(A joint venture company between PETRONAS Gas Berhad and NRG Consortium (Sabah) Sdn Bhd)
PROJECT MANAGEMENT CONSULTANT: KIMANIS POWER PROJECT ENGINEERING, PROCUREMENT, CONSTRUCTION AND COMMISSIONING (EPCC) FOR 300MW COMBINED CYCLE POWER PLANT CONTRACTOR:
CTCI Corporation, CTCI Overseas Corporation Limited, CTCI Malaysia Sdn Bhd, Synerlitz (Malaysia) Sdn Bhd, SCHB Engineering Services Sdn Bhd CONSORTIUM
VEN. DOCUMENT NO:
KECSB/ABB-KIMANIS/MOS/0213/04
REV. B
TITLE:
275/132KV KIMANIS SWITCHYARD ITP FOR STEEL STRUCTURE ERECTION DOCUMENT NO:
B
CHANGES IN ATTACHMENT
A
ISSUE FOR APPROVAL
Rev.
Description
KPP-000-XK91C-009-0060
REV. B
6/3/2013
ABB
20/02/2013
ABB
Date
By
Chk.
App. Page No. 1 of 5
THIS DOCUMENT CONTAINS CTCI CORPORATION CONFIDENTIAL INFORMATION OF A PROPRIETARY NATURE. THIS INFORMATION MUST NOT BE COPIED OR DISCLOSED IN WHOLE OR IN PART TO OUTSIDE PARTIES NOR USED FOR OTHER THAN THE PURPOSE FOR WHICH PROVIDED WITHOUT PERMISSION OF MANAGEMENT. 本文件所述及資料及文件皆為中鼎工程股份有限公司(中鼎)版權所有,未徵得中鼎同意不得將其中全部或部份翻印或轉授與第三者。
CONTENT
PAGE
1.0 PROPOSE
3
2.0 SCOPE
3
3.0 PROJECT DESCRIPTION
3
4.0 ACTIVITIES
4
5.0 ATTACHMENTS
5
275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION
KPP-000-XK91C-009-0060 DATE
2 OF 5
6/3/2013 REV.
B
1.0 PURPOSE The purpose of this Procedure is to define the items that must be inspected and tested during the construction and to set the Hold Points or Witness Points for certain inspection items including required examination and test, so as to ensure that the entire construction quality complies with the requirements of the contract and project specifications. 2.0 SCOPE The examination and testing items must comply with the requirements of relevant drawings, specifications and statutory codes. This inspection and test items listed in the appendixes are the most basic requirements. 3.0 PROJECT DESCRIPTION Project: Kimanis 275/33kV Consumer Main Intake Main Contractor: ABB Malaysia Sdn. Bhd. Sub Contractor: KARISMA Energy & Construction Sdn. Bhd./SKT Semarak Sdn. Bhd.
275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION
KPP-000-XK91C-009-0060 DATE
3 OF 5
6/3/2013 REV.
B
4.0 ACTIVITIES 4.1 Before starting the work, the Project Manager shall assign the Supervisor to compile the relevant document and shall submit to the Client for review, if required. 4.2 The Contractor shall prepare the inspection and test plan, using specific forms to set all hold points/witness points according to the contractual requirements, project specifications and statutory codes.
4.3 QC manager and the Site Supervisor shall review the proposed inspection and test plans and compile the relevant inspection and test items to form a complete set of Inspection and Test Plan. It should be submitted for approval.
4.4 The approved Inspection and Test Plan shall be handed over to the responsible appointed QC Manager.
INSPECTION AND TESTING PLAN FLOWCHART STEEL STRUCTURE ERECTION CHECK LIST ELEVATION OF COLUMN FOUNDATION STRUCTURE STEEL ERECTION CHECK LIST GROUT/POUR CARD PUNCH LIST QUALITY MANAGEMENT STANDARD
275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION
KPP-000-XK91C-009-0060 DATE
4 OF 5
6/3/2013 REV.
B
ATTACHMENT 1 INSPECTION AND TESTING PLAN FLOWCHART
275/132KV KIMANIS SUBSTATION METHOD OF STATEMENT STRUCTURE ERECTION