EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No: Conducted By:
Company
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
4
5
1.1 1.2 1.3 1.4
Falling objects
Serious Physical injury Damage to property
1.5 2.1 2.2 2.3
2
Preparation work, fabrication and installation of pipe spools / electrical conduit / trunking using electrical drills, bench drills, grinders, fibre cutters,
Document1
Obstructions and trip hazards
Physical injury Damage to property
1.1 1.2 1.3
Safety Coordinator / Supervisor to brief all workers regarding scope of work and potential hazards. Workers working at height to wear body harnesses and anchor appropriately. Certified Scaffold Supervisors to check and tag mobile scaffold as fit for use. Mobile scaffold components may not be modified without knowledge of the Certified Scaffold Supervisor. Only unmanned mobile scaffolds may be moved. Workers to ensure that all loose materials are kept in a toolbox or appropriate container / bag. Toolboxes / bags shall be kept away from open edges. Do not hang tools, bags and/or boxes from the handrails. Safety Coordinator / Supervisor to brief all workers regarding scope of work and potential hazards. Maintain housekeeping to keep accessways and escape routes clear. Materials and working eqipment to be stored in Page 1 of 7
9
10
11
Additional Risk Controls
RPN
Serious Bodily Injury or Fatality Damage to property
Existing Control Measures
8
Occurrence
Falls while working at height
EHS Impact
7
Risk Assessment Severity
Usage of mobile or fixed scaffold
EHS Hazards / Aspects
6
Risk Controls
Conditions
S/N 1
Activities
Next Review Date
Legality
3
Hazard Identification
B
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Last Review Date
2
Revision
References
1
PE / FP / M5.0 / EHS / RA-03
-
Y
R
5
2
10
1. Close supervision 2. Toolbox Meeting prior to start of work
PIC: Safety Coordinator or Supervisor / Certified Scaffold Supervisor
-
Y
R
3
2
8
1. Barricade work area
PIC: Safety Coordinator or Supervisor / Supervisor
-
Y
R
2
3
6
1. Toolbox Meeting prior to start of work 2. Appropriate
PIC: Safety Coordinator or Supervisor / Supervisor
Additional Control Measures
Remarks
20 September 2010
EHS R1 1.2
Ref No:
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
3
4
5
S/N
Hazard Identification
Activities
EHS Hazards / Aspects
EHS Impact
Existing Control Measures
threading machines and grooving machines. Use of mechanical lifting devices e.g. pallet jacks, lifters.
7
8
9
10
Risk Assessment
designated temporary areas.
Bodily injury
Hand / eye / face injuries
2.1 2.2 2.3 2.4 2.5 2.6
Pinch or crush injuries
Hand and body injury Damage to property
3.1 3.2 3.3 3.4
Document1
6
Risk Controls
Legality
2
Safety Coordinator / Supervisor to brief all workers regarding scope of work and potential hazards Tool operator to wear proper PPE (e.g. gloves, eye / face protection. Cover and other guards shall not be removed and/or bypassed. Spark containment shall be provided for fibre cutters. Use appropriately rated fibre cutter and grinder discs. WIP materials shall be neatly stacked and arranged. All workers shall be briefed on proper and manual lifting methods. Piping to be properly stacked on racks or spacers at least 300mm off the floor. Wedges or guards shall be placed to prevent pipes from rolling off racks. Pipes shall not be stored vertically unless suitably Page 2 of 7
B
Next Review Date
References
1
Last Review Date
RPN
Package No.
Occurrence
Hexagon Tower Sdn Bhd
Revision
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Severity
Conducted By:
Company
PE / FP / M5.0 / EHS / RA-03
Conditions
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
-
Y
R
2
3
6
-
Y
R
3
2
6
11
Additional Risk Controls
Additional Control Measures
Remarks
PPE to be worn at all times. 1. Toolbox Meeting prior to start of work
PIC: Safety Coordinator or Supervisor / Supervisor
1. Toolbox Meeting prior to start of work
PIC: Safety Coordinator or Supervisor / Supervisor
20 September 2010
EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No: Conducted By:
Company
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
4
5
3.5 3.6 3
Installation of piping / electrical conduit and trunking using ladder / mobile scaffold / scissor lift / boom lift
Falls while working at height
Serious Bodily Injury or Fatality Damage to property
1.1 1.2 1.3 1.4
Falling objects from working platforms
Document1
Physical injury Damage to property
1.5 2.1 2.2 2.3
restrained from toppling. In no case shall vertically stored pipe be taller than 1.5m. Make use of mechanical lifting devices to handle heavy pipe spools . Maximum carry load for a single person shall be 25kg. Safety Coordinator or Supervisor to brief all workers regarding scope of work and potential hazards. Workers working at height to wear body harnesses and anchor appropriately. Certified Scaffold Supervisors to check and tag mobile platform as fit for use. Mobile scaffold components may not be modified without Certified Scaffold Supervisor knowledge. Only unmanned mobile scaffolds may be moved. Workers to ensure that all loose materials are kept in a toolbox or appropriate container / bag. Toolboxes / bags shall be kept away from open edges. Do not hang tools, bags and/or boxes from the handrails. Page 3 of 7
9
10
11
Additional Risk Controls
RPN
Existing Control Measures
8
Occurrence
EHS Impact
7
Risk Assessment Severity
EHS Hazards / Aspects
6
Risk Controls
Conditions
S/N
Activities
Next Review Date
Legality
3
Hazard Identification
B
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Last Review Date
2
Revision
References
1
PE / FP / M5.0 / EHS / RA-03
Additional Control Measures
-
Y
R
5
2
10
1. Employ buddy system if using ladders
PIC: Safety Coordinator or Supervisor / Certified Scaffold Supervisor / Supervisor
-
Y
R
3
2
8
1. Barricade work area
PIC: Safety Coordinator or Supervisor / Supervisor
Remarks
20 September 2010
EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No: Conducted By:
Company
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
4
5
3.1 3.2 3.3 3.4
3.5
4
Installation of piping – precommissioning and pressure testing
Pipe or flexible hose dislocation due to improper jointing
Minor bodily injury Damage to property
1.1 1.2 1.3 1.4
Document1
All workers / lift operators shall be briefed on proper usage of lifts. Chain blocks shall be adequately rated for load to be lifted. Attach chain blocks to designated loading points only. Always ensure that SWL limits are complied to. Avoid overloading of boom or scissor lifts by excessive materials or workers. Ensure that mobile platforms are levelled to manufacturer recommendations before extending Supervisor or Engineer to conduct line walk prior to introduction of test media. Appropriate warning signages to be posted at appropriate locations within the test area. Pressure test station to be barricaded to prevent tampering or unauthorized operation. To follow Method Statement for Pressure Testing per Approved ITP
Page 4 of 7
9
10
11
Additional Risk Controls
RPN
Serious Bodily Injury Damage to property
Existing Control Measures
8
Occurrence
Mechanical failure of mobile platform / lift / chain block
EHS Impact
7
Risk Assessment Severity
EHS Hazards / Aspects
6
Risk Controls
Conditions
S/N
Activities
Next Review Date
Legality
3
Hazard Identification
B
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Last Review Date
2
Revision
References
1
PE / FP / M5.0 / EHS / RA-03
-
Y
R
4
2
8
1. All lifting equipment shall be inspected. 2. Banksman required when moving
PIC: Safety Coordinator or Supervisor / Supervisor
-
N
N R
1
3
3
1. Close supervision required. 2. Deploy sufficient manpower
PIC: Engineer / Supervisor
Additional Control Measures
Remarks
20 September 2010
EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No: Conducted By:
Company
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
Last Review Date
4
5
EHS Impact
Trip hazard due to cables / wiring on ground
Bodily injury
Electrical hazards from electrical tools
Bodily injury Damage to property
Existing Control Measures
1.1 1.2
2.1 2.2 2.3
Electrocution 2.4 2.5
Document1
Ensure cable management is practiced for temporary supply cabling. All excess wire / cable shall be neatly coiled and hung or supported away from access-ways and exits Supervisor to check and verify that tools are fit for use and colour coded appropriately. All plugs and sockets shall be industrial grade. Extension and lead wiring shall be in good working condition. Temporary cabling shall be elevated. ELCB’s shall be used on sub-distribution outlets.
Page 5 of 7
8
9
10
11
Additional Risk Controls
RPN
Usage of electrical tools e.g. electrical drills, grinders and fibre cutter.
EHS Hazards / Aspects
7
Risk Assessment Occurrence
5
Activities
6
Risk Controls
Severity
S/N
Hazard Identification
Conditions
3
Next Review Date
Legality
2
B
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
References
1
Revision
PE / FP / M5.0 / EHS / RA-03
-
Y
R
2
3
6
NIL
PIC: Safety Coordinator or Supervisor / Supervisor
-
Y
R
5
1
5
NIL
PIC: Safety Coordinator / Supervisor / LEW
Additional Control Measures
Remarks
20 September 2010
EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No: Conducted By:
Company
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
Acknowledged By
(Names, Designations)
PE / FP / M5.0 / EHS / RA-03
Revision
B
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Last Review Date
Next Review Date
Severity Classification Table NO
SEVERITY CLASS
5
Catastrophic
4
Major
3
Serious
2
Minor
1
Insignificant
PERSONNEL
ORGANIZATION
ENVIRONMENT
Any event that leads to eventual death.
Shut down of Project Office / Project(s)
Major pollution affecting the public and adjacent property
Serious injury resulting permanent disability
Suspension of essential services and departments / affected area of projects.
Major legal non-compliance.
Hospitalisation (>24hrs), no permanent disability
Suspension of non- essential services and departments/ affected area of projects.
Departmental/Project pollution
Light injury, requiring outpatient treatment with no follow up, Temporary, minor interruption <3 days of medical leave
Pollution limited to localized area
Superficial injury requiring basic first aid, no medication required
No significant pollution.
No disruption
Occurrence Classification Table NO
IMPACT
FREQUENCY
5
Frequent
Daily Occurrence
4
Likely
Weekly Occurrence
3
Occasionally
Monthly Occurrence
2
Unlikely
Yearly Occurence
1
Remote
Less than once in three years
Risk Level Matrix Document1
Page 6 of 7
20 September 2010
EHS R1 1.2
ENVIRONMENTAL, HEALTH AND SAFETY (EHS) HAZARD / RISK ASSESSMENT
Ref No:
Hexagon Tower Sdn Bhd
Package No.
M5.0 Fire Protection Services
Process / Location
General System Installation
Date Conducted
Approved By
Rick Low, Project Manager (Hexagon Tower)
Reviewed By:
(Names, Designations)
Acknowledged By
B
Revision
Rick Low (Project Manager) Tan Yiing Yee (Contractor PM) Shan (WSHC)
Conducted By:
Company
PE / FP / M5.0 / EHS / RA-03
Last Review Date
Next Review Date
LIKELIHOOD
SEVERITY Insignificant (1)
Minor (2)
Serious (3)
Major (4)
Catastrophic (5)
Frequent (5)
Medium (5)
Likely (4)
Medium (4)
Medium (10)
High (15)
Extreme (20)
Extreme (25)
Medium (8)
Medium (12)
High (16)
Extreme (20)
Occasionally (3)
Medium (3)
Medium (6)
Medium (9)
Medium (12)
High (15)
Unlikely (2)
Low (2)
Medium (4)
Medium (6)
Medium (8)
Medium (10)
Remote (1)
Low (1)
Low (2)
Medium (3)
Medium (4)
Medium (5)
Risk Level Recommended Action Table
Document1
RISK LEVEL
ACCEPTABILITY OF RISK
RECOMMENDED ACTION
LOW
Acceptable
No additional risk control measures required. Frequent review may be required to ensure that the assigned risk level remains appropriate.
MEDIUM
Moderately Acceptable
Careful assessment of the hazards involved should be carried out to reduce the risk level as far as practicable within a defined period of time (typically the time taken to perform a specific activity). Additional interim risk control measures may be required.
HIGH
Unacceptable
Risk level shall be reduced to at least Medium Risk Level prior to commencement of work by removing the risk factors (preferred) or implementation of additional control measures. Any such measures shall not overly rely on PPE or appliances. Management intervention is required.
EXTREME
Unacceptable
Work may NOT proceed until risk level is reduced to Medium or lower. A detailed action plan and management involvement is required.
Page 7 of 7
20 September 2010