INSPECTION TEST PLAN Construction of U/G Water Tanks and Dewatering System
INSPECTION AND TEST PLAN for Construction of U/G Water Tanks and Dewatering System Work area: Between Buildings Re f no Description
1
2
3
Shop Drawing
Method of Statement
Material Approval
Inspection by Type of Verification
Document Review
Stage/ frequency
Before start work
Document Review
Before start work
Visual Inspection
Material Arrival on Site
Code / Spec / etc
Project Specification, GEN/SD-OS/0031-00, TYP/SD-ST/070401/110-00 MS Rev 03 PSS, Div 02 , Sec 02240/02300,Div 03, Sec 03300 PSS, Div 02 , Sec 02240/02300,Div 03, Sec 03300 & ACI 117
Acceptance criteria SC
Verifying Documents
CON TPI
ENG
Code A/B
N/A
H
N/A
R
Approved Submittals
Code A/B
N/A
H
N/A
R
Approved Submittals
As per approved Material Submittals Code A/B
N/A
H
N/A
S
Material Delivery Note, MDS
Trench Excavation 1
Verification on Exact Location
Visual Inspection
Before start application
Complying with PSS, Div 02 , sec 02300 Approved drawing
N/A
H
N/A
S
Checklist
2
Area & Proper Visual Equipment Inspection Preparation
Before start application
Complying PSS, Div 02 , sec 02300 with N/A Specification
H
N/A
S
Checklist
Setting out, to Survey be excavated Review Points
Before start application
Survey Report PSS, Div 02 , sec 02300 according to N/A Approved drawings
H
N/A
S
Checklist
3
Verifying Exact Depth Survey coordinating Review with approved level
Survey Report Periodically Record according to N/A by Surveyor PSS, Div 02 , sec 02300 Approved drawings
H
N/A
W
IR, Checklist
4
Conforming for Proper Trench Slope
During & After Application
N/A
H
N/A
S
Checklist
Before start application
Survey Report PSS, Div 02 , sec 02300 according to N/A Approved drawings
H
N/A
S
Checklist
Periodically
Survey Report according to N/A PSS, Div 02 , sec 02300 Approved drawings
H
N/A
S
Checklist
Visual Inspection
PSS, Div 02 , sec 02300
Approved drawings
Dewatering System
1
Identification and marking for minor trench location
2
Excavated Level at nominated depth
Page 1 of 7
Survey Review
Survey Review
UGW/COM/ITP-001/Rev:00
3
Identification proper location for Sump pit
Survey Review
H
N/A
S
Checklist
Periodically
Survey Report according to N/A PSS, Div 02 , sec 02300 Approved drawings
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
Approved PSS, Div 02 , sec 02240 drawings
N/A
H
N/A
S
Checklist
Approved PSS, Div 02 , sec 02240 drawings
N/A
H
N/A
S
Checklist
Survey Report PSS, Div 02 , sec 02240 according to N/A Approved drawings
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
4
Depth Level Verification
5
Conforming Specific Diameter Perforated Visual Pipe and Inspection Wrapped with Proper Geotextile Material
Pre-Works
6
The Pipe Setting on Selected Aggregated bed
Visual Inspection
During Process
7
Conforming the Aggregate Visual bed layer Inspection thickness
During Process
8
Proper Slope Verification & Survey Gravity Review Drains into sump point
During Work Process
9
Conforming Back fill the trench channel Visual with the Inspection selected aggregate
After Process
Verifying proper capacity 10 generator pump and suitable outlet & Inlet pipes
Survey Review
Before Excavation
Survey Report PSS, Div 02 , sec 02300 according to N/A Approved drawings
Approved drawings & PSS, Div 02 , sec 02240 Approved Material
Approved PSS, Div 02 , sec 02300 drawings
Material data sheet & approved PSS, Div 02 , sec 02240 MS with Calculation
Visual Inspection
Pre-Process
Conforming proper located Visual 11 lagoon Inspection preparation
Pre-Process
Approved PSS, Div 02 , sec 02240 MS
N/A
H
N/A
S
Checklist
Verification of pumping, Visual 12 properly Inspection directed to lagoon
During Process
Approved PSS, Div 02 , sec 02240 MS
N/A
H
N/A
S
Checklist
Ground Water Visual Level Stability Inspection
Every 3 Hours
Approved PSS, Div 02 , sec 02240 MS
N/A
H
N/A
S
Checklist
13
Under Ground Water Tank & Pump Room Construction Ground Basement Preparation
Page 2 of 7
UGW/COM/ITP-001/Rev:00
1
50 cm stones layer Levelling and Compaction
Test Review
2
20 cm gravel filter layer Levelling and Compaction
3
5 cm Blinding Visual Concrete Pour Inspection
Test Review
After Process
After Application
After pouring
Approved MS, maximum PSS, Div 02 , sec 02300
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
Approved PSS, Div 03 , sec 03300 drawings
N/A
H
N/A
S
Checklist
Approved PSS, Div 03 , sec 03300 drawings
N/A
H
N/A
W
IR, Checklist
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
S
Checklist
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
W
IR, Checklist
6” sized
stone material Approved MS, PSS, Div 02 , sec 02300 maximum 20 mm size Approved PSS, Div 03 , sec 03300 MS
Water Proofing System for Foundation
1
Bituminous Primer Coat
2
Bituminous Membrane & Conforming proper overlapping
Visual Inspection
Visual Inspection
After Application
During & After Application
3
Geotextile Layer
Visual Inspection
After Application
4
Protection Screed Layer (5 cm)
Visual Inspection
After Application
Approved drawing & material PSS, Div 07 , sec 07135 specificatio n Approved drawing & material PSS, Div 07 , sec 07135 specificatio n Approved drawing & material PSS, Div 03 , sec 03300 specificatio n Approved drawing & PSS, Div 03 , sec 03300 MS
Water Tank & Pump Room Foundation
Visual Inspection & After Survey Process Review
1
Setting out & Positioned of Formwork
2
Verification of Visual Proper Spacer Inspection
After Process
3
Rebar Fabrication and Fixed Correct Position
Visual Inspection
After Process
4
Concrete Sampling
Test Review
During Process
5
Concrete Visual Pouring & Inspection Consolidating
Page 3 of 7
During Process
Survey Report according PSS, Div 03 , sec 03300 to Approved drawings
UGW/COM/ITP-001/Rev:00
6
7
Verification the application of approved Visual water stopper Inspection at construction joint
Curing
Visual Inspection
After Process
During Process
Approved MS, PSS & Material PSS, Div 07 , sec 07135 Specificatio n PSS, Material PSS, Div 03 , sec 03300 Specificatio n
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
H
IR, Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
RC Wall (Shear Wall) Construction
1
Rebar Fabrication Visual and Fixed Inspection Correct Dowel Position
After Process
Approved IR Drawing, PSS, Div 03 , sec 03300 PSS
2
PreEngineered Panels positioned correctly as form
Visual Inspection
After Process
Approved Record Drawing, PSS, Div 03 , sec 03300 PSS
3
Verifying Spacers in proper
Visual Inspection
After Formed
Approved Record Drawing, PSS, Div 03 , sec 03300 PSS
4
Concrete Sampling
Test Review
During Process
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
S
Checklist
5
Concrete Pouring & Verifying Visual proper Inspection Consolidation process
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
6
Deforming & Curing
Visual Inspection
During Process
After Process
PSS, Material PSS, Div 03 , sec 03300 Specificatio n
Water Tank & Pump Room Slab Construction
Visual Inspection & After Survey Process Review
1
Formwork Construction
2
Verification of Two Opening Visual as per Inspection Approved Drawing
3
Verification of Visual Proper Spacer Inspection
Page 4 of 7
Survey Report according PSS, Div 03 , sec 03300 to Approved drawings
After Process
Approved PSS, Div 03 , sec 03300 Drawing
After Formed
Approved Drawing, PSS, Div 03 , sec 03300 PSS
UGW/COM/ITP-001/Rev:00
4
Rebar Fabrication and Fixed Correct Position
Visual Inspection
After Process
Approved Drawing, PSS, Div 03 , sec 03300 PSS
5
Concrete Sampling
Test Review
During Process
6
Concrete Visual Pouring & Inspection Consolidating
During Process
7
Curing
Visual Inspection
During Process
N/A
H
N/A
W
IR, Checklist
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
S
Checklist
Approved PSS, Div 03 , sec 03300 MS, PSS
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
Material PSS, Div 07 , sec 07135 Data Sheet
N/A
H
N/A
S
Checklist
Material PSS, Div 07 , sec 07135 Data Sheet
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
PSS, Material PSS, Div 03 , sec 03300 Specificatio n
Waterproofing System on Interior Concrete Surfaces
1
Substrate Preparation
Visual Inspection
PreApplication
2
Waterproofing Visual Material Inspection Preparation
During Application
3
Selected Visual Waterproofing Inspection Liquid coat
After Application
4
Curing
Visual Inspection
During Process
PSS, Div 07 , sec 07135
MS
Material Data Sheet PSS, Div 07 , sec 07135 & MS
Waterproofing System on Exterior Concrete Surfaces
1
Substrate Preparation
Visual Inspection
PreApplication
2
Bituminous Primer Coat
Visual Inspection
After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
3
Bituminous double Sheet Membrane & Conforming proper overlapping
Visual Inspection
During & After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
4
Conforming Proper Hardboard Protection
Visual Inspection
After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
5
Backfilling and Compaction
Test Review
During & After Process
PSS, Div 07 , sec 07135
MS
approved PSS, Div 02 , sec 02300 MS, PSS
Interior Tiling System for Water Tank (Basement)
1
Waterproofed Surface Preparation
Visual Inspection
PreApplication
PSS, Div 03 , sec 03300
2
Concrete Layer Application
Visual Inspection
After Application
PSS, Div 03 , sec 03300
Page 5 of 7
MS
MS
UGW/COM/ITP-001/Rev:00
approved drawing, PSS, Div 03 , sec 03300 survey report
3
5 to 13 cm Slope Verification
Survey review
After Application
4
Approved Adhesive Preparation
Visual Inspection
During Process
Material Data Sheet PSS, Div 09 , sec 09310 & MS
5
Adhesive Application
Visual Inspection
During Process
Material Data Sheet PSS, Div 09 , sec 09310 & MS
6
Ceramic Tile Selection & Installation
Visual Inspection
After Installation
Approved drawing, Material PSS, Div 09 , sec 09310 Data Sheet & MS
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR,Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR,Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
Interior Tiling System for Water Tank (Wall & Roof Slab)
1
Waterproofed Surface Preparation
Visual Inspection
PreApplication
Material Data Sheet PSS, Div 09 , sec 09310 & MS
2
Approved Adhesive Preparation
Visual Inspection
During Process
Material Data Sheet PSS, Div 09 , sec 09310 & MS
3
Adhesive Application
Visual Inspection
During Process
Material Data Sheet PSS, Div 09 , sec 09310 & MS
4
Ceramic Tile Selection & Installation
MS, Technical After Data Sheet & Installation Drawing
Approved drawing, Material PSS, Div 09 , sec 09310 Data Sheet & MS
Upper Surface Protection of Roof Deck
1
Substrate Preparation
Visual Inspection
PreApplication
Material Data Sheet PSS, Div 02 , sec 02741 & MS
2
Bituminous Primer Coat
Visual Inspection
After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
3
Bituminous double Sheet Membrane & Conforming proper overlapping
Visual Inspection
During & After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
4
Covering with Visual Geotextile Inspection Material
After Application
Material Data Sheet PSS, Div 07 , sec 07135 & MS
5
Protection Visual Screed Application (5 Inspection cm)
After Application
Page 6 of 7
PSS, Div 03 , sec 03300
PSS
UGW/COM/ITP-001/Rev:00
6
Selected Aggregate Visual Base Coase (8 Inspection cm)
After Application
PSS, Div 03 , sec 03300
7
Asphalt Visual Concrete Base Inspection Coarse (7cm)
After Application
PSS, Div 02 , sec 02741
8
Asphalt Concrete Finish Coarse Application (4cm)
After Application
PSS, Div 02 , sec 02741
Visual Inspection
SC : Sub Contructor TPI : Third Party Inspection
CON: Main Contractor IR : Inspection Request
PSS
PSS
PSS
N/A
H
N/A
S
Checklist
N/A
H
N/A
S
Checklist
N/A
H
N/A
W
IR, Checklist
ENG: Consultant Engineer N/A : Non-applicable
PSS : Pro ject Standard Specification S : Surveillance; Random attandance on site, no Written Confirmation is need. W : Witness Point; Attandance on site is expected, the signature is required on check sheet of IR and Checklist, but if the signatory is not present to sign at the time, follow on work may proceed and the document(s) to be signed later. (Written notification is needed) H : Hols Point; Attendance on site is required and Written confirmation is needed, contractor may not proceed if written confirmation is not available. R : Document Review; Review means Review doc ument, which includes of material test certificates, test reports, records, MS, and etc.
Page 7 of 7
UGW/COM/ITP-001/Rev:00