work to be done and the operating parameters
b)
A program to reduce the impacts to ALARP
c)
A risk assessment and development of procedures to protect employees, community and the environment
d)
A work permit system within the company signed by the HSE Manager/Department Head certifying compliance with the agreed criteria.
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 10 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
4.4.2. Listed Projects 4.4.2.1. Projects included in an approved HSEIA and/or permit that may take place after the initial start up or commissioning of the project and adhere strictly to the original HSEIA and do not contravene ADNOC HSE Guidelines. 4.4.2.2. Wells drilled in an existing field according to criteria established in a field development plan approved by the ADNOC Group HSE Committee.
4.5.
Determination of Discharges Discharges may be measured or calculated. The acceptable methods are: 4.5.1. Methods described in the ADNOC Group Manual on Discharge Inventory Compilation Methods. 4.5.2. Use of emission factors as described in U.S. EPA Publication AP-42. 4.5.3. Use of U.S. EPA models (or internationally recognised equivalents) for aquatic discharges. 4.5.4. Use of internationally acceptable air models such as U.S. EPA ISC3 series of models.
5. OVERALL IMPACTS: Each project must be reviewed for all four Phases for its contribution to the degradation of air, land, surface water, groundwater and flora and fauna when combined with all other sources within a 16km radius. It will be reviewed to establish the impacts and risks to employees, the community and ADNOC continued operations.
6. ADDITIVE IMPACTS: 6.1 For projects deemed deminimis, the contribution of that project to air, surface water, groundwater, and waste discharges as well as its impact upon social infrastructure, employee and community risk shall be considered additive. This data shall be provided to ADNOC E&S Division for inclusion in baseline data. 6.2 Multiple deminimis projects within a 8km radius that together exceed ADNOC HSEIA Guideline criteria shall require a HSEIA. For this purpose projects are additive regardless of calendar date built or ownership.
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 11 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
7. APPROVAL PROCESS: For projects the following approval process shall be observed.
7.1.
Deminimis: A plot plan, short description of the operation including Production Process, use of raw materials and chemicals, environmental control equipment, calculated or actual discharges, plus projected risk impacts to employees and community and the environment must be submitted to the OPCO or Affiliate HSE Manager/Department Head for deminimis concurrence. For those projects where increases of emissions, effluents or wastes will occur, the deminimis review and data shall be forwarded onto ADNOC E&S Division for addition to the baseline data for the area.
7.2.
HSEIA Required:
7.2.1. For projects up to 100,000,000 Dirhams (US $ 27,000,000) in total expenditures ADNOC E&S Division can approve all stages of the HSEIA Process. 7.2.2. For projects greater than 100,000,000 Dirhams in total expenditures ADNOC E&S Division will forward the HSEIA to the ADNOC Group HSE Committee for final action.
7.3.
Other Approvals For some projects, such as, for example, construction of roads or buildings, approvals by other authorities may be required. It will be the responsibility of the party proposing the new project to procure these additional approvals.
8. HEALTH, SAFETY AND ENVIRONMENTAL IMPACT ASSESSMENT (HSEIA) 8.1.
Life Cycle Document The HSEIA is to be a document that considers the full life cycle of a project. It shall assess the Health, Safety and Environmental impacts of the proposed project. The project HSEIA shall address each phase of the project as described in Section 3 of this document.
8.2.
HSEIA Document Structure
8.2.1. Executive Summary Shall be in “Layman’s Language”, shall not exceed 10 pages and shall at least be a summary overview of:
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 12 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
a) Project description and background b) Project timing to operation c) Project life cycle d) Raw materials and energy requirements e) Products and by-products produced f) Waste, emissions and effluents g) Significant impacts by phase h) Mitigation measures i) Resultant HSE impact contribution j) On-site/off-site emergency preparedness k) Recommendations and next steps l) Conclusions
8.2.2. HSE Impact Assessment Summary Shall include a summary discussion of the following, including mitigation measures, for each phase of the project and the total projected life of the project. a) Life Cycle description and evaluation b) Siting evaluation c) Environmental Impacts d) Wastes, emissions and effluents and their reduction, substitution, reuse, recycle, elimination and/or disposal e) Occupational and environmental health issues f) Safety issues g) Risk and HAZOPs issues h) Crisis Management and Emergency Action Issues and Plans i) Infrastructure issues
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 13 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
j) Cost and savings of short and long term impacts, control and mitigation measures, and risk reduction
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 14 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
8.2.3. HSE Data and Assessments Shall contain in chapters and/or appendices the collection of data and the resultant analysis of this data. As appropriate, UAE and Abu Dhabi HSE laws and regulations and ADNOC and OPCO or Affiliate HSE Policies and Guidelines will be addressed for each issue. This section contains the data compilation, calculations, methodology, impact analysis, mitigation evaluations and techniques, rational for decisions and references. The impact analysis should include a summary/table of sources and targets, potential impacts and severity. At least the following shall be addressed, where applicable, for each phase and shall be additive for all phases. a) Description of planned action with plot plans and other drawings. This does not need to include detailed Project drawings. Schematic drawings will suffice. Estimated cost of project by phase. b) Time line or proposed schedule with differentiation of on site construction and/or erection vs. offsite work occurring elsewhere in U.A.E. and out of the region. Projected life of the project is to be addressed. c) Descriptions of products and by-product that are to be sold at world market [by-product example - sulphur produced during gas sweetening or refining]. d) A general mass balance for normal operations, scheduled turnarounds, anticipated upset conditions, and emergency shut down situations. Address raw materials and outside provided resources (such as electricity) consumed, processed, manufactured, transported and/or used in this facility or at this site or sites. e) Risk and hazards operation analysis/assessment addressing, as appropriate, at least, fire and explosion, equipment separation for over-pressure control, business interruption, safety, occupational and environmental health exposures, environmental impacts, infrastructure, bottom hazard survey, currents, weather, pipeline releases, feed-stocks, raw materials, chemical usage. To include milestones in the project at which time HSE reviews should occur.
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 15 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
f) Emergency action planning for construction, start-up and operational phases. Include onsite and offsite exposures, risks, resource requirements, and infrastructure requirements. Plans should be compatible with ADNOC Crisis Management Plan and Group Company or Affiliate Plan. It should also address local government plans. g) Site location description of the existing environment, including at least, geography, geology, stratigraphy, seismic activity, soils, vegetation, agriculture, land usage (site and surrounding area), access, water bottoms, reef structures, wetlands, coastal zone management issues and other significant aspects of the chosen location and shall include roads, shipping lanes, pipelines and electrical transmission routes/corridors. h) Meteorology, climatology and air quality on a regional and immediate site basis. Must include 10, 25 and 50 year storm evaluations. Existing air quality and project impacts upon air quality must be addressed. Compare resultant emission and air quality impacts to ADNOC HSE Guidelines. Validated air quality models should be used as a predicting tool for air quality. i) Oceanography of area including currents, bottom survey, bathymetry and water physicochemistry on a regional and site basis. Usage and management of the coastal zone must be discussed where appropriate. j) Ecology of area including common, threatened and endangered species of flora and fauna, both indigenous and migratory to the area. Discuss ecology on a regional basis and for the site area(s). k) Water resources evaluation for area and site shall include surface water and groundwater [groundwater may be excluded for offshore projects in greater than 10 meters water depth and 5 kilometres from shore or where it has been reasonably established that groundwater is not of usable quality or is greater than 15,000 mg/l Total Dissolved Solids (TDS)]. Possible groundwater impacts due to drilling, production, injection and land surface discharges must be addressed. Degradation of surface or marine water quality or contamination or impacts on bottom must be discussed. l) Archaeological and other important anthropological or natural sites or artefacts must be identified and impacts discussed. A survey may be required to assess the importance of the site. m) Cultural impacts on local people and populations due to construction and operation of the project. n) Access to site shall detail ingress and egress to site by roads, walkways, shipping lanes, air routes or other means of access for walking, vehicles, drilling rigs, construction and other heavy equipment, marine craft and aircraft. Impacts upon transportation routes, congestion and/or required upgrading to reduce risk, emergency access and evacuation routes must be addressed. o) Supporting resources upon which demands are made but which are not part of the project site shall be addressed. This includes, but is not limited to, such things as the need for supply of electricity, potable water, irrigation water, cooling water, sewage treatment, fire fighting and police services, housing, schools, medical facilities, recreational facilities, temporary and permanent job
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 16 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
creation, roads and highways, airports, shipping lanes, port facilities, and other required local, private or government services. p) List of major equipment that emits or creates emissions, effluents or waste streams either continuously or intermittently. Include design specifications for throughput, fuel, water, or chemical consumption and wastes generated. q) List of all chemicals and materials other than laboratory chemicals and non-hazardous spare parts to be used or stored at the site. Describe storage methodologies and amount of inventory required. Are substitute chemicals or materials available that are less hazardous? Is a substitute chemical or material available that is presently being used in an ADNOC operation? Include methodology for tracking inventory and assuring employee, emergency response personnel and medical clinic personnel are knowledge of material. r) Radiation exposures including radio isotopes, x-ray equipment and sources, Naturally Occurring Radio-active Material (NORM), testing and logging sources, and other identified sources (both ionizing and non-ionizing radiation should be addressed). s) Identify all discharges associated with the project including emissions, effluents to land, surface and groundwater, solid and other waste generated at the site, and associated support resources. This shall include construction, start-up, performance and acceptance testing, normal operation, planned maintenance and turnarounds, and expected upset type conditions. Types and amounts of wastes associated with construction, demobilisation and eventual decommissioning should also be addressed in Phase I, II and III HSEIAs. Short and long term fate and effects should be addressed. All wastes to be disposed must be clearly identified, characterised and quantified with appropriate disposal technology and costs discussed. t) Fire fighting systems, equipment, water supply, appropriate foams, chemicals, suppressants, deluge systems, coatings, response needs and training requirements. u) Work environment in relation to equipment accessibility, illumination, noise, vibration, heat stress, personal protection equipment (PPE) requirements, safe havens, blast walls, breathing apparatus. v) Occupational exposures to employees and possible health threatening exposures to the neighbouring community shall be addressed. This shall include physical, chemical and biological exposures. w) Describe the operational monitors or sampling/monitoring methods proposed for Health, Safety and Environmental control and discuss data collection and management. x) Development of safety procedures, Process Safety Management (PSM) and Health, Safety and Environmental Management Systems (HSEMS).
Chalr/Rnc/18-2-97
ADNOC GROUP HEALTH, SAFETY AND ENVIRONMENT (HSE) COMMITTEE Page 17 of 0
Health, Safety and Environmental Management
Health, Safety & Environmental Impact Assessment Guidelines
Effective Date: April 15, 1997 Approved by General Manager Version: 1.0
Chalr/Rnc/18-2-97