Inspection, Testing and TracebilityDeskripsi lengkap
Deskripsi lengkap
This procedure applies to identification and traceability of material and constructed work under the responsibility of EMC and its Subcontractors at the stages of supply, and installation.
Full description
Descrição completa
Safety
Nueva norma CQI sobre Trazabilidad para el Sector de Automoción.Descripción completa
buku
In a Manufacturing Industry, be it of any scale, the entity of utmost importance is the technical data. As the quantum of the generation of such necessary data is large, it paves the way to the need of establishing a data management tool such that wo
buku
An assessment of the process by which railway rolling stock gets accepted on to the European rail network and the implications for cross-border competition Follow Colin Buchanan on twitter …Full description
TraceabilityFull description
Prerequisites from purchasers and governments to create increasingly supportable items have expanded amid late years. Regardless of whether items are certied, one cant ensure organizations meet these necessities, since no chain of occasions can check
HAZOP PlanFull description
List out Hazard Identification How to identify
010- TRACEBILITYFull description
Theme Identification of the theme or the broad area of research is the first and most important step in any research.
Descrição completa
Hazard
Hazard IdentificationFull description
hazard identificationFull description
QUALITY MANAGEMENT SYSTEM PROCEDURE
Title:
Identification and Traceability
Identification No.:
QMSP-753
Revision No.:
5
No. of effective pages:
2
Prepared by:
S.O.
Approved by:
F.H.
Issued by:
Quality Department
Revision date:
February 10 2011
th
This Quality Assurance procedure is proprietary and must not be reproduced without the written consent of the Quality Assurance Manager of AP&C
Quality Management System Procedure .
IDENTIFICATION & TRACEABILITY
QMSP-753
1.0
PURPOSE 1.1
2.0
Traceability refers to the ability to trace the history, application or location of an entity by means of recorded identification.
RESPONSIBILITIES 4.1
5.0
This procedure applies to the identification of all materials and items upon receipt and throughout all stages of production, delivery and installation, when required by the contract, to provide traceability of individual components and/or batches.
DEFINITIONS 3.1
4.0
To describe the methods employed and the personnel responsible for controlling, documenting and performing product identification and traceability, where appropriate, through all stages of production and service operations.
SCOPE 2.1
3.0
Page 1 of 2
All personnel are responsible for ensuring that product is identified and traceable as per this procedure
PROCEDURE
5.1
All materials and products must be identified (i.e. raw materials, supplies, finished products) by applicable documentation (specifications, product identifier numbers, packaging, shipping documents) during all stages from receiving raw material to product delivery as follows:
5.2
Receiving & Incoming Inspection: All purchased products pass through the AP&C receiving department, where they are received as per AP&C internal procedure-QMSP-740. The products are inspected for quantity damage and dimensional inspection when applicable prior to be processed. Any nonconforming product should be processed regarding QMSP-830 procedure.
5.3
Release of Job The Production and/or Quality Department prepare the internal work orders (IWO) and traveller which is reviewed and released by Quality Department and/or Production Manager. A traveller number is issued for each job.
Revision No.: 5
Prepared by: S.O.
Approved by: F. H.
Date: February 10th 2011
This Quality Assurance procedure is proprietary and must not be reproduced without the written consent of the Quality Assurance Manager of AP&C
Quality Management System Procedure .
IDENTIFICATION & TRACEABILITY
QMSP-753 5.4
Page 2 of 2
Production
5.4.1 Before processing any spool of wire the operator has to keep a sample from each one for further investigations or tests in case of a problem. 5.4.2 The traveller always identifies the product. Traveller includes the customer name, customer PO number, powder and description when applicable, which are taken directly from the customer Purchase order and/or Internal Work order. The traveller must also include any special customer requirements. AP&C maintains the identification of the configuration of the product in order to meet customer requirements. When processes are completed, the operations on the traveller are signed off by personnel responsible for them. 5.5
Final Inspection & Test Personnel verify the product, release all conforming lots and sign the travel card.
5.6
Shipping Personnel pack and ship the product as AP&C -QMSP-755 or customer supplied procedure.
6.0
7.0
5.7
All the documents are kept on file regarding procedure QMSP-423
5.8
FIFO A “First-In, First Out” procedure is applicable in production.
REFERENCES 6.1
QMSP-830
Control of Nonconforming Product
6.2
QMSP-740
Receiving Inspection
6.3
QMSP-423
Control of Documents
6.4
QMSP-755
Handling, Storage and Shipping
6.5
Quality Manual QM-0501 Section 7.5.3
ATTACHMENTS 7.1
QMSP-753-F2
Powder preparation
7.2
QMSP-753-F3
Traceability log - Lots
7.3
QMSP-753-F4
Traceability log - IPN
7.4
SOP-09-21-F1
Powder production
Revision No.: 5
Prepared by: S.O.
Approved by: F. H.
Date: February 10th 2011